RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2023/24, totalling £11,760,992, be accepted. Reasons: 1. To ensure that the Council has adequate resources in place to meet its capital expenditure commitments. 2. To reflect additions or other changes to the Capital Programme that have occurred in the 3rd quarter of the year.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The original Capital Programme for 2023/24 was approved by Council on 22nd February 2023 and amounted to £3,618,500, including a borrowing requirement of £2,295,500.
Since then, there have been a number of changes to the Capital Programme, including £5,349,204 brought forward from 2022/23. The following table shows the latest Capital Programme which now amounts to £11,760,992, (including S106 projects).
Appendix A gives a scheme-by-scheme breakdown of the planned expenditure for 2023/24.
£ Approved Capital Programme 2023/24 10,450,009
New Additions 1. Trenching works at Huncote Leisure Centre 29,965 2. Regeneration & Housing Property 760,000 3. ICT Security Upgrades 15,000 4. IT Infrastructure improvements 500,000 5. Fleet Vehicle Replacement Programme 164,861 6. Disabled Facilities Grants 21,367 7. CCTV cameras at 3 sites 5,000 8. Contaminated Land Works, Enderby 25,000 9. Southey Close Landfill Gas Remedial Works 25,000
Reductions 10. CCTV cameras, Blaby Town Centre and Narborough (40,000) Station 11. Refurbishment of vacant units at ERIE (12,210) 12. Car park improvements, Bouskell Park (200,000)
11,743,992 13. Add S106 Contributions allocated to projects in 2023/24 17,000 Revised Capital Programme 2023/24 11,760,992
The reasons behind the additions and reductions highlighted in the table above are as follows:
Additions
1. Trenching works at Huncote Leisure Centre - The Huncote Major Incident Reserve was increased to £600,000 by approval at Council in April 2022. Approval was given by Council on 25th October 2023 for additional budget to cover works necessary to enable the land fill gas to be released safely and prevent any build-up of gas beneath the Leisure Centre.
2. Regeneration & Housing Property - Approval was given at Council on 25th October 2023 to use the budget set aside for strategic investment for the purchase of 16 dwellings to reduce homelessness pressures. This followed the award of grant funding from the Local Authority Housing Fund. Although the expenditure budget has increased by £760,000, this is offset by the grant of £1,366,000 leading to a net reduction in our borrowing need.
3. ICT Security Upgrades – Additional budget has been required to cover costs for the Privilege Access Management element of the Security upgrade. There is the possibility that these costs may be achieved through a subscription rather than outright purchase. If it is confirmed, this element of the project would need to be treated as revenue expenditure and removed from the Capital Programme
4. IT Infrastructure improvements – The project budget is provisionally set and is pending the outcome of the options appraisal.
5. Fleet Vehicle Replacement Programme – Funding has been received from Defra towards the purchase of an Electric Sweeper.
6. Disabled Facilities Grants – The project budget has been increased to recognise the final allocation,
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.