Quarter 1 Capital Monitoring Report as at 30 June 2025
AgreedExecutive1 paper
AI summaryCabinet noted a £19.514M forecast capital spend for 2025/26, £0.688M below the £20.202M budget, and recommended Council approve changes including a £1.139M Manydown scheme increase and a new £0.301M Affordable Housing scheme.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedRecommend Council approve four capital programme changes
Money£19.514M forecast, £0.688M under budgetLatest agreed 2025/26 capital budget is £20.202M
What happens nextCouncil meeting 16 October 2025Full Council to decide on recommended changes
Who it affectsCapital programme 2025/26 to 2028/29Schemes across regeneration, housing, waste, digital
What was decided
Cabinet noted the 2025/26 capital expenditure forecast of £19.514M, which is £0.688M lower than the latest agreed capital programme budget of £20.202M.
Cabinet recommended that Council approve an increase to the Manydown Development scheme of £1.139M in 2025/26 and £0.153M in 2026/27.
Cabinet recommended that Council approve three further changes: a £0.384M reduction to the New Waste Collection Contract scheme in 2025/26, a £0.644M increase to the Local Authority Housing Fund scheme in 2025/26, and a new Affordable Housing Schemes capital scheme of £0.301M in 2025/26.
Why
The report updates Cabinet on major changes in the capital programme for 2025/26 to 2028/29 since the outturn reported to Council in July 2025. Report P20, P24
The capital programme remains fully funded from the council's own resources up to 2028/29, based on the latest forecast of available resources.
Risks such as partner delivery delays, supplier availability and adverse weather are managed through monthly monitoring, profiled budgets and regular challenge. Report 9.4, 9.3
What happens next
Council is to consider the recommended capital programme changes on 16 October 2025. Report P25
The capital programme will continue to be monitored monthly and reviewed in-year to mitigate pressures. Report 9.3
Any potential savings identified from the capital monitoring process will be built into future capital programme updates. Report 16.2
The money
£19.514M Forecast capital expenditure for 2025/26
£20.202M Latest agreed capital programme budget for 2025/26 Report P28
£0.688M Difference between forecast and budget for 2025/26
£1.139M Recommended increase to Manydown Development scheme in 2025/26
£0.153M Recommended increase to Manydown Development scheme in 2026/27
£0.384M Recommended reduction to New Waste Collection Contract scheme in 2025/26
£0.069M Recommended reduction to New Waste Collection Contract scheme in 2026/27
£0.644M Recommended increase to Local Authority Housing Fund scheme in 2025/26
£0.301M Recommended new capital budget for Affordable Housing Schemes in 2025/26
Options considered
Chosen: Recommend Council to approve the four capital programme changes (Manydown increase, waste contract reduction, housing fund increase, new affordable housing scheme). Cabinet supports the changes to deliver Council Plan Priorities
Implications
Risk: Capital programme risks include partner delivery delays, supplier and lead time issues, and adverse weather, managed through monthly monitoring and budget profiling. Report 9.3, 9.4, 9.5
Equalities: No differential impacts identified for any protected characteristic groups; works are forecast to be completed on time. Report 12.1
Climate: Improvement schemes and EV charging points are expected to have a positive carbon effect, though slippage would delay these benefits. Report 14.1, 14.2
Staffing: No HR implications arise from this report. Report 15.1
Other: Some schemes depend on planning permission being granted, and S106 or CIL funding must be used in line with the original agreement purposes. Report 11.1, 11.2
Who and where
Residents in the borough receiving capital-funded housing, waste, leisure and community schemes Report P27, P28
Council departments delivering the schemes, including Regeneration and Resident Services Report P27, P28
Developers and partners contributing S106 and CIL funding for infrastructure Report 11.1
Timeline
30 June 2025: Quarter 1 monitoring position reported
July 2025: Last capital programme outturn reported to Council Report P24
7 October 2025: Cabinet considered the Quarter 1 Capital Monitoring Report Report P25
16 October 2025: Council scheduled to decide on recommended capital programme changes Report P25
2025/26 to 2028/29: Period covered by the capital programme Report P28
Plain English for the jargon
Capital programme: The council's multi-year plan for spending on major projects and asset purchases.
S106: Section 106 developers' contributions, paid by developers towards infrastructure to support new development.
CIL: Community Infrastructure Levy, a charge on new development used to fund local infrastructure.
Outturn: The actual final spending position for a financial year, compared with the budget.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item39/25
Resolved
Cabinet note: 1. The forecast capital expenditure for 2025/26 of £19.514M which is £0.688M lower that the latest agreed capital programme budget of £20.202M; 2. The approved increases to the 2025/26 capital budget from S106 contributions and scheme rephasing under the Chief Finance Officer’s delegated powers as shown in section 2 of the report; 3. The 2025/26 significant forecast variations and explanations for them as shown in section 3 of the report; 4. The latest forecast of capital receipts, grants and contributions for 2025/26 in section 4 of the report; 5. The risks associated with the capital forecasts are as detailed in section 9 of the report; 6. The latest approved capital programme for 2025/26 to 2028/29 and the financing as shown in section 5 and detailed in Appendix 1 of the report; and 7. The capital programme remains fully funded from the council’s own resources up to 2028/29, based on the latest forecast of available resources. Cabinet recommend Council to approve: 8. Changes to the capital programme as described in section 6 of the report to support the delivery of Council Plan Priorities as follows: · an increase to the Manydown Development scheme of £1.139M in 2025/26 and £0.153M in 2026/27; · a reduction to the New Waste Collection Contract scheme of £0.384M in 2025/26 and £0.069M in 2026/27; · an increase to the Local Authority Housing Fund scheme of £0.644M in 2025/26; and · a new capital scheme for Affordable Housing Schemes with a capital budget of £0.301M in 2025/26.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Cabinet / Council Date: 7th October 2025/ 16th October 2025 Subject: Quarter 1 Capital Monitoring Report as at 30 June 2025 Cllr Gavin James – Co-Leader and Cabinet Member for Report of: Finance and Property
Lead Officer: Chief Finance Officer (Section 151 Officer) Chief Finance Officer (Section 151 Officer) – Adam Swain [email protected] Contact Officer: Accountancy Manager (Deputy Section 151 Officer) – Sarah Finch – Tel 01256 845330 or email [email protected]
Ward(s): All Key Decision: Yes Appendix 1: Latest Approved Capital Programme 2025/26 to 2028/29
Exempt or Confidential Information It is considered that information contained within this report and appendix does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public.
Foreword – Cllr Gavin James Co-Leader and Cabinet Member for Finance and Property This report sets out the position on the council’s capital programme for the first quarter of 2025/26.
The current forecast outturn for capital expenditure is £19.514M which is £0.688M below the latest approved programme for the year. This is due to changes in the expected timing of a number of programmes which will result in delayed spend, offset by expenditure on another scheme being brought forward and a change in accounting treatment of costs relating to the introduction of food waste collection.
I am pleased to see that there are requests for an additional £2.084M to be added to the programme in the year to support the delivery of Council Plan Priorities. Recommendation to Cabinet
It is recommended that Cabinet note:
1. The forecast capital expenditure for 2025/26 of £19.514M which is £0.688M lower that the latest agreed capital programme budget of £20.202M;
2. The approved increases to the 2025/26 capital budget from S106 contributions and scheme rephasing under the Chief Finance Officer’s delegated powers as shown in section 2;
3. The 2025/26 significant forecast variations and explanations for them as shown in section 3;
4. The latest forecast of capital receipts, grants and contributions for 2025/26 in section 4;
5. The risks associated with the capital forecasts are as detailed in section 9;
6. The latest approved capital programme for 2025/26 to 2028/29 and the financing as shown in section 5 and detailed in Appendix 1; and
7. The capital programme remains fully funded from the council’s own resources up to 2028/29, based on the latest forecast of available resources.
It is recommended that Cabinet request Council to approve:
8. Changes to the capital programme as described in section 6 to support the delivery of Council Plan Priorities as follows: • an increase to the Manydown Development scheme of £1.139M in 2025/26 and £0.153M in 2026/27; • a reduction to the New Waste Collection Contract scheme of £0.384M in 2025/26 and £0.069M in 2026/27; • an increase to the Local Authority Housing Fund scheme of £0.644M in 2025/26; and • a new capital scheme for Affordable Housing Schemes with a capital budget of £0.301M in 2025/26. Background, corporate objectives and priorities
In accordance with the council’s Financial Procedure Rules, the Chief Finance Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.
The capital programme is reviewed on a quarterly basis in accordance with the council’s Capital Strategy, with a quarterly update reported to Cabinet and Council (for approval if required). This is only required to enable capital schemes in the programme to proceed and approve additions and changes to the programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.