RESOLVED that a) the progress for Future High Streets Fund, Towns Fund and UK Shared Prosperity Fund programmes, be received and noted; b) Council be recommended to approve that subject to receipt of funds, the funding from S106 contributions be added to the Capital Programme; c) Council be recommended to approve the allocation of general funds towards capital projects being included on the Capital Programme, as detailed in the report. Reasons: 1. To ensure that Cabinet is kept updated on progress with the regeneration programmes. 2. To ensure that projects and spend are achieved within the set timeframes and programme budget envelopes. 3. To ensure delivery of the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment. 4. To ensure funding streams are delivered collaboratively and effectively.
Word for word from the decision Ashfield published for this meeting.Source: democracy.ashfield.gov.uk
To ensure that Cabinet is kept updated on funding allocations, progress of funded programmes and bids for external funding.
To add Public Open Space Section 106 contributions / grant income or project contributions to the Capital Programme.
To approve allocations from the Council’s general fund towards capital projects identified in the report.
Recommendation(s)
1. To note the progress for Future High Streets Fund, Towns Fund and UK Shared Prosperity Fund programmes.
2. To recommend to Council that subject to receipt of funds the funding from S106 contributions are added to the Capital Programme.
3. To recommend to Council, allocation of general funds towards capital projects detailed in the report to be included on the Capital Programme.
Reasons for Recommendation(s)
1. To ensure that Cabinet is kept updated on progress with the regeneration programmes. 2. To ensure that projects and spend are achieved within the set timeframes and programme budget envelopes. 3. To ensure delivery of the Council’s Corporate Plan and improvements to parks and green spaces with a rolling programme of investment. 4. To ensure funding streams are delivered collaboratively and effectively.
Alternative options considered
1. Not to approve the allocation of project income on the Capital Programme – not recommended. The funding covers essential works that support the completion of projects on the regeneration programme.
Detailed Information
Summary of key updates:
A further year of UK Shared Prosperity Fund (UKSPF) has been secured and is being used to support a range of projects in Ashfield: • Funding for Hucknall to support projects which were included in the Levelling Up Fund programme before the Government withdrew the funding. This includes improvements to Central Walk and Chapel Street, and investment in the library to enable more promotion of the heritage of the town. • Community grants for local voluntary and community sector organisations • Support for local businesses through enterprise grants, help for high street businesses and opportunities for people to try their business idea at our markets • Help and advice for residents who are struggling financially • Employment support for residents who are out of work, with a focus on young people aged 18-25 • Funding for projects in Stanton Hill, in line with the Stanton Hill Investment Plan
In addition, a number of projects in Sutton town centre will complete in the next couple of months. The renovation of Portland Square will complete in July, the Cornerstone Theatre will open in August and the new Construction Training Centre will open for teaching in September.
UKSPF 2025/26 allocations are in green text.
Project Achievements/ progress/next steps Start/ Next key Risk Level / Completion Milestone programme Dates and Budget Succeed in Ashfield
ADMC Contract: S: April Social Value The PCSA agreement for the building 2025 Investment contract has been completed to deliver C: Feb - Est: May / June the pre-construction phase works. This March 2026 2025 included, Design work, invasive surveys, Towns Fund: stage 1 ecology work. £20,483,141 The main contract for the building work is being reviewed by the legal team for approval. The Section 278 work designs and approvals are progressing alongside surveys to ascertain the fixed price for the highway construction and junction improvements.
The start date of the contract work has slipped due to the current technical design approval still progressing for the Section 278 works. The S278 work had increased due to requirements set out through the planning process. The main building work is now due to commence late June / early July
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Plan Year End Delivery 2025/26RESOLVED that a) the levels of delivery achieved against the Corporate Plan Priorities, as outlined in the report, be...
Corporate Risk Year End 2025/26 PositionRESOLVED that the current significant items on the Corporate Risk Register, as presented, be received and noted. Reas...
Appropriation of Land at Kingsway ParkRESOLVED that a) it be noted that the Secretary of State for Housing, Communities & Local Government granted consent ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.