Decision The Policy and Resources Committee – 1. noted the revenue budget monitoring report as at 30 June 2025; 2. noted the capital plan monitoring report as at Quarter 1 and approved the proposed budget changes to the Capital Plan outlined in paragraphs 4.3 to 4.6 of that report; 3. noted the 2025-26 financial risks report; and 4. noted the reserves and balances report as at 30 June 2025. (Reference: Report by Section 95 Officer dated 30 July 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
FINANCIAL SERVICES 21 AUGUST 2025
FINANCIAL MONITORING OVERVIEW – 30 JUNE 2025
1. INTRODUCTION
1.1This report provides a summary of the overall financial position of the council for 2025-26 as at 30 June 2025. It outlines the key highlights from the detailed financial monitoring reports in respect of the following:
• Revenue Budget; • Capital Plan; • Financial Risks; and • Reserves and Balances.
2. DETAIL
2.1Revenue Budget Monitoring Report
2.1.1 This report provides a summary of the actual and forecast outturn expenditure and income of the council in comparison to the approved 2025-26 revenue budget.
2.1.2 At this stage, there are no changes to the budget approved by Council in February 2025, and there are no budget virements over £200k, requiring committee approval.
2.1.3 As at 30 June 2025, there is a forecast underspend of £0.500m on the approved budget for the year. This underspend is in respect of a forecast over-recovery of Council Tax income of £0.500m. At this stage, there are no forecast variances in respect of services net expenditure.
2.1.4 It is anticipated that savings in debt interest costs will be achieved during the year, providing an opportunity to redirect resources to future council priorities. At this stage, it is deemed prudent to assume no variance in the 2025-26 forecast outturn position.
2.1.5 There is an overspend of £2.950m on the profiled budget to date. However, these variances mainly relate to the actual timing of income and expenditure, and the recharging of costs to capital, in comparison to assumed budget profiles. The main focus of budget monitoring is the forecast outturn position.
2.1.6 The 2025-26 approved budget savings options, to be achieved in 2025-26, total £2.762m. There are 15 savings options impacting 2025-26, of which 7 have been delivered (£1.342m), a further 7 are on track to be delivered (£1.220m) and 1 is under development (£0.200m). The delivery of approved savings options will continue to be monitored throughout the year. 2.1.7 The 2025-26 HSCP forecast outturn position in respect of Social Work services as at 30 June 2025 is an overspend of £0.258m. However, this is expected to be managed from within HSCP reserves, with no impact on the council’s financial position.
2.2Capital Plan Monitoring Report
2.2.1 This report provides an update on financial performance and the delivery of capital projects against the approved capital plan budget resources and timescales as at Quarter 1, 30 June 2025.
2.2.2 A number of budget changes are proposed to reflect additional capital resources totalling £17.194m, approved by Council in February 2025; and in respect of additional resources totalling £1.500m, confirmed during the quarter. Previously reported project slippage from 2024-25 totalling £22.035m has been carried forward into the new plan. In addition, projects completed as at 31 March 2025 have been removed from the plan.
2.2.3 Approved gross expenditure on the capital plan, excluding spend incurred in prior years, totals £210.272m, while project specific income, excluding amounts accounted for in prior years, totals £12.243m. This gives approved net expenditure of £198.029m to be incurred across 2025-26 and future years.
2.2.4 Forecast gross expenditure and project specific income, taking account of budget changes, have been profiled across 2025-26, 2026-27 and future years. The resulting forecast gross expenditure profile as at Quarter 1 is £75.384m 2025-26, £63.546m 2026-27 and £71.522m future years, while forecast project specific income is profiled £12.243m 2025-26. The profile of forecast expenditure will be reviewed and updated throughout the year, with an explanation of future movements reported to committee.
2.2.5 Actual gross expenditure of £6.725m has been incurred during the first quarter of 2025-26, representing 8.9% of the £75.384m gross expenditure forecast for the year. No project specific income has been received during the quarter.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.