UPDATE ON ARGYLL AND BUTE COUNCIL'S ECONOMIC STRATEGY ACTION PLAN

Noted Committee 1 paper

AI summaryArgyll and Bute councillors backed a new cluster-based approach to delivering the council's Economic Strategy Action Plan and asked for a fully revised 2026-2029 plan in December 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSix new clusters replace previous delivery model
MoneyMultiple funding streams, multi-million poundsRGD £70m, UKSPF, CRP £20m cited
What happens nextRevised ESAP to December 2026 committeeFull plan for 2026-2029 to be presented
Who it affectsResidents, businesses, island communitiesAcross all six cluster areas of Argyll and Bute

What was decided

The committee noted progress on 2025/26 ESAP actions and the revised short-term success measures for 2026-2029 set out in Appendix 1. Report 1.1, 3.1

Members endorsed a new cluster approach to the ESAP, organised around six clusters: renewable and green energy, blue economy and marine, marine research, innovation, digital and AI, defence and engineering, food and drink including whisky regions, and visitor economy and hospitality. Report 4.5, P27

A fully revised ESAP covering 2026-2029 will be brought to the committee in December 2026, using the council's Connect for Success approach across the four pillars of people, place, planet and prosperity. Report 1.2, 4.6, P7

Why

The plan needs refreshing to respond to the Community Wealth Building (Scotland) Act 2026 and global economic uncertainty, and to focus on place-based investment of scale. Report 2.1, 4.1

Many 2025/26 actions depended on annual funding and will not be fully realised until the medium term, requiring a new delivery model built around natural economic clusters. Report 1.3, 4.2, 4.3

Resources are limited, so the council wants to concentrate on key interventions that maximise impact for residents, businesses and communities. Report 4.9

What happens next

A collaborative meeting on the new ESAP approach was held on 16 September 2026, with further development of SMART actions around the cluster models to follow. Report P37

The Workforce Argyll and Bute Road Map will be finalised in late autumn 2026 and reported to the committee before the end of the calendar year. Report P38

Findings of the Visitor Levy Scheme consultation, which closed on 5 October 2026, will be collated in late autumn 2026, with the fully revised 2026-2029 ESAP prepared for the committee in December 2026. Report P39, P40

The money

  • £292,290.24 Total investment in the Argyll and Bute Community Regeneration Partnership projects Report P79
  • £20m Community Regeneration Partnership funding announced November 2025 Report P79
  • £98,240 UK Shared Prosperity Transition Fund support for further Community Regeneration Partnership projects Report P79
  • £70m Rural Growth Deal investment over 10 years Report P79
  • £470k CLLD Fund support to 20 projects during 2025/26 Report P80
  • £878k Total project cost of CLLD-supported projects, leveraging £408k match funding Report P80
  • £200m Provisional UK Government levelling up allocation referenced for Argyll and Bute transport priorities Report P83
  • £7m RSAP funding for STEM Hub North 2026/27 Report P74
  • £762,500 Match funding into STEM Hub North 2026/27 Report P74
  • £450k Funding for Short-term Let Control Zones consultation Report P84
  • £5m Community Regeneration Fund housing-related projects from UK Government Report P84
  • £3m HEEPS grant secured for this financial year Report P87
  • £240,127 UKSPF-funded business support grants committed and to be spent by end of March 2027 Report P91
  • £5m RGD Town Infrastructure Fund allocation for Colgrain Report P92
  • £200k RCGF planning start funding for Kintyre Seasports, with £800k further RCGF support Report P93

Options considered

  • Rejected: Continue with the existing 2025-2028 ESAP delivery structure. No longer sufficient to respond to new legislation and economic uncertainty Report 2.1, 4.1
  • Chosen: Adopt a new cluster approach organised around six place-based clusters. Connects sustainable economic assets into mutually reinforcing clusters to attract investment of scale Report 4.4, 4.5, P27
  • Chosen: Embed a Community Wealth Building approach wherever practicable. Limited resources require focus on inclusive wellbeing economy interventions Report 4.9

Implications

  • Financial: Ongoing external funding will be required to deliver the strategic intent. Report 6.2
  • Risk: Buy-in by partner agencies and stakeholders may be difficult due to uncertainty around future funding streams, with many budgets still set annually. Report 6.6
  • Legal: All appropriate legal implications have been considered, including the Fairer Scotland Duty under Part 1 of the Equality Act 2010. Report 6.3
  • Equalities: All activities will comply with Equal Opportunities policies and obligations, and with the council's Consumer Duty. Report 6.9, 6.10
  • Climate: Economic actions under the planet pillar have been framed to address the net zero transition agenda. Report 6.7
  • Staffing: Staff will be required to support delivery of the actions to realise outcomes for residents and communities. Report 6.4
  • Other: Actions have been and will be delivered across the whole of Argyll and Bute including the island communities. Report 6.11

Who and where

  • Residents, businesses and communities across Argyll and Bute, including island communities Report 6.11, 4.9
  • The Argyll and Bute Community Planning Partnership and member organisations Report 1.3
  • External partners including Highlands and Islands Enterprise, Scottish Enterprise, Skills Development Scotland, UHI Argyll, SAMS and DYW Report 1.3, P69, P73, P74
  • Small and medium-sized businesses in the renewable energy, marine, defence, food and drink, and visitor economy sectors Report 4.4, P27, 4.9

Timeline

  • 28 August 2025: Report by Executive Director for Development and Economic Growth dated for committee Report P58
  • December 2025: Mobile phone coverage mapping to be concluded Report P83
  • Late autumn 2026: Workforce Argyll and Bute Road Map to be finalised and Visitor Levy consultation findings to be collated Report P38, P39
  • End of 2025/26 (March 2026): UK Shared Prosperity Fund core monies concluded; HIE Graduate Placement programme funded by UKSPF to be concluded Report 4.3, P71
  • 30th April 2026: ABEP Annual Investment Plan 2026/27 bids to be submitted to Scottish Government Report P75
  • June 2026: Community Wealth Building workshop at Senior Leadership Forum Report P81
  • September 2026: Employers' Forum MS Teams engagement event held 4-5 p.m. Report P69
  • 16 September 2026: Collaborative meeting within Development and Economic Growth service on the new ESAP approach Report P37
  • 5 October 2026: End of 12-week Visitor Levy Scheme consultation Report P39
  • 9 October 2026: Environment, Development and Infrastructure Committee meeting considering ESAP update Report P9
  • December 2026: Fully revised ESAP 2026-2029 to be presented to the committee Report P7, P40
  • By end of 2026: Helensburgh Strategic Development Framework to be completed Report P84
  • By end of 2025/26: CRP funding of £20m concludes (announced November 2025) Report P79
  • By 31st March 2027: Tailored modern apprenticeship scheme work and council invest-to-spend commitment; Active Travel Strategy to be approved Report P70, P83
  • By 31st March 2028: Foundation Apprenticeship programmes to increase by 10% and uptake by 15%; Graduate Apprenticeship uptake to rise 10%; STEM Hub South to be delivered; Employers' Forum to be established Report P71, P74, P69
  • By March 2029: Full Business Case for the Colgrain Business Park to be finalised; RSAP four Full Business Cases to be approved by government Report P74, P92
  • By 2027: Oban Airport Business Case for the West Coast UAV Logistics and Training Hub to be approved; Rothesay Pavilion to be completed Report P87, P93
  • By 2028-2029: Construction and Engineering Renewables Centre (CERC) enhancement at UHI Argyll College to be delivered Report P74

Plain English for the jargon

  • ESAP: Economic Strategy Action Plan, the council's delivery plan for its Economic Strategy 2024-2034
  • ABEP: Argyll and Bute Employability Partnership, the local employability partnership
  • CPP: Community Planning Partnership, local partnership of public bodies and other agencies
  • RSAP: Rural Skills Accelerator Programme, a STEM education and skills programme
  • CLLD: Community Led Local Development, a community-driven local development approach funded by the Scottish Government
  • CRP: Community Regeneration Partnership, a regeneration funding programme
  • CWB: Community Wealth Building, a local economic development approach underpinned by the Community Wealth Building (Scotland) Act 2026
  • RGD: Rural Growth Deal, a multi-year investment programme for the region
  • RCGF: Regeneration Capital Grant Fund, a Scottish Government fund
  • UKSPF: UK Shared Prosperity Fund, a UK Government fund for local growth
  • SAMS: Scottish Association for Marine Science, a research organisation based in Oban
  • HEEPS: Home Energy Efficiency Programme for Scotland
  • CERC: Construction and Engineering Renewables Centre, a planned UHI Argyll facility
  • HIE: Highlands and Islands Enterprise, the regional development agency
  • SE: Scottish Enterprise, the national economic development agency
  • DYW: Developing the Young Workforce, the Scottish youth employment programme
  • TIF: Tax Incremental Financing, a funding model that borrows against future tax income
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Decision The Environment, Development and Infrastructure Committee – 1. noted the progress on actions for 2025/26 through the delivery of the Economic Strategy Action Plan, 2025-2028, which included current and revised short term success measures for the next three years, 2026-2029, as outlined in Appendix 1 of the report; 2. endorsed the new cluster approach to the Economic Strategy Action Plan going forward; and 3. agreed that a fully revised Economic Strategy Action Plan for 2026-2029 would be presented to members of the Environment, Development and Infrastructure Committee at the meeting in December 2026. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated 28 August 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee, 35 pages

Executive summary

1.1The purpose of this paper is to provide members of the Environment, Development and Infrastructure Committee with an update on the progress on actions for 2025/26 (see Appendix 1) from the in-year delivery of the Economic Strategy Action Plan (ESAP), 2025-2028. The paper then goes on to provide proposals for a new strategic approach going forward for the next three years, 2026-2029 and beyond to 2034.

1.2The revised approach retains the four strategic pillars of people, place, planet and prosperity while introducing a stronger focus on place-based cluster models throughout 2026/27, designed to complement the priorities of Argyll and Bute Council, existing and revised action plans and route maps to encourage investment of scale. As it’s an Economic Strategy for the whole council, the Council’s Connect for Success approach will be adopted to drive Argyll and Bute’s economic growth agenda.

1.3A principal requirement of the ESAP is that the actions are SMART (Specific, Measurable, Achievable, Realistic, Time-bound) and delivers opportunities that drive inclusive, economic growth and a fair and inclusive wellbeing economy. Many of the actions within the ESAP in Appendix 1 will not be fully realised until the medium term, where their delivery depends on strong collaboration and a joined-up approach, working closely with internal council colleagues across services, the Argyll and Bute Community Planning Partnership (CPP), both Governments, partner agencies and key stakeholders across Argyll and Bute at both a regional and national level.

1.4It is recommended that Members of the Environment, Development and Infrastructure Committee:

• Note the progress on actions for 2025/26 through the delivery of the Economic Strategy Action Plan, 2025-2028, which includes current and revised short term success measures for the next three years, 2026-2029, as outlined in Appendix 1.

• Endorse the new cluster approach to the Economic Strategy Action Plan (ESAP) going forward.

• Agree that a fully revised Economic Strategy Action Plan for 2026-2029 is presented to members of the Environment, Development and Infrastructure Committee at the meeting in December 2026.

1 ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE

DEVELOPMENT AND ECONOMIC GROWTH 9 OCTOBER 2026

UPDATE ON ARGYLL AND BUTE COUNCIL’S ECONOMIC STRATEGY ACTION PLAN

2.0INTRODUCTION

2.1A successful economy is essential to delivering and achieving many of our council priorities, including the delivery of worker housing, delivering inclusive economic growth and population sustainability – all of which contribute to our quality of life as a place to live, work, learn and visit. With the pace national legislative changes, such as the Community Wealth Building (Scotland) Act 2026 and global economic uncertainty accelerating, there is a clear need to update our Economic Strategy Action Plan (ESAP) and reaffirm our strategic intent over the next three years, 2026-2029.

2.2A key requirement of ESAP is that it is an ongoing working document that contains actions that are SMART (Specific, Measurable, Achievable, Realistic, Time-bound) and delivers opportunities that drive economic growth and a fair and inclusive wellbeing economy across the four strategic pillars: people, place, planet and prosperity. A refresh of SMART actions will be part of the new strategic approach.

Recommendations

3.1It is recommended that Members of the Environment, Development and Infrastructure Committee:

• Note the progress on actions for 2025/26 through the delivery of the Economic Strategy Action Plan, 2025-2028, which includes current and revised short term success measures for the next three years, 2026-2029, as outlined in Appendix 1.

• Endorse the new cluster approach to the Economic Strategy Action Plan (ESAP) going forward.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UPDATE ON ARGYLL AND BUTE COUNCIL'S ECONOMIC STRATEGY ACTION PLANReport 35 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
IP
Councillor Iain PatersonMember, expected
JP
Julieann PenmanSecretary, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, expected
GH
Councillor Graham HardieMember, expected
WH
Councillor Willie HumeMember, expected
AK
Councillor Andrew KainMember, expected
JL
Councillor Jim LynchMember, expected
TM
Councillor Tommy MacPhersonMember, expected
IM
Councillor Ian MacQuireMember, expected

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. UPDATE ON ARGYLL AND BUTE COUNCIL'S ECONOMIC STRATEGY ACTION PLANThis decision
  2. Argyll and bute outcomes and improvement plan - priorities updateNoted
  3. Argyll and Bute Climate Action NetworkNoted
  4. Argyll and bute improvement plan - priorities updateNoted
  5. Argyll and bute improvement plan - priorities updateNoted
  6. Argyll and bute harbour board workplanNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies