CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Blaby District Council
Cabinet Executive, Monday 16 February 2015

Revised Capital Programme 2014/15

Noted Executive 2 papers

Cabinet Executive noted this item on Monday 16 February 2015. Below is the council's own wording, with the papers it was decided on.

Item254

Resolved

RECOMMENDATIONS TO COUNCIL 1. That the report be noted. 2. That the additional capital expenditure of £99,576 as highlighted in the report be formally authorised for inclusion in the Capital Programme. Reasons: 1. It is important that the Cabinet is kept informed of progress in meeting the Council’s capital investment programme for the financial year. 2. To ensure that any additions to the overall Capital Programme are formally approved by full Council in line with the constitutional requirements.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Background

Progress against the 2014/15 Capital Programme was last reported to Cabinet Executive on 3rd November 2014. It was noted then that at 30th September 2014 the Council’s forecast capital expenditure for 2014/15 amounted to £5.25m. Since then there have been a number of further schemes added leading to an increased Capital Programme total of £5.48m. 4.2 The following schemes have been added to the Capital Programme:

Refurbishment of Enderby Road Industrial Estate Units – funded £85,000 by way of a contribution from the General Reserve Fund

Depot Relocation – transfer of unused revenue budget in respect of £45,916 feasibility study

Increase in the Disabled Facilities Grants budget – funded by £37,936 contributions from East Midlands Homes

Play equipment, Oakfield Park, Blaby – funded by a S106 £56,640 contribution

Contribution to Blaby CCTV scheme – funded by revenue £5,000 contribution £230,492

The project for refurbishment of industrial estate units was reported to Council last July and has already been formally approved. This work is well underway and will enable the Council to generate additional rent income once the units are re-let.

Council has previously approved the sum of £80,000 to fund a feasibility study into the proposal to relocate the depot. Upon completion of the feasibility study £45,916 of this budget provision was left unspent. This has been used to supplement the Capital Programme as a contribution towards the design and build costs.

The remaining balance from the table above, £99,576, will require the formal approval of full Council in order for it to be included within the Capital Programme. All of this expenditure can be financed without any impact on General Fund Balances.

4.3Appendix A provides a detailed breakdown, scheme by scheme, of actual expenditure against the Capital Programme for the period 1st April 2014 to 31st December 2014. As at 31st December a total of £1,257,299 had been spent against the budget of £5,481,969, a variance of £4,224,670.

The main variances are:

 New Depot Site, Whetstone (£2,449,787) – the majority of the work undertaken to date relates to design, site surveys, and value engineering to assess the potential build costs. The Council has signed a pre- construction contract with Wates which commits us to £32,000 for work they have done on surveys and associated activity. There will be no significant construction costs until the new financial year, once the planning application has been considered on 5th March 2015. If successful the intention would then be to complete the lease of land from Leicestershire County Council.

 Pavilion Refurbishment Programme (£363,000) – the business plan was approved by Council in September 2014, and only limited expenditure had been incurred by 31st December. However, at that date contractual commitments amounted to almost £277,000. Building work is currently ahead of schedule and the project is expected to come in on budget.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Capital Programme 2014-15Appendix A 76 KB Download
PDF
Revised Capital Programme 2014/15Report 176 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
EF
Councillor E. F. WhiteLeader, present
AV
Councillor. A. V. Greenwood MBEDeputy Leader, present
FG
Councillor F. G. H JacksonMember, present
DF
Councillor D. FreerMember, apologies
TJ
Councillor T. J. RichardsonMember, present
SS
Councillor S. ScottMember, present
MA
Councillor M. A. WrightMember, present
SW
Mrs S. WhilesOfficer, in attendance
JT
Mrs J. TomanOfficer, in attendance
MA
Mr. M. AlflatOfficer, in attendance
CJ
Mr C. JonesOfficer, in attendance
SP
Mrs S. PennelliOfficer, in attendance

All 19 on the meeting page

On this subject at Blaby

Search all
  1. Revised Capital Programme 2014/15This decision
  2. Revised Capital Programme 2018/19Approved
  3. Revised Capital Programme 2018/19Decided
  4. Revised Capital Programme 2017/18Approved
  5. Revised Capital Programme 2017/18Decided
  6. Revised Capital Programme 2016/17Approved

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies