It is recommended that Cabinet note: 1. The forecast capital expenditure for 2022/23 of £46.709M which is £2.055M (4.21%) less than the latest approved budget for the capital programme; 2. The 2022/23 significant outturn forecast variations, and explanations for them, are shown in section 4 of the report; 3. The quarter two forecasts and the impact of scheme variances for 2022/23 on future years’ capital expenditure were reported to the Capital Programme Board in November 2022; 4. The capital programme budget for 2022/23 has been profiled to show the period when the budget will be spent, so that progress on scheme delivery may be monitored more closely. Profiled budgets by Council Plan Priority and capital scheme are shown in section 5 and Appendix 2 of the report; 5. That expenditure to date against the quarter two profiled budget shows overall slippage of £1.375M; 6. The latest forecast of capital receipts, grants and contributions for 2022/23 in section 6 of the report; 7. The risks associated with the capital forecasts are as detailed in section 9 of the report; 8. The latest approved capital programme for 2022/23 to 2025/26 and associated financing as shown in section 7, and detailed in Appendix 1of the report; and 9. The capital programme remains fully funded from the council’s own resources up to 2025/26, based on the latest forecast of available resources.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Quarter 2 Capital Monitoring Report as at 30 September 2022 Cllr John Izett - Cabinet Member for Finance and Property and Deputy Leader
Report to: Cabinet
Meeting date: 6 December 2022
Ward(s): All Key Decision: Yes
Appendix 1: Latest Approved Capital Programme 2022/23 to 2025/26 Appendix 2: Capital Scheme Profiled Budgets 2022/23
Papers Relied On: 2022/23 Quarter 1 Capital Monitoring Report as at 30 June 2022
Foreword – Cllr John Izett Deputy Leader and Cabinet Member for Finance and Property– Q2 words to be provided This report sets out the position on the council’s capital programme for the second quarter of 2022/23.
The current forecast outturn for capital expenditure is £46.709M which is £2.055M (4.21%) less than the agreed programme which reflects the forecast underspend on slippage of some certain schemes, mainly where additional feasibility or investigative works need to be completed before the scheme can progress. At this stage of the financial year there is time potentially to address some of these underspends which I know the finance team will be pressing those officers in the responsible departments to do.
Looking ahead our projected capital base looks secure and well able to meet the significant programme of capital projects totalling over £117M through to the end of the MTFS in 2025/26. I look forward to seeing the results of the Property Investment Strategy in meeting its target of £30M of capital receipts and to further work on the profile of Community Infrastructure Levy receipts being added to our capital base. It is recommended that Cabinet note:
1. The forecast capital expenditure for 2022/23 of £46.709M which is £2.055M (4.21%) less than the latest approved budget for the capital programme.
2. The 2022/23 significant outturn forecast variations, and explanations for them, are shown in section 4.
3. The quarter two forecasts and the impact of scheme variances for 2022/23 on future years’ capital expenditure were reported to the Capital Programme Board in November 2022.
4. The capital programme budget for 2022/23 has been profiled to show the period when the budget will be spent, so that progress on scheme delivery may be monitored more closely. Profiled budgets by Council Plan Priority and capital scheme are shown in section 5 and Appendix 2;
5. That expenditure to date against the quarter two profiled budget shows overall slippage of £1.375M.
6. The latest forecast of capital receipts, grants and contributions for 2022/23 in section 6.
7. The risks associated with the capital forecasts are as detailed in section 9.
8. The latest approved capital programme for 2022/23 to 2025/26 and associated financing as shown in section 7, and detailed in Appendix 1; and
9. The capital programme remains fully funded from the council’s own resources up to 2025/26, based on the latest forecast of available resources. Background, Corporate Objectives and Priorities
In accordance with the council’s Financial Procedure Rules, the Chief Financial Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.
The capital programme is reviewed on a quarterly basis in accordance with the council’s Capital Strategy. The forecast position is reported to the Capital Programme Board with a quarterly update reported to Cabinet and Council (for approval if required). This is only required to enable capital schemes in the programme to proceed and approve additions and changes to the programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.