DECISION That the report be accepted and the revisions to the 2010/11 capital programme and associated funding sources be approved. Reason: To update the Cabinet Executive of the current position regarding the Council’s capital investment programme during 2010/11 financial year.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1To provide the Cabinet Executive with an updated position on the progress of capital schemes during 2010/11 financial year.
Recommendation
2.1That the report be noted and the revisions to the 2010/11 capital programme and associated funding sources be approved.
3. Reason for Decision Recommended
3.1To update the Cabinet Executive of the current position regarding the Council’s capital investment programme during 2010/11 financial year.
4. Forward Plan
01/11(067)
5. Key Decision
5.1Yes
6. Matters for Consideration
6.1Progress on the 2010/11 Capital Programme was reported to Cabinet Executive on 8th November 2010. This report provides a further update including the likely outturn at year end.
6.2The Council’s capital investment programme represents an important element of the overall resources available to continue to improve the quality of services provided to the residents of the District. The annual programme is determined from capital bids which are required to reflect the priorities set out in the current Corporate Plan, Capital Strategy and Asset Management Plan.
6.3In accordance with the arrangements set out in the Capital Strategy an officer Asset Management Group oversees the development and monitoring of the capital programme. Each capital project has a nominated project manager who is responsible for the delivery of the project. Progress on the current year’s programme together with the committed schemes brought forward from previous years is reviewed by the Asset Management Group as part of the formal budget monitoring arrangements.
6.4In Appendix A to this report, the first table shows at summary level the overall 2010/11 Capital Programme, complete with estimated expenditure outturn for the year. The second table sets out the proposed sources of funding to meet the anticipated 2010/11 outturn expenditure of £3,004,502. The programme has been revised to take into account in-year changes to the projects and to reflect variations in project costs.
6.5The significant changes to the programme which have occurred since the report in November are set out below:
Due to the shortage of storage space within the IT computer network a project to increase the Council’s data storage capacity has been brought forward from the 2011/12 capital programme.
Due to the imminent expiry of the existing IT remote access fobs which form part of the business continuity arrangements the replacement of the fobs has been brought forward from 2011/12 capital programme.
Spend on Disabled Facilities Grants has now reached the 2010/11 limit. A facility has been made available to allow grants from the 2011/12 programme to be approved. However, no expenditure will be incurred until the new financial year.
The Circular walk project has not been able to proceed as anticipated with external funding being withdrawn. However, further consultations are ongoing with project partners in an attempt to allow this project to commence in the future.
6.6Appendix B gives a detailed project by project analysis of capital expenditure including the variances to both the brought forward and 2010/11 schemes
7. Other Relevant Considerations
7.1Human Rights Act 1998
Human rights have been considered but there are no overarching matters for concern in relation to this report.
7.2Legal Implications There are no legal implications
7.3Human Resources Implications
There are no human resources implications
7.4Risk Assessment & Business Continuity
7.5Equalities
No EINA is required for this report
8. Other Options Considered
8.1The option of proceeding with the current years capital programme without review and amendment could lead to a mismatch of resources and needs.
9. Appropriate Consultations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.