Resolved
RECOMMENDATION TO COUNCIL That the latest Capital Programme totalling £6,416,825 be accepted. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
Cabinet Executive decided this item on Monday 15 February 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RECOMMENDATION TO COUNCIL That the latest Capital Programme totalling £6,416,825 be accepted. Reason: To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.
The original Capital Programme for 2020/21 was approved by Council on 17 th February 2020, and amounted to £3.59m. This included just under £1.1m in respect of the Fleet Vehicle Replacement Programme alone.
The following table shows the latest Capital Programme which now amounts to £6,416,825, taking into account £2.06m brought forward from 2019/20. Appendix A gives a complete breakdown of planned expenditure on a scheme by scheme basis, including how it will be resourced. £ Approved Capital Programme 2020/21 6,404,593
Additions: Installation of Electric Vehicle Charging Points 103,740
Less: Fosse Meadows – Flood and Access Works deferred to (16,000) 2021/22 Fosse Meadows – Footpath Upgrades deferred to 2021/22 (11,500)
HR & Payroll System deferred to 2021/22 (250,000)
6,230,833 Add S106 Contributions allocated to projects in 2020/21 185,992 Revised Capital Programme 2020/21 6,416,825
• The On-Street Residential Charge Point Scheme was approved at Cabinet on 27th October 2020. This project has now been added to the Capital Programme. The project is part of the Council’s Climate Change Strategy, and will help us to reduce transport based carbon emissions and improve air quality. • Budget of £16,000 in respect of Fosse Meadows Flood and Access Works and £11,500 budget in respect of Fosse Meadows footpath upgrades has been deferred to the 2021/22 Capital Programme due to the ground conditions and the impact of Covid-19. Fosse Meadows has proven to be our most popular park in the district resulting in an increase in visitors throughout the Pandemic using the open space for their daily exercise. Several inspections have been undertaken and due to the need to use plant and equipment for the works to be carried out, it has been deemed that the risk would be too high and it could have a detrimental impact on visitors to the park whilst the works are undertaken. • Budget of £250,000 for the HR & Payroll project has been deferred to 2021/22. The procurement is planned to commence once the eFinancials upgrade has been completed in order to ensure availability of resource. It is possible that the full budget will not be required, dependent upon the route to procurement and length of the implementation period. • S106 contributions allocated to projects has increased by £185,992, bringing the total to £861,239. 4.2 At the end of the third quarter of 2020/21, the Council had spent £1,685,717 against its planned Capital Programme, excluding Section 106 contributions, of £5,555,717. S106-backed schemes are covered in paragraph 4.3 below.
Members will be aware from the previous two quarterly reports that the outbreak of COVID-19 had heavily impacted a number of the Capital Projects from being carried out as planned.
Explanations for the main variances in Quarter 3 are as follows:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Q3 Capital programme review 2020-21Appendix A | 100 KB | Download |
PDF |
Quarter 3 Capital Programme Review 2020/21Report | 147 KB | DownloadRead as text |
Follow Cabinet Executive at Blaby and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... | Approved | Open |
| 21 Sep 2026 | Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... | Approved | Open |
| 21 Sep 2026 | Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... | Approved | Open |
| 21 Sep 2026 | Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... | Approved | Open |
| 29 Jun 2026 | Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.