2021/22 Quarter 2 Capital Monitoring Report as at 30 September 2021

Approved Committee 1 paper

Council approved this item on Thursday 20 January 2022. Below is the council's own wording, with the papers it was decided on.

Item68/21

Resolved

Council approve 1) An increase in the Local Infrastructure Fund Scheme of £0.378M in 2021/22 and £0.379M in 2022/23 to reflect the final approved grants under the scheme which is to be funded from a final reserve release from the Local Infrastructure Fund Reserve. 2) A reduction in the 5G Living Lab Scheme of £1.917M in 2021/22 which reflects the latest council and external partner funding arrangements for delivery of the scheme. 3) An increase in the Smarter Ways of Working Scheme of £0.297M, funded from revenue savings on related spending in 2021/22, reflecting a revised mix of capital and revenue expenditure on the overall scheme costs. 4) An increase of £4.599M to the capital programme in 2021/22, in respect of a development at Site 3, Jays Close, Viables , reflecting the transfer of a commercial unit to the council. This represents the consideration given for a ground lease restructure at the site, and will be offset by an equivalent financing increase in the form ... view the full minutes text for item 68/21
Word for word from the decision Basingstoke and Deane published for this meeting. Source: democracy.basingstoke.gov.uk

Follow this further

Built from Basingstoke and Deane's papers

What the report saysPro

Report to Council

2021/22 Quarter 2 Capital Monitoring Report as at 30 September 2021 Cllr John Izett - Cabinet Member for Finance and Major Projects

Report to: Cabinet Council

Meeting date: 7 December 2021 20 January 2022

Ward(s): All Key Decision: Yes

Appendix 1: Revised Capital Programme 2021/22 to 2024/25

Papers Relied 2021/22 Quarter 1 Capital Monitoring Report as at 30 June 2021 On:

Foreword – Cabinet Member for Finance and Major Projects

The Quarter 2 Capital Programme Monitoring report records some slippage in forecast spend as at September 30th 2021. On a budgeted capital spend for the financial year of £31.23M, which is a substantial target, actual committed expenditure has undershot by 13.37%. Much of the explanation for these delays is down to the continuing impact of the pandemic including supply chain shortages and availability of consultancy support. Officers recognise these challenges, and it is important that every effort is made to return capital expenditure on behalf of our residents to the agreed programmes.

It is noted that no allowance is made for future CIL receipts which should be substantial and of considerable future benefit in terms of infrastructure expenditure for our communities. The work of assessing likely CIL sums will be undertaken in the coming months in time for inclusion in the 2022/23 Capital Programme and will be considered by EPH Committee.

1 of 22 It is recommended that Cabinet note:

1. That forecast capital expenditure for 2021/22, as at the end of quarter two is £31.230M as shown in section 3. This is £4.821M or 13.37% below the latest agreed capital programme budget;

2. The 2021/22 significant forecast outturn variations and explanations are as shown in section 4;

3. The quarter two forecasts and impact of scheme variances for 2021/22 on future years’ capital expenditure were reported to the Capital Programme Board in October 2021;

4. The latest forecast of capital receipts, grants and contributions for 2021/22 in section 5;

5. The risks associated with the capital forecasts are as detailed in section 8;

6. The revised capital programme for 2021/22 to 2024/25 and its financing as shown in section 6 and detailed in Appendix 1.

7. The capital programme remains fully funded up to 2024/25 based on the latest forecast of available resources.

Cabinet requests Council to approve:

8. An increase in the Local Infrastructure Fund Scheme of £0.378M in 2021/22 and £0.379M in 2022/23 to reflect the final approved grants under the scheme which is to be funded from a final reserve release from the Local Infrastructure Fund Reserve.

9. A reduction in the 5G Living Lab Scheme of £1.917M in 2021/22 which reflects the latest council and external partner funding arrangements for delivery of the scheme.

10. An increase in the Smarter Ways of Working Scheme of £0.297M, funded from revenue savings on related spending in 2021/22, reflecting a revised mix of capital and revenue expenditure on the overall scheme costs.

11. An increase of £4.599M to the capital programme in 2021/22, in respect of a development at Site 3, Jays Close, Viables, reflecting the transfer of a commercial unit to the council. This represents the consideration given for a ground lease restructure at the site, and will be offset by an equivalent financing increase in the form of a premium/notional capital receipt. Background, corporate objectives and priorities

In accordance with the council’s Financial Procedure Rules, the Chief Financial Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2021/22 Quarter 2 Capital Monitoring Report as at 30 September 2021Report 738 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

37 of 40 attended
RB
Councillor Rebecca BeanCommittee Member, present
SB
Councillor Simon BoundCommittee Member, present
AB
Councillor Andrea BowesCommittee Member, present
SC
Councillor Samuel CarrCommittee Member, present
AC
Councillor Abigail Compton-BurnettCommittee Member, apologies
RC
Councillor Richard CourtCommittee Member, present
OC
Councillor Onnalee CubittChair, present
HE
Councillor Hayley EachusCommittee Member, present
LE
Councillor Laura EdwardsCommittee Member, present
GF
Councillor Graham FalconerCommittee Member, present
AF
Councillor Angie FreemanCommittee Member, present
JG
Councillor Jay GaneshCommittee Member, present

All 40 on the meeting page

On this subject at Basingstoke and Deane

Search all
  1. 2021/22 Quarter 2 Capital Monitoring Report as at 30 September 2021This decision
  2. Quarter 3 Capital Monitoring Report as at 31 December 2025Approved
  3. Quarter 2 Capital Monitoring Report as at 30 September 2025Agreed
  4. Quarter 1 Capital Monitoring Report as at 30 June 2025Approved
  5. Quarter 1 Capital Monitoring Report as at 30 June 2025Agreed
  6. Quarter 3 Capital Monitoring Report 2024/25Agreed

More from Basingstoke and Deane Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Capital Programme Outturn for 2025/26Council note: 1) That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is ... Agreed Open
16 Jul 2026 Revenue Outturn Report 2025/26That Council approve: 1) The proposed transfer of the remaining outturn surplus of £1.51M after grant and income rese... Approved Open
16 Jul 2026 Treasury Management 2025/26 Annual ReportResolved that: The Treasury Management 2025/26 Annual Report be noted and the amendments to the Treasury Management S... Noted Open
16 Jul 2026 Old Basing and Lychpit Community Governance Review – Final RecommendationsResolved that: Council 1) Note the outcome of the consultations. 2) Agree the final recommendations for the Community... Noted Open
16 Jul 2026 Appointment of Interim S151 OfficerResolved : that Sarah Finch be appointed as Interim Section 151 Officer from 1 October 2026. Decided Open