Cabinet Executive, Monday 7 November 2016

Revised Capital Programme 2016/17

Decided Executive 3 papers

Cabinet Executive decided this item on Monday 7 November 2016. Below is the council's own wording, with the papers it was decided on.

Item152

Resolved

RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the additional capital projects totalling £190,303, highlighted in paragraph 4.1, be authorised as additions to the Capital Programme. 3. That subject to completion of a full investment appraisal, and an additional £7,425 is added to the Capital Programme to facilitate the creation of a Spinning Studio. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Background

The Revised Capital Programme for 2016/17 amounts to £6.548m, including £0.370m which is backed by Section 106 contributions. The detailed programme, on a scheme by scheme basis, appears at Appendix A. The Section 106 contributions are shown separately to distinguish them from the main Capital Programme. Since the original Capital Programme was approved by Council on 18th February 2016 there have been a number of additions, including incomplete capital schemes brought forward from 2015/16. The following table provides a summary of the Council’s latest capital expenditure commitments.

£ Approved Capital Programme 2016/17 3,182,055 Additions: Incomplete schemes brought forward from 2015/16 (excluding S106) 2,632,537 th Demolition of Littlethorpe Depot (approved by Council on 20 September 167,582 2016) Additional costs in relation to construction of new depot (i) 41,426 Acquisition of new jet washer for depot (ii) 20,406 Furniture and racking for new depot (iii) 47,337 ICT and Audio Visual Equipment for new depot (iv) 24,653 Replacement Door Access Control System at Main Offices (v) 14,995 Grants to Parish Councils towards acquisition of ICT equipment th (approved by Council on 26 July 2016) 5,454 Enhancement of Noise Monitoring Equipment (vi) 1,418 Replacement cheque printer (vii) 4,000 Upgrade Financial Management System (viii) 30,000 Disabled Facilities Grants - additional government grant received (ix) 6,068 6,177,931 Add S106 Contributions allocated to projects in 2016/17 369,769 Revised Capital Programme 2016/17 6,547,700

The table above includes new projects with a total estimated cost of £190,303 which have been added to the Capital Programme either for reasons of an urgent nature or on the back of external funding becoming available. These additions require formal approval by Council in order to ratify their inclusion in the Capital Programme.

(i) Additional costs in relation to construction of new depot – £41,426. During the fit out stage of the project it was noted that certain elements of the design needed to be delivered differently to those initially included within the build programme. Additional costs include further electrical sockets within the office area, the design of jet wash screens in addition to the firming up of costs for items that were provisional sums within the original contract cost.

(ii) Jet Washer - £20,406. To replace the jet washer used to wash down operational vehicles.

(iii) Furniture and racking for new depot - £47,337. Under normal circumstances purchase of furniture and fixtures of this nature would be purchased periodically in smaller numbers and would be funded via the revenue budget. The furniture at the former depot has not been replaced for a considerable number of years, nor has there ever been a facility for all the operational staff to be seated in one area at the depot.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Capital Programme 2016-17Appendix A 63 KB Download
PDF
Revised Capital Programme 2016-17Appendix B 100 KB Download
PDF
Revised Capital Programme 2016/17Report 171 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
TR
Councillor Terry RichardsonLeader, present
MW
Councillor Maggie WrightDeputy Leader, present
LB
Councillor Lee BreckonMember, present
DF
Councillor David FreerMember, present
IH
Councillor Iain HewsonMember, present
GJ
Councillor Guy JacksonMember, present
SS
Councillor Sheila ScottMember, present
JT
Mrs Jane TomanOfficer, in attendance
MA
Mr Mark AlflatOfficer, in attendance
SP
Mrs Sarah PennelliOfficer, in attendance
CJ
Mr Colin JonesOfficer, in attendance
MF
Mark FooteOfficer, in attendance

All 21 on the meeting page

On this subject at Blaby

Search all
  1. Revised Capital Programme 2016/17This decision
  2. Revised Capital Programme 2018/19Approved
  3. Revised Capital Programme 2018/19Decided
  4. Revised Capital Programme 2017/18Approved
  5. Revised Capital Programme 2017/18Decided
  6. Revised Capital Programme 2016/17Approved

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies