RESOLVED that a) progress for Future High Streets Fund, Towns Fund and UK Shared Prosperity Fund programmes, as presented, be received and noted; b) the UKSPF funding from East Midlands Combined County Authority (EMCCA) be accepted and delegated authority be granted to the Executive Lead Member for Growth, Regeneration and Local Planning, to agree allocation of the funding; c) Council be recommended to approve funding from Sport England being included on the Capital Programme for Hucknall Leisure Centre; d) Council be also recommended, following receipt of funds, that the identified funding be included on the Capital Programme. Reasons: 1. To ensure that Cabinet is kept updated on progress with the regeneration programmes. 2. To ensure that projects and spend are achieved within the set timeframes and programme budget envelopes. 3. To ensure delivery of the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment. 4. To ensure funding streams are delivered collaboratively and effectively.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To ensure that Cabinet is kept updated on funding allocations, progress of funded programmes and bids for external funding.
To add Public Open Space Section 106 contributions / grant income or project contributions to the Capital Programme.
Recommendation(s)
1. To note the progress for Future High Streets Fund, Towns Fund and UK Shared Prosperity Fund programmes.
2. To accept UKSPF funding from East Midlands Combined County Authority (EMCCA) and delegate authority to the Executive Lead Member for Growth, Regeneration and Local Planning to agree allocation of the funding.
3. To recommend to Council that funding from Sport England be included on the Capital Programme for Hucknall Leisure Centre.
4. To recommend to Council, following receipt of funds, that the identified funding be included on the Capital Programme. Reasons for Recommendation(s)
1. To ensure that Cabinet is kept updated on progress with the regeneration programmes. 2. To ensure that projects and spend are achieved within the set timeframes and programme budget envelopes. 3. To ensure delivery of the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment. 4. To ensure funding streams are delivered collaboratively and effectively.
Alternative options considered
1. Not to approve the allocation of project income on the Capital Programme – not recommended. The funding covers essential works that support the completion of projects on the regeneration programme.
Detailed Information
Project Achievements/ progress/next steps Start/ Next key Risk Level / Completion Milestone programme Dates and Budget Succeed in Ashfield
ADMC The first phase of pre-development work S: April Contract was completed with the boundary 2025 Start Est: hedgerow reduction to prepare for it being C: Feb - April 2025 relocated. The main works contract is March being drafted for review and completion. 2026 Towns Fund: £20,483,141 The non-material amendment has been approved by the planning authority.
Documentation for the procurement of an operator is progressing.
Ashfield The purchase of the former Wilko’s VWNC: Start of Construction building has been completed including the S: Jan 2025 Renovation Centre and lease of the building to Vision West Notts work – Satellite College and the award of grant to enable March/ Towns Fund: the college to renovate the building into a April 2025 £4,801,755 construction skills hub. Co-funding: £1,837,500 Ashfield Civil Two location options at the Council depot C: Dec 2025 Partnerships Towns Fund: Engineering are being reviewed with stakeholders working £2,101,134 Centre before agreeing the final position. A grant with local Co-funding: agreement is being developed to cover the businesses £763,517 delivery for the project and draft Heads of March / Terms are being prepared to lease the land April to Vison West Notts College.
Enterprising A boosted Facebook post before Christmas C: March December Ashfield yielded some great results. Achieving over 2026 2024 100k impressions, reached over 26k Enterprising Risk accounts/people which resulted in 737 Ashfield Reduced clicks through to the course pages on the Business website. Following this, we then received Support 55 course enrolment forms in the w/c 16th Event. Towns Fund: December which is our most ever in one £3,845,000 week. Co-funding: £3,746,867 This level of course enrolments will hopefully be maintained through the coming weeks as the rest of the campaign kicks in (radio, bus stops, direct mail, socials etc).
The team are now working to update the graduate placement offer on the website and communicate this via email and socials to eligible businesses.
Working on producing analytics report to show the reach the marketing activity has had on the project to date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.