RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the additional capital expenditure of £278,957 highlighted in paragraph 5 of the report, be formally authorised for inclusion in the Capital Programme. Reasons: 1. It is important that the Cabinet Executive is kept informed of progress in meeting the Council’s capital investment programme or the financial year. 2. To ensure that any additions to the overall Capital Programme are formally approved by full Council in line with constitutional requirements.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
Progress against the 2017/18 Capital Programme was reported to Council on 14th November 2017. It was noted then that at 30th September 2017 the Council’s forecast capital expenditure for 2017/18 amounted to £3,088,146, including £395,550 backed by Section 106 contributions.
Since then the main Capital Programme has increased by £60,359 and a further £218,598 S106 contributions have been allocated, taking the total Capital Programme to £3,367,103. In addition to this the sum of £8,410 has been transferred from the Fleet Replacement Programme to fund the purchase of an improved refuse vehicle CCTV recording system, and a further £8,000 has been redirected from the contingency to purchase a mobile/smarter working module for the IDOX Planning system. These two transfers do not affect the overall value of the Capital Programme.
The following table provides a summary of the Council’s latest capital expenditure commitments.
£ Approved Capital Programme 2017/18 – as per November report 3,088,146 Additions: Additional Disabled Facilities Grant Funding 52,806 Open Space Development Project increase 7,553 3,148,505 Additional S106 Contributions allocated to projects in last quarter 218,598 Revised Capital Programme 2017/18 3,367,103
Disabled Facilities Grants – the Government announced in the Autumn budget that it would be making an additional £42m available to local authorities in England. Whilst this funding is intended to be spent predominantly on home adaptions, it may also be used to support wider social care projects, with the proviso that it must be spent by 31st March 2018. Blaby has received £48,453 additional funding. A further £4,353 has also been allocated to Blaby in respect of unclaimed funding from other authorities which did not accept the Government’s offer of additional grant. This gives Blaby an additional £52,806 funding, and officers are currently exploring options for utilising this sum on projects which will comply with the Government’s grant conditions.
Open Space Development – unused revenue funding was utilised to allow pathways to be constructed and kissing gates installed at The Osiers.
4.2Main Capital Programme
Appendix A shows the actual expenditure against the budget for all schemes in the approved Capital Programme at the end of period 10 of the financial year. As at 31st January 2018 the Council has incurred capital expenditure of £1,424,320 against its planned Capital Programme of £2,752,955, excluding those schemes backed by S106 contributions. S106-backed schemes are covered in paragraph 4.3 below. This represents an underspend at the end of the January of £1,328,635, or 48%. The main reasons behind this significant variance are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.