Note: 1. The forecast capital expenditure for 2022/23 of £47.503M which is £1.255M (2.57%) below the latest agreed capital programme budget; 2. The 2022/23 significant outturn variations and explanations for them as shown in section 4 of the report; 3. The quarter one forecasts and impact of scheme variances for 2022/23 on future years’ capital expenditure were reported to the Capital Programme Board in July 2022; 4. The capital programme budget for 2022/23 has been profiled to show the period when the budget will be spent, so that progress on scheme delivery may be monitored more closely. Profiled budgets by Council Plan Priority and capital scheme are shown in section 5 and Appendix 2 of the report; 5. Spend against the quarter one profiled budget shows an overall advanced spend of £0.213M in the quarter and explanations for significant variances are detailed in section 6 of the report; 6. The latest forecast of capital receipts, grants and contributions for 2022/23 in section 7 of the report; 7. The risks associated with the capital forecasts are as detailed in section 10 of the report; 8. The latest approved capital programme for 2022/23 to 2025/26 and its financing as shown in section 8 and detailed in Appendix 1 of the report; and 9. The capital programme remains fully funded from the council’s own resources up to 2025/26, based on the latest forecast of available resources.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Quarter 1 Capital Monitoring Report as at 30 June 2022 Cllr John Izett - Cabinet Member for Finance and Property and Deputy Leader
Report to: Cabinet
Meeting date: 6 September 2022
Ward(s): All Key Decision: Yes
Appendix 1: Latest Approved Capital Programme 2022/23 to 2025/26 Appendix 2: Capital Scheme Profiled Budgets 2022/23
Papers Relied Capital Programme Update and Strategy Report 2021/22 to 2025/26 On: Capital Programme Outturn for 2021/22
Foreword – Cllr John Izett Cabinet Member for Finance and Property and Deputy Leader This report sets out the position on the council’s capital programme for the first quarter of 2022/23.
The current forecast outturn for capital expenditure is £47.503M which is £1.255M (2.57%) less than the agreed programme which reflects the forecast slippage of some schemes mainly where additional feasibility or investigative works need to be completed before the scheme can progress.
This includes rephasing into future years £0.232M estimated not to be required for Home Improvement Financial Assistance and further feasibility work on the Norden community project (£0.392M), which I have asked officers to review.
More positively, I am pleased that early delivery has been achieved on soft landscaping works at Russell Howard Park (£0.040M), and at Pennine Way, Buckskin (£0.030M), and improvement works at Oakley Cricket Club and Kingsclere’s Fieldgate Centre (£0.075M).
I am pleased to see that capital budget profiling has been introduced which will improve financial management to identify where progress on scheme spend is delayed allowing deferment, rephasing into future years or cancellation and where appropriate, release of funds back into the revenue account.
Our capital projects work is being carried out at a time of escalating costs and increasing interest rates which will make this financial year challenging both in terms of budget control and delivery times.
It is recommended that Cabinet note:
1. The forecast capital expenditure for 2022/23 of £47.503M which is £1.255M (2.57%) below the latest agreed capital programme budget;
2. The 2022/23 significant outturn variations and explanations for them as shown in section 4;
3. The quarter one forecasts and impact of scheme variances for 2022/23 on future years’ capital expenditure were reported to the Capital Programme Board in July 2022;
4. The capital programme budget for 2022/23 has been profiled to show the period when the budget will be spent, so that progress on scheme delivery may be monitored more closely. Profiled budgets by Council Plan Priority and capital scheme are shown in section 5 and Appendix 2;
5. Spend against the quarter one profiled budget shows an overall advanced spend of £0.213M in the quarter and explanations for significant variances are detailed in section 6;
6. The latest forecast of capital receipts, grants and contributions for 2022/23 in section 7;
7. The risks associated with the capital forecasts are as detailed in section 10;
8. The latest approved capital programme for 2022/23 to 2025/26 and its financing as shown in section 8 and detailed in Appendix 1; and
9. The capital programme remains fully funded from the council’s own resources up to 2025/26, based on the latest forecast of available resources. Background, Corporate Objectives and Priorities
In accordance with the council’s Financial Procedure Rules, the Chief Financial Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.