DECISION That the report be noted and that the additional capital expenditure of £100,000, highlighted in paragraph 6.4, is authorised as an addition to the Capital Programme. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
1.1To inform Members of the progress of the Capital Programme 2014/15 and to gain approval for the addition of new schemes to the programme.
2. Recommendation to Council
2.1That the report is noted and that the additional capital expenditure of £100,000, highlighted in paragraph 6.4, is authorised as an addition to the Capital Programme.
3. Reason for Decision Recommended
3.1To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
4. Forward Plan
4.1Yes, this report has been included on the Forward Plan.
5. Key Decision
5.1Not applicable it is a matter for Council 6. Matters for Consideration
6.1Forecast expenditure on capital schemes in 2014/15 now amounts to £5.25m. The detailed programme on a scheme by scheme basis appears at Appendix A.
Since the original Capital Programme was approved by Council on 20th February 2014 there have been a number of additions including incomplete capital schemes carried forward from 2013/14. The table below provides a summary of the Council’s latest capital expenditure commitments.
£ Approved Capital Programme 3,640,182 Additions: Incomplete schemes carried forward from 2013/14 947,045 Pavilion Refurbishment Programme (approved by Council 16th September 367,000 2014) Upgrade BMX track at the Pavilion (approved by Council 22nd July 2014) 30,000 Section 106 Contributions (externally funded) 18,397 Customer Channel Shift (approved by Council 15th April 2014) 80,000 Hardware for implementation of Individual Electronic Registration (externally 10,959 funded) Parish Council Community Development Programme (externally funded) 1,963 Schemes funded from New Homes Bonus (approved by Council 19th 60,000 November 2013) Works to Offices in support of the People Strategy (see paragraph 6.4) 100,000 5,255,546 Net reduction in other capital schemes (4,073)
Revised Capital Programme 5,251,473
6.2Appendix A also shows the actual expenditure against budget for all schemes in the approved capital programme for the period 1st April 2014 to 30th September 2014. The overall position at 30th September 2014 is that actual expenditure of £587,346 has been incurred against the overall revised budget of £5,251,473, leaving an unspent balance of £4,664,127.
6.3As at 30th September 2014 the main variances are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.