Resolved
To approve additions to the capital programme of £0.300M to support the delivery of Council Plan Priorities as set out in section 8 of the report to fund a new capital scheme, Maritime House.
Council approved this item on Thursday 17 October 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
To approve additions to the capital programme of £0.300M to support the delivery of Council Plan Priorities as set out in section 8 of the report to fund a new capital scheme, Maritime House.
Cabinet / Council Date: 10 September / 17 October Subject: Quarter 1 Capital Monitoring Report as at 30 June 2024 Cllr Gavin James – Co-Leader and Cabinet Member for Report of: Finance and Property
Lead Officer: Chief Finance Officer (Section 151 Officer) Chief Finance Officer (Section 151 Officer) – Adam Swain [email protected] Contact Officer: Accountancy Manager (Deputy Section 151 Officer) – Sarah Finch – Tel 01256 845330 or email [email protected]
Ward(s): All Key Decision: Yes Appendix 1: Latest Approved Capital Programme 2024/25 to 2027/28
Exempt or Confidential Information It is considered that information contained within this report and appendix does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public.
Foreword – Cllr Gavin James Co-Leader and Cabinet Member for Finance and Property This report sets out the position on the council’s capital programme for the first quarter of 2024/25.
The current forecast outturn for capital expenditure is £35.035M which is £0.406M below the with the revised programme for the year. This is due to changes in the expected timing of a number of programmes which will result in delayed spend, offset by expenditure on another scheme being brought forward.
This position at quarter 1 reflects the work undertaken by officers to identify where progress on a scheme spend is delayed allowing deferment, rephasing into future years or cancellation and where appropriate, allowing a reprioritisation of funds.
I am pleased to see that there is a request for an additional £0.300M to be added to the programme in the year to support the delivery of Council Plan Priorities.
1 of 17 While this is a positive position, there remains challenges in terms of build cost inflation and supply chain issues. I recognise that this could have an impact on our capital projects, both in terms of budget control and delivery times.
Recommendation to Cabinet
It is recommended that Cabinet note:
1. The forecast capital expenditure for 2024/25 of £35.035M which is £0.406M lower that the latest agreed capital programme budget of £35.441M;
2. The 2024/25 significant outturn variations and explanations for them as shown in section 4;
3. The quarter one forecasts and impact of scheme variances for 2024/25 on future years’ capital expenditure;
4. The latest forecast of capital receipts, grants and contributions for 2024/25 in section 5;
5. The risks associated with the capital forecasts are as detailed in section 11;
6. The latest approved capital programme for 2024/25 to 2027/28 and the financing as shown in section 6 and detailed in Appendix 1; and
7. The capital programme remains fully funded from the council’s own resources up to 2027/28, based on the latest forecast of available resources.
It is recommended that Cabinet request Council to approve: 8. Additions to the capital programme of £0.300M to support the delivery of Council Plan Priorities as set out in section 8 to fund a new capital scheme: • Maritime House
Background, corporate objectives and priorities
In accordance with the council’s Financial Procedure Rules, the Chief Finance Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.
The capital programme is reviewed on a quarterly basis in accordance with the council’s Capital Strategy, with a quarterly update reported to Cabinet and Council (for approval if required). This is only required to enable capital schemes in the programme to proceed and approve additions and changes to the programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarter 1 Capital Monitoring Report as at 30 June 2024Report | 304 KB | DownloadRead as text |
Follow Council at Basingstoke and Deane and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Capital Programme Outturn for 2025/26Council note: 1) That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is ... | Agreed | Open |
| 16 Jul 2026 | Revenue Outturn Report 2025/26That Council approve: 1) The proposed transfer of the remaining outturn surplus of £1.51M after grant and income rese... | Approved | Open |
| 16 Jul 2026 | Treasury Management 2025/26 Annual ReportResolved that: The Treasury Management 2025/26 Annual Report be noted and the amendments to the Treasury Management S... | Noted | Open |
| 16 Jul 2026 | Old Basing and Lychpit Community Governance Review – Final RecommendationsResolved that: Council 1) Note the outcome of the consultations. 2) Agree the final recommendations for the Community... | Noted | Open |
| 16 Jul 2026 | Appointment of Interim S151 OfficerResolved : that Sarah Finch be appointed as Interim Section 151 Officer from 1 October 2026. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.