AI summaryArgyll and Bute Policy and Resources Committee notes updated Storm Eowyn cost estimates, with total estimated spend rising by £233,000 to £4.185 million and a £0.244 million funding surplus still to allocate.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFive points noted, including final report to follow
Money£4.185m estimated total costUp £233,000 from June 2025 figure
What happens nextFinal report back to committeeOnce remaining cost estimates are confirmed
Who it affectsLive Argyll and Helensburgh Leisure CentreSupport extended by further six months
What was decided
The Committee noted updated cost estimates for Storm Eowyn and that some estimates remain unknown pending officer assessment. Report P2
The Committee noted the change in estimated Live Argyll support cost linked to the delayed reopening of Helensburgh Leisure Centre. Report P10
The Committee noted that current cost estimates sit within previously agreed funding, and that a final report will return to committee in due course. Report P2
Why
Storm Eowyn struck on 24 January 2025 with winds up to 100 mph, damaging roads, sea walls, harbour facilities and Council property, most significantly Helensburgh Leisure Centre. Report P4
Repair complexities and further surveys at Helensburgh Leisure Centre mean its reopening is likely delayed, extending the need for Live Argyll financial support. Report P10
What happens next
Officers will continue assessing outstanding cost estimates, including Helensburgh Waterfront, and review the Helensburgh Leisure Centre repair programme. Report P10, P13, P14
Any remaining funding surplus after final costs are known is recommended to be returned to the Unallocated General Fund. Report P20
A final report will be brought back to committee in due course. Report P2
£337,138 Final Bellwin Scheme claim submitted 24 September 2025 Report P6
£303,424 Bellwin payment received, equivalent to 90% of final claim Report P7
£0.455m Original estimated cost of £65k per month support to Live Argyll for seven months Report P9
£0.390m Increase in Live Argyll support cost from six month extension Report P10
£0.845m Revised estimated cost of Live Argyll support Report P10
£0.100m Maximum Live Argyll redundancy earmarked reserve agreed Report P9, P11
£4.185m Total estimated Storm Eowyn expenditure at January 2026 Report P14
£4.092m Total funding identified by Council and EDI Committee Report P17
£0.244m Estimated surplus on storm funding at January 2026 Report P18, P20, 4.2
Options considered
Chosen: Extend Live Argyll £65k per month support by a further 6 months. Helensburgh Leisure Centre reopening likely delayed due to repair complexities and further surveys Report P10
Chosen: Return any remaining surplus to the Unallocated General Fund once final costs are known. Recommended once all storm costs are finalised Report P20
Implications
Financial: Estimated £0.244m surplus on storm funding, but further costs are likely, particularly for Helensburgh Leisure Centre. Report 4.2, P20
Staffing: Live Argyll's cost reduction plan has had staffing implications; redundancy costs not yet finalised but capped at £0.100m. Report P11
Risk: Significant risk of future weather events affecting Council property and infrastructure, and risk that estimated costs could increase.
Climate: Storm impact likely linked to climate change, highlighting need for further adaptation and significant investment to improve infrastructure resilience.
Users of Helensburgh Leisure Centre Report P4, P10
Roads, sea walls and harbour infrastructure across Argyll and Bute Report P4
Council taxpayers and the Unallocated General Fund Report P20
Timeline
24 January 2025: Storm Eowyn struck Argyll and Bute with winds up to 100 mph Report P4
24 May 2025: Initial Bellwin Scheme claim of £352,898 submitted to the Scottish Executive Report P6
26 June 2025: Council agreed financial assistance to Live Argyll and identified earmarked reserve Report P6, P9
24 September 2025: Final Bellwin Scheme claim of £337,138 submitted to the Scottish Government Report P6
12 January 2026: Section 95 Officer's report dated Report P25
19 February 2026: Policy and Resources Committee noted updated cost estimates
Plain English for the jargon
Bellwin Scheme: A Scottish Government scheme that provides financial support to local authorities for emergency costs from major incidents such as severe storms.
Live Argyll: An arms-length organisation linked to the Council that operates leisure and related services, including Helensburgh Leisure Centre.
Section 95 Officer: The Council's chief finance officer with statutory responsibility for the proper administration of its financial affairs.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18
Resolved
Decision The Policy and Resources Committee noted – 1. the updated cost estimates in respect of Storm Eowyn; 2. that some cost estimates remain unknown and were subject to ongoing assessment by the relevant Council officers; 3. the change in the estimated cost of support for Live Argyll in relation to the potential delay in the reopening of the Helensburgh Leisure Centre; 4. that the updated cost estimates were currently within the funding previously identified and agreed by the Council; and 5. that a final report would be brought back to committee in due course. (Reference: Report by Section 95 Officer dated 12 January 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
a) Note the updated cost estimates in respect of Storm Eowyn. b) Note that some cost estimates remain unknown and are subject to ongoing assessment by the relevant Council officers. c) Note the change in the estimated cost of support for Live Argyll in relation to the potential delay in the reopening of the Helensburgh Leisure Centre. d) Note that the updated cost estimates are currently within the funding previously identified and agreed by the Council. e) Note that a final report will be brought back to committee in due course.
3. DETAIL
Background
3.1.1 Storm Eowyn struck Argyll and Bute on 24 January 2025, bringing wind speeds of up to 100 mph and causing significant damage to the Council’s infrastructure, particularly to roads, sea walls and harbour facilities. In addition, a number of other Council properties were also damaged and required repair the most significant of which was Helensburgh Leisure Centre which suffered extensive damage to its roof and water damage to the interior of the building and fixtures and fittings.
3.1.2 Since the storm, a number of works projects have been undertaken to repair the damage caused by the storm to the Council’s infrastructure and property and work remains ongoing on some sites. 3.2 Bellwin Claim
3.2.1 As noted in the report to Council on 26 June 2025, the Council activated the Bellwin Scheme in respect of Storm Eowyn and an initial claim for financial support was submitted to the Scottish Executive on 24 May 2025 for the sum of £352,898. The final claim for funding support under the Bellwin Scheme was submitted to the Scottish Government on 24 September 2025 for the value of £337,138. The final claim amount reduced by £15,760 following additional scrutiny by Financial Services staff to ensure that the costs claimed met the scheme’s criteria.
3.2.2 To date, a payment of £303,424, equivalent to 90% of the final claim amount, has been received. The final balance of the claim will be paid following the conclusion of the Scottish Government’s scrutiny of the claim which has yet to be completed.
3.3Live Argyll
3.3.1 The Council agreed on 26 June 2025 to provide financial assistance to Live Argyll whose financial position has been significantly impacted due to the closure of the Helensburgh Leisure Centre. The financial assistance extended to Live Argyll included £65k per month for seven months, at an estimated cost of £0.455m. It should be noted that the time period agreed for this support was not fixed by members but was based on an assumption on the likely timescale for repairs to be completed and the centre to reopen based on the information available at the time. The assistance agreed also provided Live Argyll with to access the Council’s redundancy earmarked reserve up to a maximum of £0.100m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.