STORM EOWYN - ESTIMATE OF COST UPDATE

Noted Committee 1 paper

AI summaryArgyll and Bute Policy and Resources Committee notes updated Storm Eowyn cost estimates, with total estimated spend rising by £233,000 to £4.185 million and a £0.244 million funding surplus still to allocate.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFive points noted, including final report to follow
Money£4.185m estimated total costUp £233,000 from June 2025 figure
What happens nextFinal report back to committeeOnce remaining cost estimates are confirmed
Who it affectsLive Argyll and Helensburgh Leisure CentreSupport extended by further six months

What was decided

The Committee noted updated cost estimates for Storm Eowyn and that some estimates remain unknown pending officer assessment. Report P2

The Committee noted the change in estimated Live Argyll support cost linked to the delayed reopening of Helensburgh Leisure Centre. Report P10

The Committee noted that current cost estimates sit within previously agreed funding, and that a final report will return to committee in due course. Report P2

Why

Storm Eowyn struck on 24 January 2025 with winds up to 100 mph, damaging roads, sea walls, harbour facilities and Council property, most significantly Helensburgh Leisure Centre. Report P4

Repair complexities and further surveys at Helensburgh Leisure Centre mean its reopening is likely delayed, extending the need for Live Argyll financial support. Report P10

What happens next

Officers will continue assessing outstanding cost estimates, including Helensburgh Waterfront, and review the Helensburgh Leisure Centre repair programme. Report P10, P13, P14

Any remaining funding surplus after final costs are known is recommended to be returned to the Unallocated General Fund. Report P20

A final report will be brought back to committee in due course. Report P2

The money

  • £352,898 Initial Bellwin Scheme claim submitted 24 May 2025 Report P6
  • £337,138 Final Bellwin Scheme claim submitted 24 September 2025 Report P6
  • £303,424 Bellwin payment received, equivalent to 90% of final claim Report P7
  • £0.455m Original estimated cost of £65k per month support to Live Argyll for seven months Report P9
  • £0.390m Increase in Live Argyll support cost from six month extension Report P10
  • £0.845m Revised estimated cost of Live Argyll support Report P10
  • £0.100m Maximum Live Argyll redundancy earmarked reserve agreed Report P9, P11
  • £4.185m Total estimated Storm Eowyn expenditure at January 2026 Report P14
  • £4.092m Total funding identified by Council and EDI Committee Report P17
  • £0.244m Estimated surplus on storm funding at January 2026 Report P18, P20, 4.2

Options considered

  • Chosen: Extend Live Argyll £65k per month support by a further 6 months. Helensburgh Leisure Centre reopening likely delayed due to repair complexities and further surveys Report P10
  • Chosen: Return any remaining surplus to the Unallocated General Fund once final costs are known. Recommended once all storm costs are finalised Report P20

Implications

  • Financial: Estimated £0.244m surplus on storm funding, but further costs are likely, particularly for Helensburgh Leisure Centre. Report 4.2, P20
  • Staffing: Live Argyll's cost reduction plan has had staffing implications; redundancy costs not yet finalised but capped at £0.100m. Report P11
  • Risk: Significant risk of future weather events affecting Council property and infrastructure, and risk that estimated costs could increase.
  • Climate: Storm impact likely linked to climate change, highlighting need for further adaptation and significant investment to improve infrastructure resilience.

Who and where

  • Live Argyll Report P9, P10
  • Users of Helensburgh Leisure Centre Report P4, P10
  • Roads, sea walls and harbour infrastructure across Argyll and Bute Report P4
  • Council taxpayers and the Unallocated General Fund Report P20

Timeline

  • 24 January 2025: Storm Eowyn struck Argyll and Bute with winds up to 100 mph Report P4
  • 24 May 2025: Initial Bellwin Scheme claim of £352,898 submitted to the Scottish Executive Report P6
  • 26 June 2025: Council agreed financial assistance to Live Argyll and identified earmarked reserve Report P6, P9
  • 24 September 2025: Final Bellwin Scheme claim of £337,138 submitted to the Scottish Government Report P6
  • 12 January 2026: Section 95 Officer's report dated Report P25
  • 19 February 2026: Policy and Resources Committee noted updated cost estimates

Plain English for the jargon

  • Bellwin Scheme: A Scottish Government scheme that provides financial support to local authorities for emergency costs from major incidents such as severe storms.
  • Live Argyll: An arms-length organisation linked to the Council that operates leisure and related services, including Helensburgh Leisure Centre.
  • Section 95 Officer: The Council's chief finance officer with statutory responsibility for the proper administration of its financial affairs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

Decision The Policy and Resources Committee noted – 1. the updated cost estimates in respect of Storm Eowyn; 2. that some cost estimates remain unknown and were subject to ongoing assessment by the relevant Council officers; 3. the change in the estimated cost of support for Live Argyll in relation to the potential delay in the reopening of the Helensburgh Leisure Centre; 4. that the updated cost estimates were currently within the funding previously identified and agreed by the Council; and 5. that a final report would be brought back to committee in due course. (Reference: Report by Section 95 Officer dated 12 January 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendations

2.1Committee is recommended to:

a) Note the updated cost estimates in respect of Storm Eowyn. b) Note that some cost estimates remain unknown and are subject to ongoing assessment by the relevant Council officers. c) Note the change in the estimated cost of support for Live Argyll in relation to the potential delay in the reopening of the Helensburgh Leisure Centre. d) Note that the updated cost estimates are currently within the funding previously identified and agreed by the Council. e) Note that a final report will be brought back to committee in due course.

3. DETAIL

Background

3.1.1 Storm Eowyn struck Argyll and Bute on 24 January 2025, bringing wind speeds of up to 100 mph and causing significant damage to the Council’s infrastructure, particularly to roads, sea walls and harbour facilities. In addition, a number of other Council properties were also damaged and required repair the most significant of which was Helensburgh Leisure Centre which suffered extensive damage to its roof and water damage to the interior of the building and fixtures and fittings.

3.1.2 Since the storm, a number of works projects have been undertaken to repair the damage caused by the storm to the Council’s infrastructure and property and work remains ongoing on some sites. 3.2 Bellwin Claim

3.2.1 As noted in the report to Council on 26 June 2025, the Council activated the Bellwin Scheme in respect of Storm Eowyn and an initial claim for financial support was submitted to the Scottish Executive on 24 May 2025 for the sum of £352,898. The final claim for funding support under the Bellwin Scheme was submitted to the Scottish Government on 24 September 2025 for the value of £337,138. The final claim amount reduced by £15,760 following additional scrutiny by Financial Services staff to ensure that the costs claimed met the scheme’s criteria.

3.2.2 To date, a payment of £303,424, equivalent to 90% of the final claim amount, has been received. The final balance of the claim will be paid following the conclusion of the Scottish Government’s scrutiny of the claim which has yet to be completed.

3.3Live Argyll

3.3.1 The Council agreed on 26 June 2025 to provide financial assistance to Live Argyll whose financial position has been significantly impacted due to the closure of the Helensburgh Leisure Centre. The financial assistance extended to Live Argyll included £65k per month for seven months, at an estimated cost of £0.455m. It should be noted that the time period agreed for this support was not fixed by members but was based on an assumption on the likely timescale for repairs to be completed and the centre to reopen based on the information available at the time. The assistance agreed also provided Live Argyll with to access the Council’s redundancy earmarked reserve up to a maximum of £0.100m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
STORM EOWYN: ESTIMATE OF COST UPDATEReport 151 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 19 attended
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
MC
Councillor Math Campbell-SturgessMember, present
AF
Councillor Audrey ForrestMember, apologies
KG
Councillor Kieron GreenMember, present
AH
Councillor Amanda HampseyMember, present
MI
Councillor Mark IrvineMember, absent
RK
Councillor Reeni Kennedy-BoyleMember, present
JL
Councillor Jim LynchChair, present

All 19 on the meeting page

On this subject at Argyll and Bute

Search all
  1. STORM EOWYN - ESTIMATE OF COST UPDATEThis decision
  2. Storm eowyn - estimate of costNoted
  3. Storm eowyn weather event january 2025 infrastructure damage and recoveryNoted

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open