RESOLVED that a) progress with the Future High Streets Fund, Towns Fund and UK Shared Prosperity Fund programmes, as presented, be received and noted; b) following receipt of funds, Council be recommended to include Section 106 monies on the Capital Programme; c) following identification of suitable funding for The Wharf – Environmental improvements project, Council be recommended to include it on the Capital Programme; d) progress with the Public Sector Decarbonisation Scheme (PSDS) programme, be also noted. Reasons: 1. To ensure that Cabinet is kept updated on progress with the regeneration programmes. 2. To ensure that projects and spend are achieved within the set timeframes and programme budget envelopes. 3. To ensure delivery of the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment. 4. To ensure funding streams are delivered collaboratively and effectively.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To ensure that Cabinet is kept updated on funding allocations, progress of funded programmes and bids for external funding.
To add Public Open Space Section 106 contributions to the Capital Programme.
Recommendation(s)
1. To note the progress for Future High Streets Fund, Towns Fund and UK Shared Prosperity Fund programmes.
2. To recommend to Council, following receipt of funds, that Section 106 monies be included on the Capital Programme.
3. To recommend to Council that following identification of suitable funding The Wharf – Environmental improvements project be included on the Capital Programme.
4. To note the progress for the Public Sector Decarbonisation Scheme (PSDS) programme. Reasons for Recommendation(s)
1. To ensure that Cabinet is kept updated on progress with the regeneration programmes. 2. To ensure that projects and spend are achieved within the set timeframes and programme budget envelopes. 3. To ensure delivery of the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment. 4. To ensure funding streams are delivered collaboratively and effectively.
Alternative options considered
1. Not to approve the allocation of S106 funding on the capital programme – not recommended. Not allocating the funds will mean that public open space improvement projects cannot be delivered.
Detailed Information
The report provides an overview of progress and performance for the regeneration programmes.
1.2Progress A progress and risk-based summary for each project is provided below.
Project Achievements/ progress/next steps Start/ Next key Risk Level / Completion Milestone programme Dates and Budget Succeed in Ashfield
ADMC Planning approval is secured. The design S: Jan 2025 Contract team are continuing to work through the C: Feb 2026 Start Est: discharge of pre-commencement Autumn conditions relating to highways access. 2024 Towns Fund: RIBA stage four is progressing under a £20,483,141 PCSA agreement with the contractor.
The land purchase is progressing with the detailed negotiation estimated to be completed by end of November 2024
Ashfield The detailed negotiations for the VWNC: Building Construction purchase of a commercial building in the S: Nov/Dec acquisition Centre and town centre are being finalised, minor 2024 Oct/Nov2024 Satellite complications with details of the land C: Dec 2024 Towns Fund: have delayed the completion which is £4,801,755 now estimated to be by the end of Co-funding: November 2024. £1,837,500
The lease with Vison West Notts college will be completed alongside the site purchase and the college will take occupation to deliver construction skills.
Ashfield Civil The key risk is reducing in relation to the C: Dec 2025 Partnerships Engineering interdependencies with the Council’s working with Towns Fund: Centre redevelopment of the Depot following the local £2,101,134 depot stage 2 plans being approved and a businesses Co-funding: planning application being submitted. £763,517
A review of how the Civils project can be delivered and a sequencing plan is being progressed.
Enterprising Due to the changes agreed by the Board C: March December Ashfield in September, the risk has reduced. Steps 2026 2024 are in place to report on the new learners Enterprising Risk and repeat learners. For the purposes of Ashfield Reduced this report, we have accounted for the Business period 17 August 2024- 16 September Support 2024. Event. Towns Fund: £3,845,000 240 enrolments in the programme with Co-funding: 115 entrepreneurs who have been £3,746,867 assessed both business ready and have signed up for their corn seed, establishment grant. One of the new businesses has successfully published and launched a book.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.