Note: 1) The forecast capital expenditure for 2023/24 of £20.369M which is £11.038M (35.14%) less than the latest approved budget for the capital programme; 2) The 2023/24 significant outturn variations and explanations for them as shown in section 4 of the report; 3) The quarter three forecasts and the impact of scheme variances for 2023/24 on future years’ capital expenditure were reported to the Capital Programme Board in January 2024; 4) The latest forecast of capital receipts, grants and contributions for 2023/24 in section 5 of the report; 5) The latest approved capital programme for 2023/24 to 2027/28 and it’s financing (approved by Council in February 2024) as shown in section 6 and detailed in Appendix 1 of the report; 6) The risks associated with the capital forecasts are as detailed in section 8 of the report; and 7) The capital programme remains fully funded from the council’s own resources up to 2027/28, based on the latest forecast of available resources.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Subject: Quarter 3 Capital Monitoring Report as at 31 December 2023 Report of: Cllr Gavin James – Co-Leader and Cabinet Member for Finance and Property Lead Officer: Sue Cuerden – Executive Director of Corporate Services and Assets (S151 Officer) Contact Officer: Sue Cuerden – Executive Director of Corporate Services and Assets (S151 Officer) Tel No: 01256 845513 Email: [email protected] Adam Swain – Head of Financial Services and Commercialisation (Deputy S151 Officer) Tel No: 01256 845515 Email: [email protected] Sarah Finch – Accountancy Services Manager Tel No: 01256 845330 Email: [email protected]
Ward(s): All Key Decision: No Latest Approved Capital Programme 2023/24 to 2027/28 Appendix 1: (Council February 2024) It is recommended that Cabinet note:
1. The forecast capital expenditure for 2023/24 of £20.369M which is £11.038M (35.14%) less than the latest approved budget for the capital programme;
2. The 2023/24 significant outturn variations and explanations for them as shown in section 4;
3. The quarter three forecasts and the impact of scheme variances for 2023/24 on future years’ capital expenditure were reported to the Capital Programme Board in January 2024;
4. The latest forecast of capital receipts, grants and contributions for 2023/24 in section 5;
5. The latest approved capital programme for 2023/24 to 2027/28 and it’s financing (approved by Council in February 2024) as shown in section 6 and detailed in Appendix 1;
6. The risks associated with the capital forecasts are as detailed in section 8; and
7. The capital programme remains fully funded from the council’s own resources up to 2027/28, based on the latest forecast of available resources.
Exempt or Confidential Information It is considered that information contained within this report and appendices does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public.
Foreword – Cllr Gavin James Co-Leader and Cabinet Member for Finance and Property
This report sets out the position on the council’s capital programme for the third quarter of 2023/24. The current forecast outturn for capital expenditure is £20.369M which is 35% less than the latest approved budgeted programme for the year.
The most significant variance has occurred in respect of the projected spend on the drawdown of the land at Manydown North and the accompanying infrastructure delivery.
The updated position is reflected in the revised capital programme for 2023/24 to 2027/28. Background, Corporate Objectives and Priorities
In accordance with the council’s Financial Procedure Rules, the Chief Financial Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.
The capital programme is reviewed on a quarterly basis in accordance with the council’s Capital Strategy. The forecast position is reported to the Capital Programme Board with a quarterly update reported to Cabinet and Council (for approval if required). This is only required to enable capital schemes in the programme to proceed and approve additions and changes to the programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.