T o approve a dditions to the capital programme to support the delivery of Council Plan Priorities as set out in section 9 of the report to fund: An increase to the Local Authority Housing Fund scheme of £1.392M in 2023/24; and New scheme May Place with a capital budget of £1.300M in 2024/25 and £0.800M in 2025/26.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Cabinet Council Date: 5 December 2023 14 December 2023 Subject: Quarter 2 Capital Monitoring Report as at 30 September 2023 Report of: Cllr Gavin James – Co-Leader and Cabinet Member for Finance and Property Lead Officer: Sue Cuerden – Executive Director of Corporate Services and Assets (S151 Officer) Contact Officer: Sue Cuerden – Executive Director of Corporate Services and Assets (S151 Officer) Tel No: 01256 845513 Email: [email protected] Adam Swain – Head of Financial Services and Commercialisation (Deputy S151 Officer) Tel No: 01256 845515 Email: [email protected] Sarah Finch – Accountancy Services Manager Tel No: 01256 845330 Email: [email protected]
Ward(s): All Key Decision: Yes Appendix 1: Latest Approved Capital Programme 2023/24 to 2026/27 Appendix 2: Capital Scheme Profiled Budgets 2023/24 It is recommended that Cabinet note:
1. The forecast capital expenditure for 2023/24 of £28.337M which is £1.904M (6.30%) less than the latest approved budget for the capital programme;
2. The 2023/24 significant outturn variations and explanations for them as shown in section 4;
3. The quarter two forecasts and impact of scheme variances for 2023/24 on future years’ capital expenditure were reported to the Capital Programme Board in November 2023;
4. The capital programme budget for 2023/24 has been profiled to show the period when the budget will be spent, so that progress on scheme delivery may be monitored more closely. Profiled budgets by Council Plan Priority and capital are shown in section 5 and Appendix 2;
5. The latest forecast of capital receipts, grants and contributions for 2023/24 in section 6;
6. The latest approved capital programme for 2023/24 to 2026/27 and it’s financing as shown in section 7 and detailed in Appendix 1;
7. The risks associated with the capital forecasts are as detailed in section 10; and
8. The capital programme remains fully funded from the council’s own resources up to 2026/27, based on the latest forecast of available resources.
It is recommended that Cabinet request Council to approve: 9. Additions to the capital programme to support the delivery of Council Plan Priorities as set out in section 9 to fund:
An increase to the Local Authority Housing Fund scheme of £1.392M in 2023/24; and New scheme May Place with a capital budget of £1.300M in 2024/25 and £0.800M in 2025/26.
Exempt or Confidential Information It is considered that information contained within this report and appendices does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public. Foreword – Cllr Gavin James Co-Leader and Cabinet Member for Finance and This report sets out the position on the council’s capital programme for the second quarter of 2023/24. The current forecast outturn for capital expenditure is £28.337M which is 6.30% less than the latest approved budgeted programme for the year.
I am pleased to see that there has been approvals for an additional £1.167M to be added to the programme in the year to support the delivery of Council Plan Priorities, with requests to increase the programme further by £3.492M in this report.
While the forecast expenditure for 2023/24 of £28.337M is a positive position, I recognise that current economic conditions are still challenging and this could have further impact on our capital projects, both in terms of budget control and delivery times.
It is positive that capital budget profiling is being utilised to improve financial management. This allows earlier identification where progress on scheme spend is delayed allowing deferment, rephasing into future years or cancellation and where appropriate, allowing a reprioritisation of funds.
Background, Corporate Objectives and Priorities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme Outturn for 2025/26Council note: 1) That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.