Resolved
RESOLVED that the Audit progress report, as submitted, be received and duly noted.
Audit Committee noted this item on Thursday 28 November 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit progress report, as submitted, be received and duly noted.
Audit Progress Report Ashfield District Council– Year end 31 March 2024
November 2024 Contents
01 Overview of engagement 02 Government measures to clear the backlog in local government accounts audit
This document is to be regarded as confidential to Ashfield District Council. It has been prepared for the sole use of the Audit Committee as the appropriate sub-committee charged with governance. No responsibility is accepted to any other person in respect of the whole or part of its contents. Our written consent must first be obtained before this document, or any part of it, is disclosed to a third party.
2 Overview of engagement 01 Overview of engagement We are appointed to perform the external audit of Ashfield District Council (the Council) for the year ending 31 March 2024. The scope of our engagement is set out in the Statement of Responsibilities of Auditors and Audited Bodies, issued by Public Sector Audit Appointments Ltd (PSAA) available from the PSAA website: https://www.psaa.co.uk/managing-audit-quality/statement-of-responsibilities-of-auditors-and-audited-bodies/. Our responsibilities are principally derived from the Local Audit and Accountability Act 2014 (the 2014 Act) and the Code of Audit Practice issued by the National Audit Office (NAO), and we summarise the position to date as follows:
Area Responsibilities Status: Ashfield District Council
Audit opinion We are responsible for forming and expressing an opinion on whether the financial We are currently part way through our fieldwork the financial statements for 2023/24. We reported statements are prepared, in all material respects, in accordance with the Code of our planned timeline to the Committee in September 2024 which showed the planned fieldwork Practice on Local Authority Accounting. Our audit does not relieve management or the dates as October – November, with completion expected in January 2025. Audit & Governance Committee, as Those Charged With Governance, of their On 30 July 2024, the Minister of State for Local Government and English Devolution made a responsibilities. statement to propose secondary legislation, with the proposed backstop date for financial years up- to-and-including 2022/23 as 13 December 2024 and the financial year 2023/24 being 28 February 2025. We are working to complete the audit ahead of the 28th February deadline.
Value for money We are responsible for forming a view on the arrangements that the Council has in We have started our planning and risk assessment work and have requested management’s self- place to secure economy, efficiency and effectiveness in its use of resources. assessment. We will continue to update our risk assessment as the audit progresses.
Wider reporting and We report to the National Audit Office (NAO) on the consistency of the Council’s We are unable to report to the NAO until our work on the financial statements is complete. electors’ rights financial statements with its Whole of Government Accounts (WGA) submission. We have not received any matters of correspondence from electors. The 2014 Act requires us to give an elector, or any representative of the elector, the opportunity to question us about the accounts of the Council and consider objections made to the accounts. We also have a broad range of reporting responsibilities and powers that are unique to the audit of local authorities in the United Kingdom.
4 Government measures to clear the backlog in local government accounts audit 02 Government measures to clear the backlog in local government accounts audit Backstop update
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MAZARS: Audit Progress ReportReport | 1 MB | DownloadRead as text |
Follow Audit Committee at Ashfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2026 | Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... | Noted | Open |
| 25 Jun 2026 | Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... | Decided | Open |
| 25 Jun 2026 | FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. | Noted | Open |
| 25 Jun 2026 | Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... | Approved | Open |
| 25 Jun 2026 | Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.