2025/26 ACTIVE TRAVEL PROGRESS REPORT

Decided Committee 1 paper

AI summaryBute and Cowal Area Committee welcomed 2025/26 active travel progress and backed using Tier 1 funding in the 26/27 block grant to develop and deliver further active travel projects.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedOfficers instructed to develop more projects
Money£1.1M external funding in 2025/26Tier 1 element of 26/27 block grant backed
What happens nextSubmit future funding applicationsAwait 26/27 ATIF Tier 2 funding offers
Who it affectsBute and Cowal residents and businessesEspecially 26% of households without a car

What was decided

Members welcomed progress by the small Active Travel Team across a significant number of active travel projects in 2025/26. Report P22

Members supported continuing current projects and submitting future funding applications to external challenge funds. Report P23

Members backed using the Tier 1 active travel funding element within the 26/27 Council block grant for active travel projects, including those already underway in Bute and Cowal, and asked officers to keep developing new ones. Report P24, P25

Why

The 1.7 FTE Active Travel Team secured £1.1M of external funding in 2025/26 and delivered 17 projects across Argyll and Bute, despite late Tier 2 funding offers from Transport Scotland. Report 4.1, 4.5, 4.8

26% of Bute and Cowal households (2,758) have no motor vehicle and rely on walking, wheeling, cycling and public transport, so active travel routes improve access to services and cut transport poverty. Report 1.3, 4.19, 4.20

Active travel links to schools, shops and tourism, and may cut future school transport and social care costs while reducing carbon emissions. Report 1.3, 4.21, 4.22, 4.24

What happens next

Officers will continue to seek external challenge funding and submit new applications as opportunities arise. Report P23, 4.14

Officers will identify and develop new active travel projects for Bute and Cowal residents, businesses and communities. Report P25, 5.1

Officers are engaging Transport Scotland on the timing of 26/27 ATIF Tier 2 funding offers, which are progressing through internal approvals. Report 4.10

The money

  • £1.1M External funding secured by Active Travel Team in 2025/26 for 17 projects Report 1.6, 4.5
  • £188.7M Scottish Government 25/26 budget committed to active travel and bus improvements Report 1.11, 4.11
  • £226M Scottish Government 26/27 budget committed to active travel and bus improvements Report 1.11, 4.11
  • 30% Minimum share of construction cost Transport Scotland asks Local Authorities to provide from non-Transport Scotland sources Report 4.7, 4.16
  • £15M Sustrans Scotland direct funding from Transport Scotland for 24/25 National Cycle Network Report 4.16

Options considered

  • Chosen: Welcome 2025/26 progress and support continuation of projects and future funding bids. Recognises the small team's delivery of 17 projects and £1.1M external funding Report P22, P23
  • Chosen: Allocate Tier 1 active travel funding within 26/27 block grant to active travel projects in Bute and Cowal. Tier 1 must be spent appropriately for the Council to remain eligible for Tier 2 Report P24, 4.6
  • Chosen: Instruct officers to keep developing new active travel projects. To extend benefits to local residents, businesses and communities Report P25

Implications

  • Financial: Active travel in Argyll and Bute is currently funded only via external challenge funds; the Council has not yet contributed to design or capital costs, and new infrastructure will need future maintenance funding. Report 4.1
  • Financial: New safe active travel routes to school may cut school transport spend, and more active lifestyles may reduce future social care costs. Report 1.3, 4.21, 4.24
  • Legal: Legal Services input will be needed for any land acquisition required for new active travel routes.
  • Risk: There is a reputational risk to the Council if the projects are not completed within a reasonable timeframe.
  • Equalities: New and improved routes will be DDA compliant and accessible for wheelchairs, mobility aids and prams, helping residents reliant on walking, wheeling and cycling.
  • Equalities: Improved routes will help reduce transport poverty and inequality for those without cars or with low incomes. Report 4.20
  • Climate: Active travel is the least carbon intensive mode of travel, so more routes and behaviour change will help cut Argyll and Bute's carbon footprint.
  • Other: Projects support the Council's Outcomes Improvement Plan (Transport Infrastructure and Community Wellbeing), the Scottish Government Cycling Action Plan for Scotland and the National Walking Strategy. Report 6.1

Who and where

  • Residents of Bute and Cowal, including 2,758 households without a motor vehicle Report 1.3, 4.19
  • Local businesses and visitors in Rothesay, Dunoon, Innellan, Sandbank, Blairmore, Kilmun, Strone and Tighnabruaich Report 1.3, 4.19
  • School pupils, parents and staff, where routes to school may be improved Report 1.3, 4.24
  • Community organisations including ACT, Dunoon Community Development Trust and Positive Pedals in Rothesay Report 4.13, P60, P61, P62
  • People with mobility impairments, wheelchair users and parents with prams who use new accessible routes Report 1.2

Timeline

  • 09 December 2025: Transport Scotland ATIF Tier 2 design stage funding offers received for 25/26 projects Report 1.9, 4.8
  • 13 February 2026: Transport Scotland ATIF Tier 2 construction stage funding offer received for 25/26 Report 1.9, 4.8
  • 31 March 2026: Deadline to spend or return all 25/26 ATIF Tier 2 funds Report 1.9, 4.8
  • 10 May 2026: Date of the report by the Executive Director for Development and Economic Growth Report P58
  • 02 June 2026: Bute and Cowal Area Committee meeting at which the decision was taken Report P16, P17
  • 2026/27: Rothesay Town Active Travel Network: Developed Design stage planned; Competitive Tier 2 application submitted Report 4.10, P63
  • 2027/28: Rothesay Town Active Travel Network: Technical Design stage planned Report P63
  • 2029/30, 2034/35: Rothesay Town Active Travel Network: Construction stage planned Report P63

Plain English for the jargon

  • Active Travel: Accessible everyday walking, wheeling (mobility aids, prams, buggies) and cycling, particularly for those with mobility impairments.
  • ATIF Tier 1: Active Travel Infrastructure Fund money paid to the Council through the block grant, monitored by Transport Scotland to confirm it is spent on appropriate active travel work.
  • ATIF Tier 2: A competitive annual challenge fund run by Transport Scotland for larger active travel infrastructure projects, requiring a fresh application each year.
  • LADA: Local Authority Direct Award from Transport Scotland, ring fenced for active travel behaviour change work and reclaimed after spend.
  • HITRANS / SPT People and Place Programme: Transport Scotland funding passed to Regional Transport Partnerships (HITRANS, SPT) for active travel behaviour change, with each RTP choosing its own distribution model.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

Decision The Bute and Cowal Area Committee – 1. welcomed the progress made to date across a significant number of active travel projects by the very small Active Travel Team; 2. supported the continuation of the projects and the submission of future funding applications to external challenge funds to continue to develop design and construction stages to deliver these projects; 3. supported the allocation of the Tier 1 active travel funding element in the Council’s 26/27 block grant to the development and delivery of appropriate active travel projects, including those already underway in Bute and Cowal; and 4. instructed Officers to continue to identify and develop new active travel projects to benefit local residents, businesses and communities. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 10 May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Bute and Cowal Area Committee

Executive summary

1.1This report provides an update to Members on the progress made in 2025/26 in relation to active travel projects in the B&C Area, informs Members of the continued delays in receipt of Scottish Government active travel funding and seeks continued support for the projects and wider active travel measures from Members.

1.2Active travel encompasses accessible, everyday Walking, Mobility Assistance and child push scooters and prams/buggies (collectively termed “Wheeling”) and Cycling. The focus of active travel is on accessible provision including those with mobility impairments.

1.3Active Travel can offer significant benefits to the area: • Access to essential services and employment: In B&C 26% of households (2,758 households) do not have access to a motor vehicle and are therefore reliant on public transport and active travel modes. Within the key settlements the proportion of households without access to a motor vehicle is 41% (947) in Rothesay, 26% (1,370) in Dunoon, Innellan and Sandbank, 15% (50) in Blairmore, Kilmun and Strone and 13% (40) in Tighnabruaich. (2022 census) • Health benefits: being more active reduces the risk of premature morbidity and death, particularly from diseases related to inactivity. (NHS Scotland) • Economics: People who travel to shops by walking and/or cycling have a higher monthly spend than people who travel to shops by private car. (Pedestrian Pound, 2024) • Improving safety: high quality active travel infrastructure reduces the frequency of injuries from collisions with motor vehicles. (Transport Scotland) • A number of active travel projects link to schools, offering the opportunity to increase the numbers of pupils, parents and staff choosing to walk, cycle or wheel to school. While focus is improved physical and mental health, where new active travel infrastructure creates a safe route to school where one did not previously exist it could reduce the requirement to provide school transport on safety grounds, thereby creating a revenue saving to the Council’s school transport budget. 1.4. No Council funding is currently received by the Active Travel Team, 1.7 Full Time Equivalent employees, which is part of the Strategic Transport Team within the Development and Economic Growth Service. All project costs, including internal staff costs, are funded via successfully securing highly competitive external challenge funds.

1.5The Active Travel Team work with communities, internal and external stakeholders across Argyll and Bute to develop and deliver active travel projects which provide new/improved accessible infrastructure (e.g. paths, cycle lanes) and behaviour change (e.g. access to bikes, walking/cycle training, promotional activities).

1.6In 2025/26, the Active Travel Team secured £1.1M external funding for the development and delivery of a total of 17 projects across Argyll and Bute.

1.7The Active Travel Team work to secure highly competitive funding from a range of sources, the main of which are Transport Scotland’s Active Travel Infrastructure Fund (ATIF) Programme, Transport Scotland’s Local Authority Direct Award (LADA) fund and HITRANS Regional People and Place Fund. It is recognised at a national level that the Active Travel Team in Argyll and Bute Council deliver more projects and subsequently secure significantly more funding than similar staffed teams in other Local Authorities.

1.8Officers also support community organisations in Argyll and Bute to secure funding from the HITRANS / SPT Regional People and Place Community Funds to deliver behaviour change projects in their local area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 ACTIVE TRAVEL PROGRESS REPORTReport 221 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
KM
Katie McKenzieSecretary, expected
GB
Councillor Gordon BlairVice-Chair, present
AF
Councillor Audrey ForrestMember, apologies
DH
Councillor Daniel HampseyMember, apologies
RK
Councillor Reeni Kennedy-BoyleChair, present
LM
Councillor Liz McCabeMember, apologies
YM
Councillor Yvonne McNeillyMember, present
RM
Councillor Ross MorelandMember, present
WS
Councillor William SinclairMember, present
PW
Councillor Peter WallaceMember, present

On this subject at Argyll and Bute

Search all
  1. 2025/26 ACTIVE TRAVEL PROGRESS REPORTThis decision
  2. 2025/26 active travel progress reportDecided
  3. 2025/26 active travel progress reportDecided
  4. 2025/26 active travel progress reportDecided
  5. A83 tarbert to whitehouse active travel project progress reportDecided
  6. Rothesay pavilion to albert pier active travel project - updated reportsApproved

More from Argyll and Bute Bute and Cowal Area Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... Noted Open
1 Sep 2026 Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... Noted Open
1 Sep 2026 Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... Agreed Open
1 Sep 2026 Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... Noted Open
1 Sep 2026 Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies