TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM - LARGE SCALE PROJECT UPDATE REPORT

Noted Committee 1 paper

AI summaryArgyll and Bute's environment committee noted progress on over £100m of regeneration projects. Five new bids will go to the Scottish Government's Regeneration Capital Grant Fund for 2027/28, with Stage 1 outcomes expected in October 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFive projects submitted as Stage 1 EOIs to RCGF
Moneyover £100mTotal value of projects and grants managed by the team
What happens nextAwait Stage 1 EOI resultsExpected during October 2026
Who it affectsCommunities across Argyll and ButeMultiple towns, villages and island communities

What was decided

The committee noted the current progress contained within the report on large-scale, externally funded project work. Report 1.1, 2.1

The committee noted the five projects listed in paragraph 4.5 that form the basis of Stage 1 expression of interest bids to the Scottish Government's Regeneration Capital Grant Fund, and that successful projects will need more detailed Stage 2 bids later in the year. Report P33, P37

The committee noted that further updates on pending funding bids will be brought back to the committee in due course. Report P38

Why

To update the committee on progress with large-scale, externally funded project work and to highlight key issues that may affect successful delivery of economic development capital projects. Report 1.1, 2.1

The Stage 1 RCGF application deadline of 14 August 2026 fell during the summer recess, so the committee was not able to agree the bids ahead of submission and is being asked to note them retrospectively. Report P33

The grant funding landscape and delivery of capital projects remains extremely challenging due to cost pressures and fixed project budgets. Report 1.5

What happens next

Officers expect to be advised during October 2026 on which Stage 1 RCGF bids are successful and can progress to Stage 2 applications. Report P38

If successful at Stage 1, more detailed Stage 2 funding bids must be submitted by the end of November 2026, with funding announcements expected in February 2027 and project delivery by the end of March 2028. Report P34

Further updates on pending funding bids will be brought to the Environment, Development and Infrastructure Committee in due course, and a further report on the remaining Crown Estate funding for 2026/27 will go to the Policy and Resources Committee. Report P51

The money

  • over £100m Cumulative value of projects and grants managed by the Transformational Projects and Regeneration Team Report 1.3
  • £20.34m Community Regeneration Partnership funding (UK Government), to be fully committed by 31 March 2027 Report 2.4
  • £4,855,681 Total Rural Growth Deal funding allocation for 2026/27 Report 5.1, P61
  • £3,898,507 Council's net Crown Estate revenue allocation for 2026/27 Report 4.7
  • £2,418,500 Combined value of four successful Stage 2 RCGF 2026/27 bids (Kintyre Sea Sports £800,000, Nonhebel Park £648,500, Tarbert Harbour £850,000, Tighnabruaich £120,000) Report P30
  • £1,747,936 RCGF funding for Isle of Luing Community Trust slate quarry project from 2025/26 Report P32
  • £4,024,000 Combined value of the five Stage 1 RCGF 2027/28 EOI applications (Oban Lorne £700,000, Rothesay Winter Garden £974,000, Tiree Gateway £1,400,000, Crinan Canal Terminus £750,000, TAC Workspace £200,000) Report P37
  • £145,000 Islands Cost Crisis Emergency Fund allocation to Argyll and Bute for 2026/27 Report P58

Options considered

  • Chosen: Submit the five listed projects as Stage 1 Expressions of Interest to the Scottish Government RCGF for 2027/28. Projects were considered a good fit with the fund criteria following review of community submissions and the Council's pipeline Report P35, P37

Implications

  • Financial: All funding has been approved for the projects detailed in the report; the team will continue to review costs and assess budgets against the fixed nature of project budgets. Report 11.2, 1.5
  • Financial: Rural Growth Deal funding cannot be drawn down before endorsement of full business cases by central government, a process that can take up to 9 months and may result in underspend being re-allocated to future years. Report 5.2
  • Financial: The principal CRP risk is the current wording of the Memorandum of Understanding, which appears to require the full £20 million capital allocation to be defrayed by 31 March 2027; ministerial approval is being sought for an amendment or clarification.
  • Legal: Each project has different legal and procurement requirements depending on the grant funder and associated grant contract conditions. Report 11.3
  • Risk: The first Internal Audit of the Rural Growth Deal reported a reasonable level of assurance but recommended that risks relating to abortive development costs be added to the Council's Operational Risk Register, and that a record retention schedule and written procedures be developed. Report P64, P65
  • Risk: Construction projects carry risks from site conditions, contractor management, design team coordination, budgets and funder requirements; these are mitigated through strong project management and robust procurement and contract management. Report 11.6
  • Equalities: Projects can be a driver for inclusion and can support positive outcomes for children and young people, including those at greatest risk of poverty. Report 11.9, 11.12
  • Climate: There is an ambition for project work to work towards net zero by adopting a carbon conscious approach, and some grant funding directly supports the transition to net zero such as the Carbon Neutral Islands fund. Report 11.7
  • Staffing: Delivery and management of these externally funded projects, plus PBI, Crown Estate, Islands Programme and RCGF grants, requires significant team resources for due diligence, financial management and risk minimisation. Report 11.4

Who and where

  • Communities across Argyll and Bute, including town centres, villages and island communities benefitting from over £100m of regeneration project work Report 1.3
  • Helensburgh town centre, through the Helensburgh CARS heritage regeneration programme and the Outdoor Museum artworks Report 4.2, P20, P21, P40
  • Tarbert village, through the new five-year Tarbert Heritage Scheme and the Crinan Canal Terminus Regeneration bid Report 4.3, P23, P37
  • Oban and North Argyll, through the proposed Oban Lorne Community Sports Facilities Upgrade Report P37
  • Rothesay, through the Winter Garden Land Redevelopment bid and the Former Royal Hotel CRP project Report P37, P69
  • Tiree, through the proposed Tiree Gateway project and the Tiree Veterinary Surgery Islands Programme bid Report P37, P54
  • Ardrishaig, through the second phase of the former Gleaner Oil site development and the Crinan Canal Terminus bid Report P27, P37
  • Isle of Bute businesses and residents, through the BID renewal ballot and the potential £158,220 per year levy Report 9.1, 9.2

Timeline

  • 12 March 2026: Scottish Government announced £1 million Islands Cost Crisis Emergency Fund for 2026/27 Report P57
  • 30 April 2026: First Annual Conversation for the Rural Growth Deal took place at Kilmory
  • May 2026: Policy and Resources Committee approved £1.5m of Crown Estates funding and final Tarbert/Lochgilphead Regeneration Fund grant of £250,000 to Scottish Canals Report P27, P42
  • 24 June 2026: Full Council agreed to approve the Isle of Bute BID Renewal Ballot Proposal Report 9.1
  • 2 July 2026: Scottish Government announced commencement of the application process for RCGF 2027/28 Report P33
  • 22 July 2026: Scottish Government confirmed the Council's net Crown Estate revenue allocation of £3,898,507 for 2026/27 Report 4.7
  • 27 July 2026: Scottish Government confirmed Islands Programme funding for 2026/27 projects Report P53
  • 14 August 2026: Stage 1 EOI deadline for RCGF 2027/28 bids Report P33
  • October 2026: Expected notification of which Stage 1 RCGF bids can progress to Stage 2 Report P38
  • 9 October 2026: Environment, Development and Infrastructure Committee meeting Report P8
  • End November 2026: Stage 2 RCGF 2027/28 application deadline Report P34
  • December 2026: First building at Oban Airport Aviation Business Park due for completion Report P69
  • February 2027: RCGF 2027-28 funded projects expected to be announced Report P34
  • 31 March 2027: CRP funding to be fully committed; deadline currently under discussion with MHCLG Report 2.4
  • April 2027: Projected construction start date for the Former Royal Hotel, Rothesay Report P69
  • By end March 2028: RCGF 2027/28 grant drawdown and project delivery deadline (1 year) Report P34

Plain English for the jargon

  • RCGF: Regeneration Capital Grant Fund, a Scottish Government grant programme
  • CRP: Community Regeneration Partnership, UK Government funding replacing the Levelling Up Partnership programme
  • RGD: Rural Growth Deal, a UK Government growth deal programme for the region
  • CARS: Conservation Area Regeneration Scheme
  • HES: Historic Environment Scotland
  • EOI: Expression of Interest, the first stage of the RCGF application process
  • BID: Business Improvement District, a levy-funded body for a defined area
  • ICCEF: Islands Cost Crisis Emergency Fund, Scottish Government support for island local authorities
  • CNI: Carbon Neutral Islands, a Scottish Government programme
  • MHCLG: Ministry of Housing, Communities and Local Government
  • SFT: Scottish Futures Trust, which administers the ICCEF on behalf of the Scottish Government
  • HIE: Highlands and Islands Enterprise
  • RSL: Registered Social Landlord
  • SAMS: Scottish Association for Marine Science
  • P&R: Policy and Resources Committee of Argyll and Bute Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

Decision The Environment, Development and Infrastructure Committee – 1. noted the current progress contained within the report; 2. noted the projects identified in paragraph 4.5 of the report which form the basis of Stage 1 expression of interest funding bids to the Scottish Government’s Regeneration Capital Grant Fund and that any projects that are successful at Stage 1 would require more detailed Stage 2 funding bids to be submitted later in the year; and 3. noted that further updates relating to pending funding bids would be brought back to the Environment, Development and Infrastructure Committee in due course to update Members. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated July 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee, 16 pages

Executive summary

1.1The purpose of this report is to update the Environment, Development and Infrastructure Committee on progress with the large-scale, externally funded project work of the Transformational Projects and Regeneration Team, and to highlight key issues that may impact on the successful delivery of economic development capital projects.

1.2The last update report was considered by the Environment, Development and Infrastructure Committee in March 2026.

1.3The team is currently responsible for the delivery and or management of projects and associated grants with a cumulative value of over £100m. It should be noted that following completion of each project, the team continues to have the responsibility for the monitoring and final drawdown and reporting up until the end of the 12-month defects period or beyond depending on conditions on the respective grant contracts.

1.4The Transformational Projects and Regeneration Team also includes responsibility for delivery of the Council’s Rural Growth Deal (RGD) Programme and Community Regeneration Partnership Funding (CRP) from the UK Government.

1.5Members are asked to note that the grant funding landscape and delivery of capital projects remains extremely challenging due to cost pressures and the fixed nature of project budgets. The Transformational Projects and Regeneration Team will continue to respond to emerging Government policy priorities and future external grant, funding opportunities.

Recommendations

It is recommended that the Environment, Development and Infrastructure Committee:-

i. Consider the current progress updates contained within the report. ii. Note the projects identified in paragraph 4.5 which form the basis of Stage 1 expression of interest funding bids to the Scottish Government’s Regeneration Capital Grant Fund. Further note that that any projects that are successful at Stage 1 will require more detailed Stage 2 funding bids to be submitted later in the year. iii. Note that further updates relating to pending funding bids will be brought back to the Environment, Development and Infrastructure Committee in due course to update Members. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE

DEVELOPMENT AND ECONOMIC 9 OCTOBER 2026 GROWTH

TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE SCALE PROJECT UPDATE REPORT

2.0INTRODUCTION

2.1The purpose of this report is to update the Environment, Development and Infrastructure Committee on progress with the large-scale, externally funded project work of the Transformational Projects and Regeneration Team.

2.2The Transformational Projects and Regeneration Team sits within the Council’s Development and Economic Growth Service and works region-wide. The team has a particular focus on ‘place’, heritage regeneration, the creative industries, renewables, islands, and manages a diverse range of capital projects and external grants. The team works closely with colleagues across the Council, communities, businesses, public agencies, third sector organisations, town centre heritage building owners, and the owners of vacant business property to realise positive change for our communities.

2.3The Transformational Projects and Regeneration Team also includes responsibility for delivery of the Council’s Rural Growth Deal (RGD) Programme and Community Regeneration Partnership (CRP) Funding from the UK Government.

2.4CRP funding replaces the Levelling Up Partnership programme and totals £20.34m for projects in Argyll and Bute with funding to be fully committed by 31 March 2027.

3.1It is recommended that the Environment, Development and Infrastructure Committee:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM: LARGE SCALE PROJECT UPDATE REPORTReport 16 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
IP
Councillor Iain PatersonMember, expected
JP
Julieann PenmanSecretary, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, expected
GH
Councillor Graham HardieMember, expected
WH
Councillor Willie HumeMember, expected
AK
Councillor Andrew KainMember, expected
JL
Councillor Jim LynchMember, expected
TM
Councillor Tommy MacPhersonMember, expected
IM
Councillor Ian MacQuireMember, expected

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM - LARGE SCALE PROJECT UPDATE REPORTThis decision
  2. Transformational projects and regeneration team - large scale project update reportNoted
  3. Transformational projects and regeneration team - large scale project update reportNoted
  4. Transformational projects and regeneration team - large scale project update reportNoted
  5. Transformational projects and regeneration team - large scale project update reportNoted
  6. Transformational projects and regeneration team - large scale project update reportNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies