RESOLVED that a) progress in relation to the Future High Streets Fund (FHSF), Towns Fund, Levelling Up Fund and UK Shared Prosperity Fund (UKSPF) programmes, be received and noted; b) the Council’s successful bid for Levelling up funding be noted and approval be given to the acceptance of the £3.1 million of funding; c) Council be recommended to approve the following: · the five-year Green Space and Public Realm Investment Plan, subject to receipt of funds; · following receipt of funds, that income from Social Value contributions, grants and/or Section 106 funding be included in the Capital Programme, as outlined in the report. Reasons: 1. To ensure that Cabinet is kept updated on progress with the funding programmes. 2. To ensure that projects and spend within the funding programmes are delivered within the set timeframes and programme budget envelope. 3. To ensure funding is spent collaboratively and effectively. 4. To note the Council’s successful bid for Levelling Up funding and to approve acceptance of the £3.1 million. 5. To ensure continued delivery of improvements in parks, green spaces and public realm with a rolling programme of investment.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To ensure that Cabinet is kept updated on funding allocations and progress of funded programmes.
To consider and approve the five-year Green Space and Public Realm Investment Plan.
To recommend to Council the addition of further Public Open Space Section 106 contributions to the Capital Programme. Recommendation(s)
1. To note the progress for Future High Streets Fund (FHSF), Towns Fund, Levelling Up Fund and UK Shared Prosperity Fund (UKSPF) programmes.
2. To note the Council’s successful bid for Levelling up funding and to approve acceptance of the £3.1 million of funding.
3. To recommend to Council the approval of the five-year Green Space and Public Realm Investment Plan, subject to receipt of funds.
4. To recommend to Council, following receipt of funds, that income from Social Value contributions, grants and / or Section 106 funding be included on the Capital Programme as outlined in the report.
Reasons for Recommendation(s)
1. To ensure that Cabinet is kept updated on progress with the funding programmes. 2. To ensure that projects and spend within the funding programmes are delivered within the set timeframes and programme budget envelope. 3. To ensure funding is spent collaboratively and effectively. 4. To note the Council’s successful bid for Levelling Up funding and to approve acceptance of the £3.1 million. 5. To ensure continued delivery of improvements in parks, green spaces and public realm with a rolling programme of investment.
Alternative options considered
1. Not to accept the £3.1 million funding from the Levelling Up Fund as match funding towards TF14 Science Discovery and Planetarium project - not recommended. The funding will significantly contribute towards the funding strategy to deliver the project and without the funding the project will not be able to progress.
2. Not to approve the five-year Green Space and Public Realm Investment Plan will result in the Council not being able to suitably resource investment where required to maintain high standards and safety standards of the green spaces and public realm.
3. Not to approve the Section 106 Public Open Space income being added to the Capital Programme: will result in the Council not being able to deliver the Corporate Plan priority of improvements in parks, green spaces and public realm. Detailed Information Funding Programmes
1. Future High Streets Fund
14 Low Street renovation work is progressing on site and remains forecast to complete within budget. The project completion has slipped by two weeks due to some amendments to the works during the contract phase and is estimated to complete March 2023.
9-11 Low Street and High Pavement projects have completed the detailed design and cost planning stages and remain within the expected budget envelope. The projects have jointly been put out to tender with the tender outcome due to be returned by early February. The estimated project completion is October 2023.
The Theatre Project design team is appointed and is progressing the design development within the envelope of funding secured including the potential re-allocation of £500k from the Towns Fund Programme. The Towns Fund allocation of £500k is subject to DLUHC approval.
The Fox Street project has completed the detailed design and cost planning stages and remains within the expected budget envelope. The project tender has been published and is due to close in early February.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.