FINANCIAL MONITORING OVERVIEW – 31 DECEMBER 2025

Approved Committee 1 paper

AI summaryArgyll and Bute Council's Policy and Resources Committee approved capital plan budget changes and noted quarter three financial monitoring reports showing a forecast overall revenue overspend of £0.627m as at 31 December 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital plan changes approved, revenue and risk reports noted
Money£0.627m forecast overspend0.2% of £336.928m revenue budget for 2025-26
What happens nextOngoing monitoringPosition to be reviewed throughout 2025-26
Who it affectsCouncil services and residentsAll directorates and council tax payers

What was decided

The committee approved the budget changes in Section 4 of the Capital Plan Monitoring report. Report P2

The committee noted the 2025-26 Revenue Budget Monitoring, Financial Risks, and Reserves and Balances reports as at 31 December 2025, and the Capital Plan Monitoring report at Quarter 3. Report P3

The committee noted there were no virements requiring approval for this reporting period. Report P4

Why

The reports provide the regular quarterly financial performance update against the approved 2025-26 budget, with the revenue net expenditure budget having increased by £2.552m since last reporting. Report 1.1, 1.2, 3.1

The pay award for SJC and Chief Officers was agreed at 4% and for teachers at 4% from 1 August 2025, with the assumption that the additional cost will be fully funded by Scottish Government grant. Report 1.3, 3.3

The HSCP is forecasting an overspend of £0.416m for Social Work services which, if not managed from HSCP reserves, would require an additional unbudgeted council contribution. Report 1.8, 4.5, P42, P43

What happens next

The financial position will continue to be monitored and reviewed on an ongoing basis, with regular updates reported to committee throughout the year. Report 1.5, P31

A review of the Loans Fund and projected debt position is being progressed under the wider capital arrangements review, with a report to members later in the year. Report 4.3, P35

Progress on delivery of approved savings totalling £2.762m will continue to be monitored, with 8 options delivered and 7 on track as at 31 December 2025. Report 1.7, 4.7, P47

The money

  • £0.627m Overall forecast revenue overspend for 2025-26 (0.2% of budget) Report 1.4, 4.1, P29
  • £0.927m Forecast net overspend across council services Report 1.4, 4.1, P29
  • £0.300m Forecast over-recovery of Council Tax income (0.4% of £70.204m) Report 1.4, 4.4, P39
  • £336.928m Revised 2025-26 revenue net expenditure budget Report 1.2, 3.1
  • £2.552m Increase to net expenditure budget since last reporting Report 1.2, 3.1
  • £1.713m Cost of additional 1% pay award above original budget Report 1.2, 3.1
  • £0.839m Amounts drawn down from earmarked reserve balances Report 1.2, 3.1
  • £1.541m Forecast overspend within Executive Directorate (Kirsty Flanagan), mainly ferry berthing income under-recovery Report 1.5, 4.2, P32, P135
  • £0.281m Forecast underspend within Executive Directorate (Douglas Hendry) Report 1.5, 4.2, P31
  • £0.333m Forecast underspend across Central budgets Report 1.5, 4.2, P31, P33
  • £0.416m HSCP forecast overspend for Social Work services in 2025-26 Report 1.8, 4.5, P43
  • £222.565m Actual services net expenditure to 31 December 2025 Report 4.6, P45
  • £2.762m Total approved revenue budget savings for 2025-26 Report 1.7, 4.7, P47

Options considered

  • Chosen: Approve budget changes in Capital Plan Monitoring report. Reflects changes since last reporting period Report P2
  • Chosen: Note Revenue Budget Monitoring, Financial Risks, and Reserves and Balances reports. Standing quarterly scrutiny of financial position Report P3
  • Rejected: Virements requiring approval. No virements requiring approval for this reporting period Report 3.2, P4

Implications

  • Financial: An overall forecast revenue overspend of £0.627m is reported for 2025-26, against a revised budget of £336.928m. Report 1.4, 4.1, P29
  • Risk: The HSCP Social Work overspend of £0.416m is described as a significant financial risk to the council if not managed from HSCP reserves. Report 1.8, P43
  • Financial: Council Tax income projections carry uncertainty due to potential appeals on reclassification of self-catering units as domestic dwellings. Report 4.4, P40
  • Financial: Anticipated savings in debt interest costs during 2025-26 may be redirected to future council priorities including the 2026-27 budget gap, with no impact on the 2025-26 revenue position assumed at this stage. Report 1.6, 4.3, P35

Who and where

  • Executive Directorate (Kirsty Flanagan) services, particularly Roads and Infrastructure Services due to ferry berthing income under-recovery Report 4.2, P32, P135
  • Education services, including Schools Residential placements and 100 Day Promise funding Report P105, P118
  • Waste Management services subject to market volatility and legislative change Report P145
  • Council tax payers in Argyll and Bute Report 4.4, P37
  • Health and Social Care Partnership partners Report 4.5, P42

Timeline

  • 31 December 2025: Date of the financial position reported Report 1.1, P10
  • 27 January 2026: Date of the Section 95 Officer's report Report P7
  • 19 February 2026: Date of the Policy and Resources Committee meeting Report P9

Plain English for the jargon

  • Virement: The process of transferring budget between cost centres, services or departments; member approval required over £200k.
  • HSCP: Health and Social Care Partnership, a joint arrangement with NHS Highland for integrated health and social care services.
  • Loans Fund: The council's fund for managing borrowing and debt interest costs related to capital investment.
  • Section 95 Officer: The council's chief finance officer with statutory responsibility for proper administration of financial affairs.
  • Earmarked reserves: Balances set aside for specific purposes, drawn down to fund known commitments.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Decision The Policy and Resources Committee – 1. approved the budget changes in Section 4 of the Capital Plan Monitoring report; 2. noted the contents of the 2025-26 Revenue Budget Monitoring, Financial Risks, and Reserves and Balances reports as at 31 December 2025 and Capital Plan Monitoring report as at Quarter 3, 31 December 2025; and 3. noted there were no Virements requiring approval for this reporting period. (Report by Section 95 Officer dated 27 January 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE

FINANCIAL SERVICES 19 FEBRUARY 2026

FINANCIAL MONITORING OVERVIEW – 31 DECEMBER 2025

1. INTRODUCTION

1.1This report provides a summary of the overall financial position of the council for 2025-26 as at 31 December 2025. It outlines the key highlights from the detailed financial monitoring reports in respect of the following:

• Revenue Budget; • Capital Plan (Quarter 3, 31 December 2025); • Financial Risks; and • Reserves and Balances.

2. DETAIL

2.1Revenue Budget

2.1.1 This report provides a summary of the actual and forecast outturn expenditure and income of the council in comparison to the approved 2025-26 revenue budget.

2.1.2 Since last reporting, the net expenditure budget has increased by £2.552m to reflect the additional 1% pay award above original budget (£1.713m) and amounts drawn down from earmarked reserve balances (£0.839m). The revised 2025-26 revenue net expenditure budget now totals £336.928m. There are no virements requiring approval since the last reporting period.

2.1.3 The budget has been updated to reflect the recently approved pay awards for SJC and Chief Officers, and Teachers with the assumption that this will be funded in full through additional Scottish Government funding, with no impact on the financial position of the council in 2025-26.

2.1.4 As at 31 December 2025, there is an overall forecast overspend of £0.627m on the approved revenue budget for the year. This overspend is in respect of a net overspend of £0.927m across council services, offset by a forecast over-recovery of Council Tax income, estimated at £0.300m.

2.1.5 It is anticipated that savings in debt interest costs will be achieved during the year, providing an opportunity to redirect resources to future council priorities, including the forecast 2026-27 budget gap. At this stage, it is deemed prudent to assume no variance in the 2025-26 forecast outturn position in this respect.

2.1.6 The 2025-26 approved budget savings options, to be achieved in 2025-26, total £2.762m. There are 15 savings options impacting 2025-26, of which 8 have been delivered (£1.375m), with the remaining 7 on track to be delivered (£1.387m). Progress on the delivery of approved savings options will continue to be monitored throughout the year.

2.1.7 The 2025-26 HSCP forecast outturn position in respect of Social Work services as at 31 December 2025 is an overspend of £0.416m. However, the HSCP expect this to be managed from within available HSCP reserves, with no impact on the council’s forecast financial position. This represents a significant financial risk to the council that will continue to be monitored on an ongoing basis throughout the year.

2.2Capital Plan

2.2.1 This report provides an update on financial performance and the delivery of capital projects against the approved Capital Plan budget and timescales as at Quarter 3 (31 December 2025) 2025-26.

2.2.2 A number of budget changes totalling £8.930m in respect of gross expenditure are proposed, comprising previously approved investment totalling £8.358m (£8.000m Learning Estate Investment Strategy - Provision and £0.358m Mull Joint Campus – Balance of Development Costs Provision) and notified additional funding totalling £0.747m, offset by a reduction of £0.175m to correct an overstatement of Nature Restoration Fund available resources.

2.2.3 Approved gross expenditure on the capital plan, excluding spend incurred in prior years, totals £221.054m, while project specific income, excluding amounts accounted for in prior years, totals £12.596m. This gives approved net expenditure of £208.458m to be incurred across 2025-26 and future years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FINANCIAL MONITORING OVERVIEW: 31 DECEMBER 2025Report 1.3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 19 attended
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Math Campbell-SturgessMember, present
AF
Councillor Audrey ForrestMember, apologies
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
MI
Councillor Mark IrvineMember, absent
RK
Councillor Reeni Kennedy-BoyleMember, present
JL
Councillor Jim LynchChair, present

All 19 on the meeting page

On this subject at Argyll and Bute

Search all
  1. FINANCIAL MONITORING OVERVIEW – 31 DECEMBER 2025This decision
  2. Financial monitoring overview – 30 june 2026Agreed
  3. Financial monitoring overview - 31 october 2025Approved
  4. Financial monitoring overview - 31 august 2025Approved
  5. Financial monitoring overview - 30 june 2025Noted
  6. Financial reports monitoring pack - 31 december 2024Agreed

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies