Resolved
RESOLVED that the Register and progress against current corporate risks, be received and noted. Reason: To prioritise and manage the mitigation of risk in order that the Council can achieve its objectives.
Audit Committee noted this item on Monday 11 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Register and progress against current corporate risks, be received and noted. Reason: To prioritise and manage the mitigation of risk in order that the Council can achieve its objectives.
For Audit Committee to review the Corporate Risk Register and the analysis of movement in risk and mitigating actions in respect of those risks.
Recommendation(s)
Audit Committee are asked to note the current significant items on the Corporate Risk Register and to consider whether any further immediate actions are necessary to mitigate those risks.
Reasons for Recommendation(s)
To prioritise and manage the mitigation of Risk in order that the Council can achieve its objectives
Alternative Options Considered (with reasons why not adopted)
None
Detailed Information
Context/Background
All strategic risk at corporate and directorate level is incorporated into the Pentana performance system to enable quarterly updates at the same time as updating performance, therefore enhancing the consideration of risk in the delivery of services. The Risk Template was revised to incorporate new columns to ensure we identify:- - business continuity links - ability to influence - actions required and milestones separate to actions completed
The full corporate risk register is appended to this report.
Corporate Risk Register
Risk Rating Summary
2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Qu 4 Qu 4 Qu4 Qu4 Qu4 Qu4 Qu3 Significant 23 15 10 10 9 7 4 Medium 10 11 9 7 6 10 10 Low 1 8 7 5 2 3 10 Total 34 34 26 22 17 20 24
Our approach is to focus our review of those risks where we believe that we have a high ability to influence and therefore seek ways to reduce or mitigate the risk. Current assessments indicate that significant risks continue to slightly reduce whilst the total number of Corporate Risks has increased with the introduction of risks related to Brexit (rated low) and 3 new risks in respect of the leisure centre of which 2 are low and one is medium risk. The risk involving Overpayments for housing benefit has also been removed as the only control over the level of overpayments we have is the level of Local Authority error Overpayments, which represents less than 10% of the total, and all of that is returned back from the Government therefore there is no loss to the Council
New additional risks are currently being considered for incorporation into the Corporate Risk Register:- workforce planning, in respect of risks relating to resilience, recruitment and retention and succession planning job families implementation risks
Those significant risks remaining are (* mitigatable, and no improvement in last 12 months):- Ethical framework * Failure to identify savings required by Medium Term Financial Strategy (MTFS)* Level of central government funding
Corporate Risk Strategy
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate RiskReport | 241 KB | DownloadRead as text |
PDF |
Corporate Risk Register Qu 3 2018/19Report | 524 KB | Download |
PDF |
Corporate Risk StrategyReport | 633 KB | Download |
Follow Audit Committee at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... | Noted | Open |
| 25 Jun 2026 | Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... | Decided | Open |
| 25 Jun 2026 | FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. | Noted | Open |
| 25 Jun 2026 | Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... | Approved | Open |
| 25 Jun 2026 | Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.