To note: 1. The forecast capital expenditure for 2022/23 of £23.867M which is £23.097M (49.18%) less than the latest approved budget at 31 December 2022 for the capital programme. Of this reported variance, £18.097M, or 78.35%, relates to slippage on the Manydown North scheme. 2. That the Capital Programme update approved by Council subsequently in February 2023 update the programme to take account of these variances. 3. The 2022/23 significant outturn forecast variations, and explanations for them, are shown in section 4 of the report. 4. The quarter three forecasts and the impact of scheme variances for 2022/23 on future years’ capital expenditure were reported to Council in February 2023. 5. The capital programme budget for 2022/23 has been profiled to show the period when the budget will be spent, so that progress on scheme delivery may be monitored more closely. Profiled budgets by Council Plan Priority and capital scheme are shown in section 5 and Appendix 2 of the report. 6. That expenditure to date against the quarter three profiled budget shows overall net slippage of £3.669M. 7. The latest forecast of capital receipts, grants and contributions for 2022/23 in section 6 of the report. 8. The risks associated with the capital forecasts are as detailed in section 9 of the report. 9. The latest approved capital programme for 2022/23 to 2025/26 and associated financing as shown in section 7 of the report and detailed in Appendix 1 of the report. 10. The capital programme remains fully funded from the council’s own resources up to 2025/26, based on the latest forecast of available resources.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Cabinet Date: 7 March 2023 Subject: Quarter 3 Capital Monitoring Report as at 31 December 2022 Report of: Cllr John Izett - Cabinet Member for Finance and Property and Deputy Leader Lead Officer: Sue Cuerden – Executive Director of Corporate Services and Assets (S151 Officer) Contact Officer: Sue Cuerden – Executive Director of Corporate Services and Assets (S151 Officer) Tel No: 01256 845513 Email: [email protected] Adam Swain – Head of Financial Services and Commercialisation (Deputy S151 Officer) Tel No: 01256 845515 Email: [email protected] Sarah Finch – Accountancy Services Manager Tel No: 01256 845330 Email: [email protected]
Ward(s): All Key Decision: No Appendix 1: Latest Approved Capital Programme 2022/23 to 2025/26 Appendix 2: Capital Scheme Profiled Budgets 2022/23
Exempt or Confidential Information It is considered that information contained within this report and appendices does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public. Foreword – Cllr John Izett Deputy Leader and Cabinet Member for Finance and Property
The Capital Monitoring Report for quarter 3 reflects the significant impacts of external factors on our budgeting forecasts. Across a number of projected capital spends for this financial year reflect the effects post-pandemic of higher costs, supply and labour shortages including contractors and consultants. The most sizeable variance has occurred in respect of the projected spend on the drawdown of the land at Manydown North and the accompanying infrastructure delivery. Negotiations with the freeholder are taking longer than expected, which is very disappointing, but it is paramount that the outcome supports a viable, good quality, deliverable scheme for the 3,400 new homes to be built by the 2 councils in partnership with Urban&Civic.
The revised capital programme is reflected in the new Medium Term Financial Strategy for 2023/24 to 2026/27
It is recommended that Cabinet note:
1. The forecast capital expenditure for 2022/23 of £23.867M which is £23.097M (49.18%) less than the latest approved budget at 31 December 2022 for the capital programme. Of this reported variance, £18.097M, or 78.35%, relates to slippage on the Manydown North scheme. 2. That the Capital Programme update approved by Council subsequently in February 2023 update the programme to take account of these variances. 3. The 2022/23 significant outturn forecast variations, and explanations for them, are shown in section 4. 4. The quarter three forecasts and the impact of scheme variances for 2022/23 on future years’ capital expenditure were reported to Council in February 2023. 5. The capital programme budget for 2022/23 has been profiled to show the period when the budget will be spent, so that progress on scheme delivery may be monitored more closely. Profiled budgets by Council Plan Priority and capital scheme are shown in section 5 and Appendix 2; 6. That expenditure to date against the quarter three profiled budget shows overall net slippage of £3.669M. 7. The latest forecast of capital receipts, grants and contributions for 2022/23 in section 6. 8. The risks associated with the capital forecasts are as detailed in section 9. 9. The latest approved capital programme for 2022/23 to 2025/26 and associated financing as shown in section 7, and detailed in Appendix 1; and 10. The capital programme remains fully funded from the council’s own resources up to 2025/26, based on the latest forecast of available resources. Background, Corporate Objectives and Priorities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.