RESOLVED that a) the progress for Future High Streets Fund and Towns Fund projects, as presented, be received and noted; b) Council be recommended, subject to Department for Levelling Up, Housing and Communities (DLUHC) approval, to make an amendment to the Capital Programme values for the Towns Fund and Future High Streets Fund schemes as outlined in the report; c) the receipt of Public Sector Decarbonisation Scheme (PSDS) Phase 3b funding, subject to the Council’s bids being successful and the engagement with Mace Limited under the Scape ‘Place Shaping’ Framework (single supplier) to deliver the projects, be approved; d) Council be recommended, following receipt of funds, to agree that Section 106 monies be included on the capital programme as outlined in the report; e) the Council’s successful bid for Cyber Security funding be noted and the £125k funding be duly accepted. Reason: To ensure that Cabinet is kept updated on progress with all the funding programmes and to ensure that projects and spend are delivered in accordance with the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To ensure that Cabinet is kept updated on funding allocations and progress of funded programmes.
To consider and approve an adjustment to the Capital Programme for the Towns Fund and Future High Streets Fund projects.
To add additional Public Open Space Section 106 contributions to the Capital Programme. Recommendation(s)
1. To note the progress for Future High Streets Fund and Towns Fund projects.
2. To recommend to Council, subject to Department for Levelling Up, Housing and Communities (DLUHC) approval, amendment of the Capital Programme values for the Towns Fund and Future High Streets Fund schemes as outlined in the report
3. To approve the receipt of Public Sector Decarbonisation Scheme (PSDS) Phase 3b funding, subject the Council’s bids being successful, and approve the engagement with Mace Limited under the Scape ‘Place Shaping’ Framework (single supplier) to deliver the projects.
4. To recommend to Council, following receipt of funds, that Section 106 monies be included on the capital programme as outlined in the report.
5. To note the Council’s successful bid for Cyber Security funding and to approve acceptance of the £125k funding.
Reasons for Recommendation(s)
1. To ensure that Cabinet is kept updated on progress with the funding programmes. 2. To ensure that projects and spend within the funding programmes are delivered within the set timeframes and programme budget envelope. 3. To ensure delivery of the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment. 4. To ensure funding streams are delivered collaboratively and effectively. 5. To note the Council’s successful bid for Cyber Security funding and to approve acceptance of the £125k funding.
Alternative options considered
1. Not to approve the re-alignment of funds on the Towns Fund and Future High Streets programmes. Not re-aligning the funds will mean that projects cannot be delivered due to budget shortfalls. Not recommended.
2. Not to approve the allocation of S106 funding on the capital programme. Not allocating the funds will mean that public open space improvement projects cannot be delivered. Not recommended.
3. Not to accept the receipt of PSDS3b funding will jeopardise the Council’s ability to fund carbon reduction measures to its non-domestic assets and not meet its carbon reduction targets. Not to mobilise the procurement and delivery of the projects imminently will jeopardise delivery in the required timescales.
4. Not to accept the £125k for cyber security to further improve the Council’s resilience against potential cyber security attacks. Not recommended. Detailed Information
1) Funded Programme and Projects Update
1.1Future High Streets Fund The four projects are progressing with the first construction contract commencing on the Sutton Low Street projects and design teams now appointed and developing all projects. Planning approvals have been secured for:
• 14 Low Street Refurbishment • 9-11 Low Street Refurbishment • 70-78 High Pavement Refurbishment
A planning application will be submitted in the autumn for the Fox Street and Portland Square project.
Branding development has been completed for the High Pavement Business Hub, Maker Space and Theatre projects.
Procurement for main contract work activities are due to commence in early autumn for the following projects:
• 9-11 Low Street Refurbishment • 70-78 High Pavement Refurbishment • Fox Street and Portland Square public realm.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.