RESOLVED that a) the content of the report be received and noted; b) the realignment of £0.5m from the Kirkby Leisure Centre capital project code to the Hucknall second swimming pool capital project code, to support the project through to completion, be approved. Reason: To ensure that Cabinet is updated on progress with delivery of the leisure transformation programme and to enable the Council to facilitate future projects in a timelier manner.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet on the implementation of the Leisure Transformation Programme which is bringing forward significant capital investment of £22.5m to Council owned leisure facilities including the Kirkby Leisure Centre new build and capital improvements at Lammas Leisure Centre and Hucknall Leisure Centre, including the second swimming pool.
To request that within the overall Council approved budget for Leisure Transformation, Cabinet approves the realignment of £0.5m from the Kirkby Leisure Centre budget to support the Hucknall second swimming pool project. The overall Council approved capital budget for the Leisure Transformation programme will not be exceeded.
Recommendation(s)
1. Cabinet is recommended to note the contents of the report. 2. Cabinet is recommended to approve the realignment of £0.5m from the Kirkby Leisure Centre capital project code to the Hucknall second swimming pool capital project code to support the project through to completion.
Reasons for Recommendation(s)
To ensure that Cabinet is updated on progress with delivery of the programme including the need to alter the design solution to Hucknall second swimming pool which has resulted in increased costs and delayed completion. Alternative Options Considered
Not to support the internal transfer of £0.5m from the Kirkby Leisure Centre budget to the Hucknall second swimming pool budget. This is not recommended as the Hucknall Leisure Centre project will overspend its budget allowance whilst Kirkby Leisure Centre will remain with a forecast underspend against budget provisions.
Detailed Information
Transformation Investments
The Kirkby Leisure Centre project has now completed Phase 1, with the opening of the new Centre. The project continues to deliver against the indicators with the demolition of Festival Hall and the new car park due to open during February 2023.
The project continues to remain within the £15.5m approved budget and it is forecast that the project will achieve an outturn cost of £14.5m with a likely underspend of £1m.
This underspend already takes into account the improved specification of PV solar panels which have been installed on the roof as well as various improvements in the internal finishes compared with the original design.
The second swimming pool at Hucknall Leisure Centre achieved start on site in early 2022. Following the excavation and detailed analysis of the sub-ground conditions along with further inspections on the existing structure, a revision to the pool construction was proposed by contractor Kier North & Scotland. The Council’s consultants have confirmed the need for this variation which will see the completion delayed by 10 weeks with the Centre complete in Quarter 1 of the 2023/24 financial year.
The delays and varied construction detail will increase costs onsite and the overall project budget of £3.5m. Realigning £0.5m of the identified underspend at Kirkby Leisure Centre will enable the Hucknall Leisure Centre second swimming pool to be completed whilst remaining within the overall approved capital programme budget for the Leisure Transformation programme.
Implications
Corporate Plan: The Leisure Transformation Programme continues to deliver on the Council’s Corporate Plan, to replace the ageing Festival Hall facility, the addition of new and improved facilities at both Lammas and Hucknall Leisure Centres to deliver activities which support the Be Healthy Be Happy priorities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.