Audit Progress Report

Noted Finance 1 paper

AI summaryAshfield District Council Audit Committee noted the Audit Progress Report as at 4 February 2026, covering 2025-26 assignments, five completed reviews and 83 open recommendations including 2 critical risk items.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAudit assignment progress and recommendation tracking noted by committee
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil departments and residentsAudits cover finance, housing, contracts, procurement and risk

What was decided

The committee received and noted the audit assignment progress and recommendation tracking as at 4 February 2026 as presented.

Why

The Audit Partnership presented the report to give the committee oversight of internal audit work and outstanding recommendations. Report P10, P55

What happens next

Audits in progress continue: Finance System Assurance at 15 percent, Strategic Procurement at 70 percent, Risk Management at 55 percent, IT Key Controls at 25 percent, Finance System Access Management at 30 percent, Housing Allocations and Lettings at 5 percent, and Depot Project at 45 percent. Report P10, P11

Two further pieces of audit work on the Technology One finance system have been added to the 2025-26 plan to seek further assurance. Report P13, P40

Implications

  • Risk: Two critical risk recommendations remain open across the estate of tracked audit actions, with 31 moderate risk items also outstanding. Report P53
  • Financial: The Technology One finance system, live since August 2024, had significant implementation issues and audit work was limited by data quality and Finance Team resourcing pressures during 2024-25 closedown. Report P40
  • Equalities: Fire safety work continues, with 32 flat entrance doors still to replace as of January 2025, including 23 leaseholder, 4 side panel and 5 standard doors, with access and tenant engagement issues cited. Report P69
  • Staffing: A new manager assumed responsibility for the Estates section on 5 January 2026, postponing implementation of two outstanding estates audit recommendations. Report P57, P60, P75

Who and where

  • Derby City Council Audit Partnership, which provides internal audit services to the council Report P3, P4, P5
  • Council departments subject to 2025-26 audits including Finance, Housing, IT, Risk and Procurement Report P10, P11
  • Council tenants, particularly around fire safety door replacement, damp and mould casework and rent arrears processes Report P29, P69, P72
  • External contractors Sports and Leisure Management Ltd, Futures Advice Skills and Employment Ltd and Second Element Ltd whose contracts were reviewed Report P34

Timeline

  • August 2024: Technology One finance system went live Report P40
  • 21 October 2025 to 4 February 2026: Period covered by completed audit assignments Report P15
  • 4 February 2026: Status date for audit progress and recommendations Report P10
  • 19 February 2026: Audit Committee meeting Report P1
  • 30/04/2027: Revised action date for Transfer of Assets recommendations on bridges, tunnels, culverts and trees inventory Report P47

Plain English for the jargon

  • Technology One (T1): The council's new finance system that went live in August 2024
  • NFI: National Fraud Initiative, now operated by the Public Sector Fraud Authority
  • iTrent: The council's HR system used to hold training records
  • Awaab's Law: Legislation referenced in relation to working inspections for damp and mould compliance from October 2025
  • Consumer Standards: Social Housing Regulation standards assessed in the Social Housing Regulation audit
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemAC.39

Resolved

RESOLVED that audit assignment progress and recommendation tracking as at 4 February 2026, as presented to Committee, be received and noted.
Word for word from the decision Ashfield published for this meeting. Source: democracy.ashfield.gov.uk

Follow this further

Built from Ashfield's papers

What the report saysPro

Report to Audit Committee

Ashfield District Council – Audit Progress Report Audit Committee: 19 February 2026 Contents Page Our Vision AUDIT DASHBOARD .................................. 3 AUDIT PLAN ............................................... 4 To bring about improvements in the control, AUDIT COVERAGE .................................... 6 governance and risk management arrangements of our Partners by providing RECOMMENDATION TRACKING ............ 13 cost effective, high quality internal audit HIGHLIGHTED RECOMMENDATIONS ..... 15 services.

Contacts Head of Audit Partnership Email: Tel: Address

Richard Boneham CPFA [email removed] 01332 643280 c/o Derby City Council Audit Managers Council House Adrian Manifold CMIIA [email removed] 01332 643281 Corporation Street Derby, DE1 2FS Mandy Marples CPFA, CCIP [email removed] 01332 643282

Hannah McDonald CMIIA, APCIP [email removed] 01332 643284

Martin Shipley CMIIA, CCIP [email removed] 01332 643292

Providing Excellent Audit Services in the Public Sector Audit Committee: 19 February 2026

Ashfield District Council – Audit Progress Report AUDIT DASHBOARD Plan Progress Jobs Completed in Period Customer Satisfaction

Recommendations Movement Recommendations Open Recommendations Overdue

Page 3 of 22 Audit Committee: 19 February 2026

Ashfield District Council – Audit Progress Report AUDIT PLAN Progress on Audit Assignments The following tables provide the Audit Committee with information on how audit assignments were progressing at 4 February 2026. 2025-26 Assignments Status % Complete Assurance Rating People Management Reviewed 90% Workforce Planning Removed from Plan Finance System Assurance In Progress 15% Insurance Removed from Plan Contract Monitoring 2025-26 Final Report 100% Reasonable Strategic Procurement 2025-26 In Progress 70% IT Key Controls In Progress 25% Risk Management 2025-26 In Progress 55% Finance System - Access Management & Systems Administration In Progress 30% Housing Allocations and Lettings 2025-26 In Progress 5% Homes England Grant Certification Complete 100% N/A Taxi Licensing Removed from Plan Waste Management Removed from Plan Rent Arrears 2025-26 Final Report 100% Reasonable Social Housing Regulation Final Report 100% Reasonable Housing Stocks & Stores Final Report 100% Reasonable

B/Fwd Assignments Status % Complete Assurance Rating Training Records Final Report 100% Limited Main Accounting - Data Assurance 2024-25 Final Report 100% N/A IT Application - IKEN Final Report 100% Substantial Council Tax 2024-25 Final Report 100% Limited Food Safety Final Report 100% Reasonable Depot Project In Progress 45% Public Sector Decarbonisation Scheme Review Reviewed 90% Transfer of Assets Final Report 100% Reasonable

Page 4 of 22 Audit Committee: 19 February 2026

Ashfield District Council – Audit Progress Report Plan Changes At the request of the Corporate Resources Director and with the agreement of the Executive Director – Governance, two audits have been added to the 2025- 26 Audit Plan. The first audit is Finance System – Access Management and Systems Administration where we will review the new finance system’s (Technology 1) access controls, data protection measures and systems support arrangements to ensure that they adequately safeguard financial data and minimise operational, data protection, and compliance risks. The second audit added to the Plan is Finance System Assurance: this audit will aim to provide assurance that the new financial system accurately records, processes, and reports financial transactions. Accordingly audits of Insurance, Workforce Planning and Waste Management have been removed from the Plan.

Page 5 of 22 Audit Committee: 19 February 2026

Ashfield District Council – Audit Progress Report AUDIT COVERAGE Completed Audit Assignments Between 21 October 2025 and 4 February 2026, the following audit assignments have been finalised.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Progress ReportReport 714 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 20 attended
JB
Councillor Jamie BellCommittee Member, absent
WB
Councillor Will BostockCommittee Member, present
JC
Councillor Jodine CronshawCommittee Member, present
PG
Councillor Paul GraftonCommittee Member, present
DJ
Councillor Dawn JusticeCommittee Member, present
WN
Councillor Warren NuttallChairman, present
DS
Councillor Dave ShawCommittee Member, present
LC
Lynn CainOfficer, in attendance
RD
Ruth DennisOfficer, in attendance
JF
Joanne FroggattOfficer, in attendance
DL
Damon LawrensonOfficer, in attendance
LW
Lisa WallOfficer, in attendance

All 20 on the meeting page

On this subject at Ashfield

Search all
  1. Audit Progress ReportThis decision
  2. Internal Audit Progress ReportNoted
  3. Internal Audit Progress ReportNoted
  4. FORVIS MAZARS: External Audit Progress ReportNoted
  5. Internal Audit Progress ReportNoted
  6. Internal Audit Progress ReportNoted

More from Ashfield Audit Committee

All decisions
MeetingDecisionOutcome
25 Jun 2026 Public Sector Decarbonisation SchemeRESOLVED that a) the findings of the Public Sector Decarbonisation Scheme review, as presented, be received and noted... Noted Open
25 Jun 2026 Section 100A Local Government Act 1972: Exclusion of the Press and PublicRESOLVED that in accordance with the provisions of Section 100A of the Local Government Act 1972, the press and publi... Decided Open
25 Jun 2026 FORVIS MAZARS: 2024-25 Audit Opinion UpdateRESOLVED that the update report be received and duly noted. Noted Open
25 Jun 2026 Audit Committee Work Plan and Improvement Plan - 2026/2027RESOLVED that a) the draft Committee Work Plan 2026/2027, as attached at Appendix 1, be approved; b) the draft Improv... Approved Open
25 Jun 2026 Automated Distribution and Manufacturing Centre (ADMC) and Ashfield Innovation and Technology Park (AITP) - UpdateRESOLVED that a) the update report, presented to Cabinet on 15 June 2026, be received and noted; b) in line with the ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies