RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2024/25, totalling £8,435,559, be accepted. Reasons: 1. To ensure that the Council has adequate resources in place to meet its capital expenditure commitments. 2. To reflect additions or other changes to the Capital Programme that have occurred in the 2 nd quarter of the year.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2024/25 was approved by Council on 27th February 2024 and amounted to £3,826,900, including a borrowing requirement of £1,665,938.
The revised Capital Programme following the 1st quarter of 2024/25 was approved in September 2024 and amounted to £8,449,878. The following table shows the latest Capital Programme which now amounts to £8,435,559. This includes £4,528,430 of unspent budget brought forward from 2023/24. Appendix A gives a scheme-by-scheme breakdown of the planned expenditure for 2024/25.
£ Approved Capital Programme 2024/25 8,449,878
New Additions 1. Fleet Vehicle Replacement Programme 178,328
Reductions 2. Installation of PV Panels at Enderby Leisure Centre (192,647)
Revised Capital Programme 2024/25 8,435,559
The reasons behind the additions and reductions highlighted in the table above are as follows:
Additions
1. Funding has been received from Defra to retrofit and electrify an existing refuse collection vehicle and the additional cost, although externally funded needs to be added to the capital programme.
2. The grant funding associated with the Installation of solar panels at the Enderby Leisure Centre has not been pursued given the grant conditions were unfavourable to the Council. An amount still remains in the capital programme to develop a scheme without utilising the Sport England funding stream.
4.2At the end of September 2024, the Council had spent £1,054,655 against its planned Capital Programme.
The reasons behind the main variances are as follows:
• Net Zero at the Depot - £1,175,587 planned spend not yet utilised: Planning permission has been granted and tendered costs have been received for the installation of solar panels at the depot. There are some minor stakeholder queries that have been raised which are currently being investigated, these are not foreseen to delay the works which are forecast to complete by March 2025. Appropriate infrastructure solutions for the Electric Vehicle infrastructure at the Council’s depot are currently being reviewed. Soft market testing will commence in early November which will be followed by a tender process.
• Fleet Vehicle Replacement Programme - £1,222,085 planned spend not yet utilised: The majority of budget is allocated for three new waste collection vehicles and the retrofitting of an existing refuse collection vehicle. Orders are to be placed for vehicles that are fuelled by diesel and HVO.
• IT Infrastructure Improvements - £941,772 planned spend not yet utilised: whilst the plans to move the IT to an in-house service are going well the expenditure to June 2024 has been limited. It is expected that the expenditure will increase during the second half of the year and the works are forecast to be completed by March 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.