Audit Committee, Thursday 19 February 2026 at 7.00pm

Technology One System Update

Noted Finance 1 paper

AI summaryAshfield Audit Committee noted an update on the Technology One system rollout. The new budgeting, forecasting and contracts modules are set to go live on 1 April 2026, with the fixed assets module to follow later in 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo decision taken beyond noting the report
MoneyNot specifiedCosts said to already be budgeted for
What happens next1 April 2026 go-livePhase 2: Budgeting and Contracts modules
Who it affectsCouncil finance staff and budget holdersWill use the new modules from April 2026

What was decided

The Audit Committee received and noted the Technology One system update report. Report P3

Why

To make sure the ongoing progress of the Technology One implementation is regularly reported to the Audit Committee. Report P4

What happens next

Phase 1 work continues: testing the Bank Reconciliation module into the live environment, creating standard reports, an internal audit of access management, and a lessons learnt assessment on the original implementation. Report P7

Phase 2 design is being finalised, with User Acceptance Training booked throughout February for the Budgeting and Forecasting module and in late February and early March for the Contracts module, both due to go live on 1 April 2026. Report P8, P9

Phase 3 detailed work on the Fixed Assets module will be scheduled once Phase 2 is fully complete, later in 2026. Report P10

Options considered

  • Rejected: No alternative options were considered Report P5

Implications

  • Other: A robust financial system should help the Council set a robust deliverable budget, supporting the Corporate Plan. Report P13
  • Risk: Risk of a single point of failure on the Budgets and Contracts modules is being mitigated by redirecting additional resources to ensure backfilling arrangements. Report P11, P19
  • Legal: Risk that the Contracts module configuration may not reflect new legislation is being mitigated by making Technology One consultants aware of the new legislation. Report P20
  • Legal: No significant legal implications identified. Report P14
  • Financial: All costs for the three phases have been budgeted for within the General Fund revenue budget. Report P16, P17
  • Staffing: No direct HR implications identified. Report P21
  • Equalities: No equalities implications. Report P23
  • Climate: No environmental or sustainability implications. Report P22

Who and where

  • Budget holders across the Council, who will get more ownership of their own budgets through the new module Report P8
  • The Council's finance team, who will work more closely with budget holders Report P8
  • Officers involved in the implementation, with additional resources being redirected to the project Report P11

Timeline

  • February 2026: User Acceptance Training for the Budgeting and Forecasting module is booked throughout February. Report P8
  • Late February and early March 2026: User Acceptance Training for the Contracts module is due to take place. Report P9
  • 1 April 2026: Phase 2 go-live date for the new Budgeting and Forecasting module and the Contracts module. Report P8, P9
  • Later in 2026: Phase 3 implementation of the Fixed Assets module, scheduled after Phase 2 is fully complete. Report P10

Plain English for the jargon

  • DMA (Decision Making Accountability): A process Council adopted under which budget holders take more ownership of their own budgets, a core reason the new Budgeting and Forecasting module is being introduced.
  • User Acceptance Training: Training and testing carried out by the people who will actually use the new software, before it goes live.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAC.38

Resolved

RESOLVED that the report be received and noted.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Audit Committee

Purpose of report

To give an update on the Technology One system implementation.

Recommendation(s)

• That Audit Committee note the contents of the report.

Reasons for Recommendation(s) To ensure the ongoing progress of the implementation of Technology One is regularly reported to the Audit Committee.

Alternative Options Considered None

Detailed Information The rollout of the Technology One system is happening in three phases.

Phase 1 – is all about tidying up and strengthening the initial implementation. This includes testing the Bank Reconciliation module and moving it into the live environment, creating a standard set of reports, and carrying out an internal audit of access management so we can act on the recommendations. Officers will also be undertaking a lessons learnt assessment on the initial implementation to ensure that any learnings can be incorporated into these phases.

Phase 2 - focuses on getting the new budgeting and forecasting module ready to go live on 1 April 2026. We’re currently finalising the design, and User Acceptance Training is booked throughout February. This new module should make it much easier for budget holders and the finance team to work together, giving budget holders more ownership of their areas. This was a core element to the Decision Making Accountability (DMA) process that Council adopted.

Council is also developing the Contracts module as part of Phase 2, with the same go-live date of 1 April 2026. We’ve already had the initial design session with Technology One, configuration work is underway, and User Acceptance Training will take place in late February and early March.

Phase 3 - will focus on implementing the Fixed Assets module later in the year. We’ve already reviewed the initial design documents, and we’ll schedule the detailed work once Phase 2 is fully complete.

Both project management and overall governance has been strengthened for these next phases with resources being redirected for the project.

Implications

Corporate Plan: Through the implementation of a robust financial system this will help to ensure that Council can set a robust deliverable budget.

Legal: There are no significant legal implications identified in the report. [RLD 11/02/2026]

Finance:

All costs associated with the 3 phases as identified within the report have been budgeted for. [AP 11/02/2026] Budget Area Implication

General Fund – Revenue Budget Costs associated with the 3 phases as identified within the report have already been budgeted for. General Fund – Capital N/A Programme Housing Revenue Account – N/A Revenue Budget Housing Revenue Account – N/A Capital Programme Risk:

Risk Mitigation

Single point of failure on Budgets Additional resources have been made available to and Contracts Modules ensure adequate back filling arrangements are in place.

Contracts - risk relates to the Technology One consultants are fully aware of the new new legislation legislation and the configuration will reflect this.

Human Resources: There are no direct HR implications contained in the report. [KH 11/02/2026]

Environmental/Sustainability: No implications.

Equalities: No implications.

Other Implications: Nil

Reason(s) for Urgency N/A

Reason(s) for Exemption N/A

Background Papers Nil

Report Author and Contact Officer Sarah Bassitt Principle Accountant Tel: 01623 457342 Email: [email protected]

Sponsoring Executive Director Criag Bonar Executive Director – Transformation Tel: 01623 457203 Email: [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Technology One System UpdateReport 88 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 20 attended
JB
Councillor Jamie BellCommittee Member, absent
WB
Councillor Will BostockCommittee Member, present
JC
Councillor Jodine CronshawCommittee Member, present
PG
Councillor Paul GraftonCommittee Member, present
DJ
Councillor Dawn JusticeCommittee Member, present
WN
Councillor Warren NuttallChairman, present
DS
Councillor Dave ShawCommittee Member, present
LC
Lynn CainOfficer, in attendance
RD
Ruth DennisOfficer, in attendance
JF
Joanne FroggattOfficer, in attendance
DL
Damon LawrensonOfficer, in attendance
LW
Lisa WallOfficer, in attendance

All 20 on the meeting page

More from Ashfield Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... Noted Open
25 Jun 2026 Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... Decided Open
25 Jun 2026 FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. Noted Open
25 Jun 2026 Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... Approved Open
25 Jun 2026 Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... Noted Open