Resolved
Note: 1. That forecast capital expenditure for 2021/22, as at the end of quarter two is £31.230M as shown in section 3 of the report. This is £4.821M or 13.37% below the latest agreed capital programme budget; 2. The 2021/22 significant forecast outturn variations and explanations are as shown in section 4 of the report; 3. The quarter two forecasts and impact of scheme variances for 2021/22 on future years’ capital expenditure were reported to the Capital Programme Board in October 2021; 4. The latest forecast of capital receipts, grants and contributions for 2021/22 in section 5 of the report; 5. The risks associated with the capital forecasts are as detailed in section 8 of the report; 6. The revised capital programme for 2021/22 to 2024/25 and its financing as shown in section 6 and detailed in Appendix 1 of the report. 7. The capital programme remains fully funded up to 2024/25 based on the latest forecast of available resources. Cabinet requests Council to approve: 8. An increase in the Local Infrastructure Fund Scheme of £0.378M in 2021/22 and £0.379M in 2022/23 to reflect the final approved grants under the scheme which is to be funded from a final reserve release from the Local Infrastructure Fund Reserve. 9. A reduction in the 5G Living Lab Scheme of £1.917M in 2021/22 which reflects the latest council and external partner funding arrangements for delivery of the scheme. 10. An increase in the Smarter Ways of Working Scheme of £0.297M, funded from revenue savings on related spending in 2021/22, reflecting a revised mix of capital and revenue expenditure on the overall scheme costs. 11. An increase of £4.599M to the capital programme in 2021/22, in respect of a development at Site 3, Jays Close, Viables , reflecting the transfer of a commercial unit to the council. This represents the consideration given for a ground lease restructure at the site, and will be offset by an equivalent financing increase in the form of a premium/notional capital receipt.