To agree 1) A budget virement of £5.365M from the Manydown Land and Infrastructure Funding Scheme to the Manydown Development scheme (2024/25 £2.365M and 2025/26 £3.000M). 2) The renaming and repurposing of The Malls Upgrading/Updating scheme to Town Centre Improvements.
Word for word from the decision Basingstoke and Deane published for this meeting.Source: democracy.basingstoke.gov.uk
Cabinet / Council Date: 10 December / 19 December 2024 Quarter 2 Capital Monitoring Report as at 30 September Subject: 2024 Cllr Gavin James – Co-Leader and Cabinet Member for Report of: Finance and Property Lead Officer: Chief Finance Officer (Section 151 Officer) Chief Finance Officer (Section 151 Officer) – Adam Swain [email protected] Contact Officer: Accountancy Manager (Deputy Section 151 Officer) – Sarah Finch – Tel 01256 845330 or email [email protected] Ward(s): All Key Decision: Yes Appendix 1: Latest Approved Capital Programme 2024/25 to 2027/28
Exempt or Confidential Information It is considered that information contained within this report and appendix does not contain exempt information under the meaning of Schedule 12A of the Local Government Act 1972, as amended, and therefore can be made public.
Foreword – Cllr Gavin James Co-Leader and Cabinet Member for Finance and Property This report sets out the position on the council’s capital programme for the second quarter of 2024/25.
The current forecast outturn for capital expenditure is £28.882M which is £6.859M below the latest approved programme for the year. This includes £3.232M relating to the Manydown development and £1.199M in respect of May Place, which leaves £2.428M due to changes in the expected timing of a number of programmes which will result in the rephasing of spend into later years, offset by expenditure on another scheme being brought forward.
While the forecast expenditure for 2024/25 of £28.882M is a positive position, there remains challenges in terms of build cost inflation and supply chain issues. I recognise that this could have an impact on our capital projects, both in terms of budget control and delivery times. Recommendation to Cabinet It is recommended that Cabinet note: 1. The forecast capital expenditure for 2024/25 of £28.882M which is £6.859M lower than the latest agreed capital programme budget of £35.741M; 2. The 2024/25 significant forecast outturn variations and explanations for them as shown in section 4; 3. The quarter two forecasts and impact of scheme variances for 2024/25 on future years’ capital expenditure; 4. The latest forecast of capital receipts, grants and contributions for 2024/25 in section 5; 5. The risks associated with the capital forecasts are as detailed in section 11; 6. The latest approved capital programme for 2024/25 to 2027/28 and the financing as shown in section 6 and detailed in Appendix 1; and 7. The capital programme remains fully funded from the council’s own resources up to 2027/28, based on the latest forecast of available resources.
It is recommended that Cabinet request Council to approve the following capital programme amendments as set out in paragraphs 1.7 and 1.8: 8. A budget virement of £5.365M from the Manydown Land and Infrastructure Funding Scheme to the Manydown Development scheme (2024/25 £2.365M and 2025/26 £3.000M). 9. The renaming and repurposing of The Malls Upgrading/Updating scheme to Town Centre Improvements.
Background, corporate objectives and priorities
In accordance with the council’s Financial Procedure Rules, the Chief Finance Officer (CFO) has a responsibility to provide financial information and to report on the overall budget position of the council. To provide assurances that the council’s budgets are well managed and maintained, regular budget monitoring is undertaken with variances and required actions reported.
The capital programme is reviewed on a monthly basis in accordance with the council’s Capital Strategy, with a quarterly update reported to Cabinet and Council for approval if required. This is only required to enable capital schemes in the programme to proceed and approve additions and changes to the programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programme Outturn for 2025/26Council note: 1) That the actual capital spending in 2025/26 was £16.281M as shown in Table 3 of the report. This is ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.