DECISION That a Community Infrastructure Levy Charging Schedule should not be progressed at this time and that a further review of the local potential to set a Charging Schedule will be undertaken in 12 months from the date of the report. Reasons: 1. The position in relation to the risks and benefits associated with a Community Infrastructure Levy (CIL) has not changed since November 2013; and Officers remain of the view that the reasons set out below for not adopting a levy remain unchanged: · The expected amounts which could be raised from development in the district would be relatively small; · The costs of setting up and administering a levy, in accordance with the Regulations, would be disproportionately high; · The introduction of a levy could lead to concerns within the development industry; at a time when there is strong developer interest in Blaby District; · Affordable housing provision could be compromised; · The Council is not well resourced for the direct delivery of new infrastructure. 2. In addition to the reasons above, there will be a general election in May 2015 which may result in a change of national policy in relation to CIL. Therefore it would be prudent to await the outcome of this.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1The purpose of this report is to enable Members to consider the current position in relation to Community Infrastructure Levy; following a report to Council in November 2013.
2. Recommendation to Council
2.1That a Community Infrastructure Levy Charging Schedule should not be progressed at this time and that a further review of the local potential to set a Charging Schedule will be undertaken in 12 months from the date of this report.
3. Reason for Decision Recommended
3.1The position in relation to the risks and benefits associated with a Community Infrastructure Levy (CIL) has not changed since November 2013; and officers remain of the view that the reasons set out below for not adopting a levy remain unchanged:
The expected amounts which could be raised from development in the district would be relatively small; The costs of setting up and administering a levy, in accordance with the Regulations, would be disproportionately high; The introduction of a levy could lead to concerns within the development industry; at a time when there is strong developer interest in Blaby District; Affordable housing provision could be compromised; The council is not well resourced for the direct delivery of new infrastructure.
3.2In addition to the reasons above, there will be a general election in May 2015 which may result in a change of national policy in relation to CIL. Therefore it would be prudent to await the outcome of this.
4. Forward Plan
4.1Yes, this report has been included on the Forward Plan.
5. Key Decision
5.1no, this is a matter reserved for Council.
6. Matters for Consideration
6.1What is the Community Infrastructure Levy?
6.1.1 The Community Infrastructure Levy (CIL) came into force in April 2010. It allows local authorities to raise funds from developers undertaking new building projects in their area, through charging a ‘tariff’. The money can then be used to fund a wide range of infrastructure that is needed as a result of development; such as new schools, improved roads, new open space, and leisure facilities among other things.
6.1.2 CIL was introduced to deliver the following benefits:
A faster and more transparent approach than the current system of securing planning obligations via S106 agreements. Increased certainly for developers ‘up front’ regarding contributions. Greater certainty over future funding for infrastructure.
6.2How can CIL be spent?
6.2.1 Local authorities are required to spend any funds raised through CIL on the infrastructure needed to support development in their area. All types of infrastructure can be included with the exception of affordable housing which is prohibited from inclusion within the regulations.
6.2.2 Authorities can also use funds to recover the costs of administering the levy; up to a total of 5%.
6.2.3 The Government requires authorities to allocate a meaningful proportion of funds raised in each neighbourhood (via development) back to that neighbourhood; to ensure that the local impacts of development can be managed effectively.
6.2.4 Developer contributions can still be secured through S106 agreements, which will remain the primary mechanism for securing affordable housing. Other infrastructure can continue to be included within S106 agreements; however it must be separate and distinct from anything which will be funded by CIL receipts.
6.3Setting the CIL charge
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.