RESOLVED that the following updates be received and noted: a) progress towards opening the Kirkby Leisure Centre during summer 2022; b) the series of capital improvements across the Hucknall and Lammas Leisure Centres; c) progress in bringing forward a second swimming pool facility at Hucknall Leisure Centre; d) the continued strong recovery of usage and membership across the existing centres, now surpassing pre pandemic levels.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To update Cabinet as to the implementation of the Leisure Transformation Programme which is bringing forward significant capital investment of £22.5m to Council owned leisure facilities across the District.
To update Cabinet as to progress with the development of the new Kirkby Leisure Centre and specific capital improvements across the Hucknall and Lammas Leisure Centres.
To update Cabinet as to the recovery in the usage and membership of the leisure facilities operated by the Council’s delivery partner Everyone Active.
To update Cabinet to the progress in forwarding the second swimming pool facility at Hucknall Leisure Centre.
Recommendation(s)
1. Cabinet is recommended to note the progress towards opening the Kirkby Leisure Centre during summer 2022. 2. Cabinet is recommended to note the series of capital improvements across the Hucknall and Lammas Leisure Centres. 3. Cabinet is recommended to note progress in bringing forwards a second swimming pool facility at Hucknall Leisure Centre. 4. Cabinet is recommended to note the continued strong recovery of usage and membership across the existing centres, which now surpass pre pandemic levels Reasons for Recommendation(s)
Cabinet will recall that the Council committed to the completion of its Leisure Transformation Programme during the early stages of the COVID-19 pandemic. The Council was adamant that the new facility at Kirkby Leisure Centre replacing The Festival Hall was needed immediately as was the need to reprocure the Leisure Operating Contract which was due for renewal in summer 2021.
Everyone Active were appointed by the Council on an initial 10 year management contract with the option for the Council to extend for a further 5 years based upon performance.
Everyone Active were appointed following a detailed multistage procurement exercise supported by Nottingham City Council Procurement unit. Everyone Active have worked with the Council diligently since being appointed with a view of increasing stakeholder and community engagement. Membership numbers and leisure centre usage have now surpassed pre pandemic levels.
As part of the new Leisure Operating Contract, the Council and Everyone Active committed jointly to bring forwards a series of new capital investments to existing leisure centres in Hucknall and at the Lammas in Sutton. These capital investments are nearing completion and are having a positive impact on user numbers to the applicable centres.
Kirkby Leisure Centre commenced onsite in 2021 following approval to appoint Kier (North & Scotland) to complete the project. Works are due to be complete to the new centre this summer with Festival Hall subsequently demolished and replaced by off street parking, including electric vehicle charging points.
Alternative Options Considered None as the report is for noting.
Detailed Information
Everyone Active were appointed on a 10 year management agreement following a procurement process overseen by Nottingham City Council. They have increased their marketing and engagement strategies, including new ways of communicating with potential and new users. Membership levels and usage across the existing sites (including Festival Hall which is due for imminent demolition) are now above pre pandemic levels.
Fitness members across the three sites now number 6436. This compares to 5703 at the start of the pandemic. An increase in membership of 12.8% compared with pre pandemic figures has been recorded for the end of December 2021 period.
Swimming lessons also continue to outperform pre pandemic levels with 3334 session bookings compared with 3035, a 9.8% increase has been recorded for the end of December 2021 period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.