RESOLVED that a) the design development completed to date regarding the second swimming pool facility at Hucknall Leisure Centre, be received and noted; b) approval be given to the commencement of the procurement stage of the project via an open tender procedure supported by Nottingham City Council Procurement Unit; c) delegation authority to award the capital works build contract, be granted to the Chief Executive Officer, in conjunction with the Corporate Finance Manager (and Section 151 Officer) and the Portfolio Holder for Leisure, Health and Wellbeing, subject to the project remaining within the Capital Programme approved budget; d) approval be given for Everyone Active to complete the Wet Leisure Village transformation at Hucknall Leisure Centre as part of the overall development. d)
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update the Cabinet on the design development of the Hucknall Swimming Pool extension which forms part of the overall £22.5m investment in leisure services across the District.
To seek approval from Cabinet to commence procurement of the Capital Works elements of the project based upon the RIBA 3 Design and latest Cost Estimates.
To obtain delegated authority for the Chief Executive Officer in conjunction with the Corporate Finance Manager to conclude the procurement exercise and appoint the successful contractor subject to the award being within the Capital Programme approved budget.
Recommendation(s)
1. Cabinet is recommended to note the design development completed to date regarding the second swimming pool facility at Hucknall Leisure Centre. 2. Cabinet is recommended to approve the commencement of the procurement stage of the project via an open tender procedure supported by Nottingham City Council Procurement Unit. 3. Cabinet is recommended to approve the delegation to award the capital works build contract to the Chief Executive Officer in conjunction with the Corporate Finance Manager, subject to the project remaining within the Capital Programme approved budget. 4. Cabinet is recommended to approve Everyone Active complete the Wet Leisure Village transformation at Hucknall Leisure Centre as part of the overall development. Reasons for Recommendation(s)
Cabinet will recall that the development of a second swimming pool facility at Hucknall Leisure Centre is a key deliverable of the Leisure Transformation Programme which the Council is delivering.
The Council is progressing with the design development of the second swimming pool facility at Hucknall and has been working with Everyone Active as the leisure services provider throughout.
Design Development has now achieved RIBA 3 Stage which has enabled the Council to submit a Planning Application for the works. Along with the addition of the second swimming pool facility the development will also see the transformation of the wet change facilities at Hucknall into a modern ‘Village’ style solution along with the installation of electric vehicle charging points and energy efficient solar panels on the roof of the new pool.
Alternative options considered
Do not develop a second swimming pool facility at Hucknall (Not Recommended) Swimming lessons, involvement and general wellbeing has become a more pressing issue following the COVID-19 pandemic. Swimming activities at Hucknall Leisure Centre are already near to pre- pandemic levels with little current opportunity to increase engagement and use of the centre without this further development.
The second swimming pool facility at Hucknall Leisure Centre was a stated Council requirement at the tender stage for the Leisure Operating Contract. The commercial returns for the operator would be impacted should this development not be completed, this in turn will have revenue implications for the Council as the Leisure Operating Contractor will have the ability to reforecast the Management Fee through to 2031.
Do not approve progress through to the procurement stage (Not Recommended) The Council has been working diligently with its Design Team and the Leisure Operator to ensure the second swimming pool is developed in line with the current programme. Planned opening of the pool in November 2022 is predicated on the procurement process being concluded before the end of the 2021 calendar year.
In not progressing with the procurement the Council would delay the project through to 2023 before the facility may be ready to open.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.