AI summaryArgyll and Bute Oban area committee noted completed and planned repairs to North Pier Pontoons damaged by Storm Éowyn, with two units to be replaced over winter 2026/27 ahead of full reopening in spring 2027.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted completed work, future works and costs
MoneyMultiple cost linesLargest confirmed spend is £371,192.12 for temporary repairs
What happens nextTender and replacementFull reopening planned for spring 2027
Who it affectsOban marine and harbour usersBoat users and visiting vessels at North Pier
What was decided
The committee noted the works which have been completed to date at the North Pier Pontoons, including inspections, surveys, minor repairs and the temporary reconfiguration of damaged units. Report 3.1
The committee noted further works required and the indicative timescales, including replacement of the two most damaged units over winter 2026/27 and full reopening in spring 2027. Report 3.1
The committee noted the confirmed and estimated costs for completed and anticipated works, with permanent replacement unit costs still to be confirmed by tender. Report 3.1, 6.0
Why
Storm Éowyn in January 2025 caused significant damage to the North Pier pontoons and breakwater, requiring immediate closure on public safety grounds. Report 1.2, 4.1
Both minor and major damage was identified through inspections, and a phased approach was required because of safety, procurement, weather and operational constraints. Report 1.3, 2.1
Temporary works were carried out to maximise safe berthing during the 2026 season while permanent replacements are arranged, avoiding full closure during peak use and planned events. Report 1.4
What happens next
Officers are preparing a tender to replace the two most damaged units, one of which cannot be safely fixed to the mooring chains and the other of which has exposed reinforcement at risk of rapid degradation. Report 5.0, 5.1
Replacement units are intended to be installed over winter 2026/27, with full reopening of the facility in spring 2027 without the current restrictions. Report 1.4
Continued communication through the council website, Notices to Mariners, committee papers and stakeholder updates is planned as the next steps progress. Report 7.1
The money
£9,126.94 Minor repairs (floats and fencing), actuals paid to date Report 6.0
£46,524 Dive survey (including annual inspection) and damage report, actuals paid to date Report 6.0
£26,840 Options report, design and contract support, actuals paid to date Report 6.0
£64,830 Options report, design and contract support, estimated total cost Report 6.0
£371,192.12 Temporary repairs, actuals paid to date Report 6.0
£40,359.72 Electrical supply, quoted Report 6.0
Implications
Financial: Unexpected and planned costs due to weather damage have implications for the Marine Asset Management Plan, alongside reduced income from the facility while aspects are out of service. Report 9.0
Other: Costs associated with surveys, inspections and temporary works were unavoidable to ensure public safety, inform the design of a permanent solution and maintain partial operations. Report 6.2
Risk: Temporary and complete works will increase the safety of the facility for users, and long term repairs will reduce the need for closure during poor weather, limiting impact on access. Report 9.0
Climate: Repair and replacement works will improve the resilience of the facility to future severe weather events, with reuse and repair of existing components prioritised where practicable to minimise material use. Report 9.0
Other: Reduced capacity at the facility during replacement works is expected to affect customer service. Report 9.0
Who and where
Local users, visiting vessels and the wider marine community using Oban's North Pier pontoons Report 2.1
Harbour users and relevant interest groups receiving stakeholder communications by email and Facebook Report 7.1
Timeline
January 2025: Storm Éowyn caused significant damage to the North Pier breakwater and pontoons, requiring immediate closure on public safety grounds Report 1.2
Early 2026: Temporary reconfiguration works were completed, increasing available berthing by approximately 240m in time for the 2026 season Report 1.4
Winter 2026/27: Replacement of the two most damaged units planned Report 1.4
Spring 2027: Full reopening of the facility planned, without the currently imposed restrictions Report 1.4
Plain English for the jargon
Pontoons: Floating platforms used for berthing boats at the North Pier
Breakwater: Structure protecting the inner berthing area from waves
Storm Éowyn: Severe storm in January 2025 that damaged the facility
Mooring chains and anchor blocks: Underwater fixings that hold the pontoon units in place
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
Decision The Oban, Lorn and the Isles Area Committee:- 1. noted the works which have been completed to date at the North Pier Pontoons 2. noted the works which are required in due course and the estimated timescales for completion of the works 3. noted the confirmed and estimated costs associated with completed and anticipated works. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure, dated May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to provide an update on repairs to the North Pier Pontoons, Oban required as a result of Storm Éowyn, including works completed, further works anticipated, timescales, and estimated costs.
1.2Storm Éowyn caused significant damage to the North Pier breakwater and pontoons in January 2025, requiring immediate closure on public safety grounds
1.3Both minor and major damage was identified via a series of inspections. Minor defects were remedied in early 2025 to enable partial re-opening. More severe damage required specialist assessment and a phased approach to repair due to safety, procurement, weather, and operational constraints
1.4Temporary reconfiguration works completed in early 2026 have increased available berthing by approximately 240m in time for the 2026 season. The most damaged units are proposed for replacement over winter 2026/27, allowing full reopening in spring 2027
1.5This report summarises works undertaken, explains the rationale for decisions made, and sets out the proposed programme and indicative costs for permanent repair. ARGYLL AND BUTE COUNCIL OBAN LORN AND THE ISLES AREA COMMITTEE ROADS AND INFRASTRUCTURE 10TH JUNE 2026
NORTH PIER PONTOONS – REPAIRS REPORT
2.0INTRODUCTION
2.1The North Pier pontoons are an important part of Oban’s waterfront, offering valuable access for local users, visiting vessels, and the wider marine community. Over the past year, they have been affected by significant weather-related damage which forced closure on safety grounds. 2.2 On 24th January 2025, Storm Eowyn caused significant damage to the facility, including visible damage to the pontoons and breakwater sections that protect the inner berthing area. As a safety precaution, the facility was initially closed completely to allow comprehensive above and underwater inspections. 2.3 A primary walkover survey was carried out by Officers immediately following the storm to assess visible damage. This was followed by a dive survey in February 2025 which indicated both minor and major damage to the facility. Officers managed the minor repairs to allow initial quick but limited re-opening of the facility in April 2025 2.4 With the support of specialist consultant engineers, an options appraisal was developed that made recommendations for both short term temporary repairs followed with longer-term replacements. This considered the severity of the major damage and balanced these against timescales for procurement of replacements in relation to the general operation of the facility, known planned events at the facility and estimated timescales for repair work. 2.5 Temporary repairs took place in early 2026 which has seen damaged units relocated to allow a wider proportion of the facility to be reopened to users. Officers are currently working on plans for long term repairs with a view to procuring and installing replacement units over winter 2026/27 3.0 RECOMMENDATIONS
3.1The Area Committee is asked to: a. Note the works which have been completed to date at the North Pier Pontoons b. Note the works which are required in due course and the estimated timescales for completion of the works c. Note the confirmed and estimated costs associated with completed and anticipated works.
4.0DETAIL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.