Cabinet note: 1. The forecast capital expenditure for 2024/25 of £30.268M which is £7.573M lower than the latest agreed capital programme budget of £37.841M; 2. The 2024/25 significant forecast outturn variations and explanations for them as shown in section 4 of the report; 3. The quarter three forecasts and impact of scheme variances for 2024/25 on future years’ capital expenditure; 4. The latest forecast of capital receipts, grants and contributions for 2024/25 in section 5 of the report; and 5. The risks associated with the capital forecasts are as detailed in section 8 of the report.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Cabinet Date: 18 March 2025 Quarter 3 Capital Monitoring Report 2024/25 as at 31 Subject: December 2024 Cllr Gavin James – Co-Leader and Cabinet Member for Report of: Finance and Property Lead Officer: Chief Finance Officer (Section 151 Officer) Chief Finance Officer (Section 151 Officer) – Adam Swain [email protected] Contact Officer: Accountancy Manager (Deputy Section 151 Officer) – Sarah Finch – Tel 01256 845330 or email [email protected] Ward(s): All Key Decision: No
Exempt or Confidential Information It is considered that information contained within this report does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public.
Foreword – Cllr Gavin James Co-Leader and Cabinet Member for Finance and Property This report sets out the position on the council’s capital programme for the third quarter of 2024/25. The current forecast outturn for capital expenditure is £30.286M which is 20% less than the latest approved budgeted programme for the year.
The most significant variance has occurred in respect of the projected spend on the May Place project, which is now expected to progress in late 2025/26 and into 2026/27.
The updated position is reflected in the revised capital programme for 2024/25 to 2028/29. Recommendation to Cabinet It is recommended that Cabinet note: 1. The forecast capital expenditure for 2024/25 of £30.268M which is £7.573M lower than the latest agreed capital programme budget of £37.841M; 2. The 2024/25 significant forecast outturn variations and explanations for them as shown in section 4; 3. The quarter three forecasts and impact of scheme variances for 2024/25 on future years’ capital expenditure; 4. The latest forecast of capital receipts, grants and contributions for 2024/25 in section 5; and 5. The risks associated with the capital forecasts are as detailed in section 8.
Background, corporate objectives and priorities
In accordance with the council’s Financial Procedure Rules, the Chief Finance Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.
The capital programme is reviewed monthly in accordance with the council’s Capital Strategy, with a quarterly update reported to Cabinet and Council for approval if required. This is only required to enable capital schemes in the programme to proceed and approve additions and changes to the programme.
This report provides the forecast 2024/25 outturn position for capital spend at 31 December 2024. The forecasts and explanations have been discussed and agreed with Directors, Heads of Services and Project Managers in accordance with the council’s Policy and Budgetary Framework and supports the development of an effective and efficient council. Main considerations
Executive Summary 1.1 The purpose of this report is to inform Cabinet of any major changes in the capital programme for the period 2024/25 to 2027/28, highlighting changes in the programme since the last reported monitoring position to Council in December 2024.
1.2This report also presents the forecast capital outturn position for 2024/25 and compares it with the latest agreed budget providing explanations for the significant variances.
1.3The latest approved capital programme for 2024/25 to 2027/28 is £146.246M as at December 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.