CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Oban Lorn & The Isles Area Committee, Wednesday 10 June 2026 at 10.30am

2025/26 ACTIVE TRAVEL PROGRESS REPORT

Decided Committee 1 paper

AI summaryOban, Lorn and the Isles councillors welcome progress on active travel projects and back continued external funding bids, with £1.1m secured in 2025/26 across 17 schemes.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee welcomed progress and backed further funding applications
Money£1.1M external funding in 2025/26Secured for 17 projects across Argyll and Bute
What happens nextOfficers to develop new projectsContinue identifying and developing new active travel schemes
Who it affectsOban, Lorn and the Isles residents1,755 households without a car in the area

What was decided

The committee welcomed the progress made by the small Active Travel Team on a significant number of active travel projects. Report P12

Members supported continuing the projects and submitting future funding applications to external challenge funds for design and construction stages. Report P13

Members supported allocating the Tier 1 active travel funding element in the Council's 26/27 block grant to appropriate active travel projects, including those already underway in OLI. Report P14

Why

In 2025/26 the team secured £1.1M external funding for 17 projects across Argyll and Bute, and is recognised nationally as delivering more projects than similarly sized teams. Report 1.6, 4.2, 4.5

18% of OLI households (1,755) have no access to a motor vehicle, so depend on public transport, walking, wheeling and cycling for everyday journeys. Report 1.3, 4.20

Active travel is the lowest carbon mode of travel, brings health benefits, and may reduce school transport and social care costs. Report 1.3, 4.22, 4.25

What happens next

Officers are instructed to continue identifying and developing new active travel projects to benefit local residents, businesses and communities. Report P15

Officers will continue to engage with Transport Scotland on the timing of 26/27 ATIF Tier 2 funding offers, which are progressing through internal approval. Report 1.10, 4.10

Funding applications have been submitted for 26/27 for the Oban Sustainable Travel Masterplan and the Tobermory and Isle of Mull Sustainable Travel Masterplan. Report 4.11

The money

  • £1.1M External funding secured in 2025/26 for 17 active travel projects across Argyll and Bute Report 1.6, 4.5
  • £188.7M Scottish Government 25/26 budget committed to active travel and bus improvements Report 1.11, 4.12
  • £226M Scottish Government 26/27 budget committed to active travel and bus improvements Report 1.11, 4.12
  • £15M Sustrans Scotland direct funding from Transport Scotland in 24/25 for the National Cycle Network Report 4.17
  • £25,000 Contribution from Argyll and Bute Council LADA fund to Adventure Oban Schools Active Travel project Report P61
  • £25,000 Contribution from Argyll and Bute Council LADA fund to ACT Bikes back to the Community project Report P62
  • £53,700 2025/26 construction funding for the U22 Achavaich Road between Oban and Connel Report P63
  • £26,400 2025/26 funding for project initiation of the Oban Sustainable Travel Masterplan Report P63

Options considered

  • Chosen: Welcome progress and support continued external funding bids for design and construction stages. Recommended to sustain project pipeline using competitive challenge funds Report P12, P13
  • Chosen: Allocate Tier 1 active travel element of the 26/27 Council block grant to active travel projects in OLI. Tier 1 spending influences future Tier 2 eligibility and unlocks further funding Report 4.6, P14
  • Chosen: Instruct officers to continue identifying and developing new active travel projects. To deliver further benefits to residents, businesses and communities Report P15

Implications

  • Financial: The Council has not yet contributed funding to design or capital costs, but will need to consider future maintenance of new active travel infrastructure, as external funds do not cover maintenance.
  • Financial: Transport Scotland will require local authorities to provide a minimum of 30% of construction cost from non-Transport Scotland sources. Report 4.7, 4.17
  • Climate: Active travel is the least carbon intensive travel mode and will help lower Argyll and Bute's carbon footprint by offering an alternative to private car use.
  • Equalities: New routes are designed to be accessible and DDA compliant for those with mobility aids, wheelchairs, and parents with prams or buggies. Report 1.2
  • Legal: Continued legal input is required to support any land acquisition needed for new active travel routes.
  • Risk: There is a reputational risk to the Council if active travel projects are not completed within a reasonable timeframe.

Who and where

  • 1,755 households in OLI without access to any motor vehicle (29% in Oban, 19% in Dunbeg, 14% in Tobermory, 11% in Connel) Report 1.3, 4.20
  • School pupils, parents and staff who could use new active travel routes to school Report 1.3, 4.25
  • Local businesses that could benefit from increased footfall and cycle trade Report 4.23
  • Island communities served by projects that link to ferry terminals

Timeline

  • 09 December 2025: ATIF Tier 2 funding offers for design stage projects received Report 1.9, 4.8
  • 13 February 2026: ATIF Tier 2 funding offer for construction stage project received Report 1.9, 4.8
  • 31 March 2026: All 25/26 ATIF Tier 2 funds had to be expended or returned Report 1.9, 4.8
  • 10 May 2026: Report by Executive Director dated Report P59
  • 10 June 2026: Oban, Lorn and the Isles Area Committee meeting Report P16
  • 26/27: Funding applications submitted for Oban Sustainable Travel Masterplan and Tobermory and Isle of Mull Sustainable Travel Masterplan Report 4.11

Plain English for the jargon

  • Active travel: Accessible, everyday walking, wheeling (mobility aids and child prams) and cycling
  • ATIF: Transport Scotland's Active Travel Infrastructure Fund, split into Tier 1 (block grant) and Tier 2 (competitive challenge fund)
  • LADA: Local Authority Direct Award, an annual allowance from Transport Scotland for active travel behaviour change work
  • HITRANS: Regional Transport Partnership covering the Highlands and Islands
  • SPT: Strathclyde Partnership for Transport, the Regional Transport Partnership for the west of Scotland
  • OLI: Oban, Lorn and the Isles area covered by this committee
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Decision The Oban, Lorn and the Isles Area Committee:- 1. welcomed the progress made to date across a significant number of active travel projects by the very small Active Travel Team; 2. supported the continuation of the projects and the submission of future funding applications to external challenge funds to continue to develop design and construction stages to deliver these projects; 3. supported the allocation of the Tier 1 active travel funding element in the Council’s 26/27 block grant to the development and delivery of appropriate active travel projects, including those already underway in Oban, Lorn and the Isles; and 4. instructed Officers to continue to identify and develop new active travel projects to benefit local residents, businesses and communities. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 10 May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Oban Lorn & The Isles Area Committee

Executive summary

1.1This report provides an update to Members on the progress made in 2025/26 in relation to active travel projects in the OLI Area, informs Members of the continued delays in receipt of Scottish Government active travel funding and seeks continued support for the projects and wider active travel measures from Members.

1.2Active travel encompasses accessible, everyday Walking, Mobility Assistance and child prams (sometime collectively termed “Wheeling”) and Cycling. The focus of active travel is on accessible provision including those with mobility impairments.

1.3Active Travel can offer significant benefits to the area: • Access to essential services and employment: In OLI 18% of households (1,755 households) do not have access to a motor vehicle and are therefore reliant on public transport and active travel modes. Within the key settlements the proportion of households without access to a motor vehicle is 29% (1,153) in Oban, 19% (80) in Dunbeg, 14% (70) in Tobermory and 11% (25) in Connel. (2022 census) • Health benefits: being more active reduces the risk of premature morbidity and death, particularly from diseases related to inactivity. (NHS Scotland) • Economics: People who travel to shops by walking and/or cycling have a higher monthly spend than people who travel to shops by private car. (Pedestrian Pound, 2024) • Improving safety: high quality active travel infrastructure reduces the frequency of injuries from collisions with motor vehicles. (Transport Scotland) • A number of active travel projects link to schools, offering the opportunity to increase the numbers of pupils, parents and staff choosing to walk, cycle or wheel to school. While focus is improved physical and mental health, where new active travel infrastructure creates a safe route to school where one did not previously exist it could reduce the requirement to provide school transport on safety grounds, thereby creating a revenue saving to the Council’s school transport budget. 1.4. No Council funding is currently received by the Active Travel Team, 1.7 Full Time Equivalent employees, which is part of the Strategic Transport Team within the Development and Economic Growth Service. All project costs, including internal staff costs, are funded via successfully securing highly competitive external challenge funds.

1.5The Active Travel Team work with communities, internal and external stakeholders across Argyll and Bute to develop and deliver active travel projects which provide new/improved accessible infrastructure (e.g. paths, cycle lanes) and behaviour change (e.g. access to bikes, walking/cycle training, promotional activities).

1.6In 2025/26, the Active Travel Team secured £1.1M external funding for the development and delivery of a total of 17 projects across Argyll and Bute.

1.7The Active Travel Team work to secure highly competitive funding from a range of sources, the main of which are Transport Scotland’s Active Travel Infrastructure Fund (ATIF) Programme, Transport Scotland’s Local Authority Direct Award (LADA) fund and HITRANS Regional People and Place Fund. It is recognised at a national level that the Active Travel Team in Argyll and Bute Council deliver more projects and subsequently secure significantly more funding than similar staffed teams in other Local Authorities.

1.8Officers also support community organisations in Argyll and Bute to secure funding from the HITRANS / SPT Regional People and Place Community Funds to deliver behaviour change projects in their local area.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2025/26 ACTIVE TRAVEL PROGRESS REPORTReport 218 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
KC
Karen CampbellSecretary, expected
KG
Councillor Kieron GreenChair, present
AH
Councillor Amanda HampseyMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainVice-Chair, present
JL
Councillor Jim LynchMember, present
LM
Councillor Luna MartinMember, present
JM
Councillor Julie McKenzieMember, present
KM
Katie McKenzieSecretary, expected
AV
Councillor Andrew VennardMember, present

On this subject at Argyll and Bute

Search all
  1. 2025/26 ACTIVE TRAVEL PROGRESS REPORTThis decision
  2. 2025/26 active travel progress reportDecided
  3. 2025/26 active travel progress reportDecided
  4. A83 tarbert to whitehouse active travel project progress reportDecided
  5. 2025/26 active travel progress reportDecided
  6. Rothesay pavilion to albert pier active travel project - updated reportsApproved

More from Argyll and Bute Oban Lorn & The Isles Area Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... Agreed Open
9 Sep 2026 CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... Noted Open
9 Sep 2026 Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... Noted Open
9 Sep 2026 Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... Noted Open
9 Sep 2026 Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies