DECISION That the report of the Development & Assets Group Manager and Financial Services Group Manager be accepted. Reason: To update the Cabinet Executive of the current position regarding the Council’s Capital Programme for 2009/2010 and available capital resources.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
To inform members of the available capital resources and the progress of the Capital Programme for 2009/10
Recommendation
2.1That the report be accepted.
3. Reason for Decision Recommended
3.1To update the Cabinet Executive of the current position regarding the Council’s Capital Programme for 2009/10 and available capital resources.
4. Forward Plan
10/09 (046)
5. Key Decision
5.1Yes
6. Matters for Consideration
6.1The 2009/10 Capital Programme was formally approved by Council on 26th February 2009. The detailed programme, which is set out in Appendix A, amounted to an investment of £1.940m. There were a number of schemes brought forward from previous years, with the allocated funding.
In accordance with the Council’s Capital Strategy, the officer Asset Management Group is charged with constantly monitoring and reviewing progress on the capital programme, including those schemes brought forward from previous years, to seek to ensure that the resources available are deployed efficiently and effectively. Each capital project has an nominated project manager who is responsible for the delivery of the project.
6.2Capital Expenditure 2009/10
6.2.1 Appendix B gives details of the actual spending against budget for all schemes in the approved capital programme for the period 1st April 2009 to 30th September 2009. The table includes any in-year changes and any identified variations in project costs.
6.2.2 The overall position at 30th September is that actual expenditure of £716,719 has been incurred with additional commitments of £369,555 against an overall budget, including brought forwards and variations, of £3,447,721. This represents 31.5% of the proposed programme, and the Asset Management Group are monitoring the schemes closely to ensure completion by the end of the financial year.
6.2.3 The following schemes were highlighted to Cabinet Executive for potential withdrawal from the Capital Programme in January 2009 due to a lack of apparent progress.
Project Progress From Jan 2009 Blaby Joint Service Shop Scheme Withdrawn. Remodelling £54,500 Bouskell Park Ice House Scheme delayed in the Planning Stage Refurbishment £10,000 by English Heritage, everything possible has been completed by BDC staff. Narborough Park – Car Park Scheme complete. £15,000 Off Street Car Parking Scheme designed and committed. £20,000 Council Offices Energy Project suspended to support the Conservation £15,000 pending East Midlands Improvement & Efficiency Carbon Management Programme
Accordingly, progress on the above schemes is considered to be satisfactory and no projects are recommended for withdrawal.
6.2.4 One of the largest schemes within the programme is the new build of Thorpe Astley Community Centre with an overall allocation of £990,680. Work has now started on the site, and completion is expected by July 2010, with the majority of expenditure being incurred within this financial year.
6.2.5 Due to the timeline for Disabled Facilities Grants to be completed, commitments for work to be carried out have to be made some considerable time in advance and in order to facilitate this, an additional amount of £200,000 is shown against the Disabled Facilities Grants allocation for commitments to be raised for work due to be carried out in 2010/11. 6.3 Capital Resources The Council’s projected available capital resources are determined at the beginning of each financial year and a detailed breakdown of the resources required to support the programme are shown in Appendix C. The funding shown in Appendix C assumes that all schemes will be fully implemented.
Estimated Resources Carried Forward 6.3.1 The total resources carried forward into 2010/11are £701,010 but of this £659,384 is already committed or ring fenced as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.