RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2023/24, totalling £9,187,982, be accepted. Reasons: 1. To ensure that the Council has adequate resources in place to meet its capital expenditure commitments. 2. To reflect additions or other changes to the Capital Programme since it was approved by Council on 22nd February 2023, including the carry forward of unspent budget from 2022/23.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2022/23 was approved by Council on 22nd February 2023 and amounted to £3,618,500, including a borrowing requirement of £2,295,500.
After allowing for unspent budget carried forward from 2022/23 and other movements, the Capital Programme now stands at £9,187,982. The movements between the original value and the latest value are shown in the following table, whilst Appendix A gives a scheme-by-scheme breakdown of the planned expenditure for 2023/24.
£ Original Capital Programme – approved February 2023 3,618,500
New Additions 1. Incomplete schemes brought forward from 2022/23 5,349,204 2. Section 106 contributions added to projects in 2023/24 193,335 3. Installation of CCTV cameras at three sites across 26,000 district 4. Green Community Grants* 16,000
Reductions 5. Capital Grants Programme* (12,000) 6. Hardware for Individual Electoral Registration (3,057)
Revised Capital Programme 2023/24 9,187,982
*Illustrates a transfer of expenditure from one scheme to another.
The reasons behind the additions and reductions highlighted in the table above are as follows:
Additions
1. Reflects schemes that were not finalised at 31st March 2023 and budget provision, along with associated resources, was carried over into the new financial year to allow for them to be completed. This includes the £2.5m provision for strategic property investment which is subject to the identification of appropriate opportunities.
2. Section 106 monies received are only released and added to the Capital Programme as and when suitable schemes are identified by the Planning Obligations Monitoring Group, following receipt of bids from Parish Councils or other community groups.
3. Funded from the capital element of Blaby’s share of the UK Shared Prosperity Fund.
4. There was no budget provision in the Capital Programme for 2023/24 as it had been included as a one-year trial only. However, demand for grants towards eco-friendly capital grants continues to rise. To meet this demand, a budget has been created in 2023/24 by transferring £12,000 from the main Capital Grants Programme (see below) and £4,000 from the existing green revenue pot. There has been limited take-up of the green revenue budget and the main capital grants pot was underspent in 2022/23. The grants panel, therefore, proposed that existing revenue and capital grant budgets be redirected to where there is greater demonstrable need. 5. See above – transfer of funding to Green Community Grants.
6. This is the remaining budget made available by central government towards the implementation of Individual Electoral Registration several years ago, and which is no longer needed for the purposes for which it was originally intended. It is unlikely to be required to be repaid so will remain in the grants unapplied account pending allocation to a suitable project.
4.2Performance to date
At the end of June 2023, the Council had spent £899,929 against its planned Capital Programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.