RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the additional capital expenditure of £128,866 highlighted in paragraph 5 be formally authorised for inclusion in the Capital Programme. Reasons: 1. It is important that the Cabinet Executive and Council are kept informed of progress in meeting the Council’s capital investment programme for the financial year. 2. To ensure that any additions to the overall Capital Programme are formally approved by full Council in line with constitutional requirements.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
Progress against the 2016/17 Capital Programme was reported to Council on 7th November 2016. It was noted then that at 30th September 2016 the Council’s forecast capital expenditure for 2016/17 amounted to £6.548m, including £0.370m which is backed by Section 106 contributions.
Since then the main Capital Programme has increased by just £11,275, taking the total to £6.189m. In addition to this, however, in accordance with the November report, the sum of £8,000 has been transferred from the Green Space Strategy project to fund the purchase of 15 static cycles for the new Spinning Studio at the Pavilion. A further £4,000 has been redirected from the Pavilion Car Park project to enable the installation of air conditioning in the Dance Studio. These transfers do not affect the overall value of the Capital Programme.
In addition to this, a further £117,591 of Section 106 contributions have been allocated, taking the total Capital Programme to £6.677m.
The following table provides a summary of the Council’s latest capital expenditure commitments.
Approved Capital Programme 2016/17 – as per November report 6,547,700 Additions: Upgrade of IDOX system 12,500 Miscellaneous savings identified (1,225) 6,558,975 Additional S106 Contributions allocated to projects in last quarter 117,591 Revised Capital Programme 2016/17 6,676,566
The upgrade of the IDOX system relates to the Uniform database, Public Access system, and Document Management system used by the Planning and Economic Development Group. The current version of the system is no longer supported by IDOX and it is, therefore, imperative that we move to the latest version of the software. The additional cost can be met from the Special Schemes (Capital) Reserve.
4.2Main Capital Programme
Appendix A shows the actual expenditure against the budget for all schemes in the approved capital programme at the halfway point of the financial year. As at 30th December 2016 the Council has incurred expenditure of £4,568,854 against its planned Capital Programme of £6,189,206, excluding those schemes backed by S106 contributions. S106-backed schemes are covered in paragraph 4.3 below. This represents an underspend at the end of the third quarter of £1,620,352, or 26.2%%. The main reasons behind this significant variance are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.