Blaby District Council
Cabinet Executive, Monday 16 September 2024

Quarter 1 Capital Programme Review 2024/25

Approved Executive 2 papers

Cabinet Executive approved this item on Monday 16 September 2024. Below is the council's own wording, with the papers it was decided on.

Item86

Resolved

RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2024/25, totalling £8,362,558, be accepted. Reasons: 1. To ensure that the Council has adequate resources in place to meet its capital expenditure commitments. 2. To reflect additions or other changes to the Capital Programme since it was approved by Council on 27th February 2024, including the carry forward of unspent budget from 2023/24.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Cabinet Executive

Blaby District Council Cabinet Executive

Date of Meeting 16 September 2024 Title of Report Quarter 1 Capital Programme Review 2024/25 This is not a Key Decision and is on the Forward Plan Lead Member Cllr. Maggie Wright - Finance, People & Performance (Deputy Leader) Report Author Accountancy Services Manager Strategic Themes All Themes: Enabling communities and supporting vulnerable residents; Enhancing and maintaining our natural and built environment; Growing and supporting our economy; Keeping you safe and healthy; Ambitious and well managed Council, valuing our people

1. What is this report about?

1.1This report provides Members an update on expenditure against the Capital Programme for the first quarter of 2024/25.

2. Recommendation(s) to Cabinet Executive and Council

2.1That the report is accepted.

2.2That the latest Capital Programme for 2024/25, totalling £8,362,558, is accepted.

3. Reason for Decisions Recommended

3.1To ensure that the Council has adequate resources in place to meet its capital expenditure commitments.

3.2To reflect additions or other changes to the Capital Programme since it was approved by Council on 27th February 2024, including the carry forward of unspent budget from 2023/24.

4. Matters to consider

4.1Background The original Capital Programme for 2024/25 was approved by Council on 27th February 2024 and amounted to £3,826,900, including a borrowing requirement of £1,665,938.

After allowing for unspent budget carried forward from 2023/24 and other movements, the Capital Programme now stands at £8,362,558. The movements between the original value and the latest value are shown in the following table, whilst Appendix A gives a scheme-by-scheme breakdown of the planned expenditure for 2024/25.

£ Original Capital Programme – approved February 2024 3,826,900

New Additions 1. Incomplete schemes brought forward from 2023/24 4,528,430 2. Section 106 contributions added to projects in 2024/25 7,228 3. Revenues & Benefits - Document Management & 28,595 MyView*

Reductions 4. Replacement CRM/Granicus solutions* (13,595) 5. Income Management System* (15,000)

Revised Capital Programme 2024/25 8,362,558 *Illustrates a transfer of budget from one scheme to another.

The reasons behind the additions and reductions highlighted in the table above are as follows:

Additions

1. Reflects schemes that were not finalised at 31st March 2024 and budget provision, along with associated resources, was carried over into the new financial year to allow for them to be completed. This includes £1,176k provision for the installation of electric vehicle infrastructure at the Council Depot, with works due to commence as plans are finalised. The brought forward budget provision also includes £662k for strategic property investment which is subject to the identification of appropriate opportunities.

2. Section 106 monies received are only released and added to the Capital Programme as and when suitable schemes are identified by the Planning Obligations Monitoring Group, following receipt of bids from Parish Councils or other community groups.

3. The budget transfer is to enable the implementation of the new Revenues & Benefits document management system and set up of Citizens Access solution to enable resident’s self-service access to the Council’s service available to them. 4. See above – transfer of budget to Revenues & Benefits - Document Management & MyView

5. See above – transfer of budget to Revenues & Benefits - Document Management & MyView

4.2At the end of June 2024, the Council had spent £673,306 against its planned Capital Programme.

The reasons behind the main variances are as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring Statement to 30 June 2024Appendix A 53 KB Download
PDF
Quarter 1 Capital Programme Review 2024/25Report 156 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
TR
Councillor Terry RichardsonLeader, present
MW
Councillor Maggie WrightDeputy Leader, present
CC
Councillor Cheryl CashmoreMember, present
NG
Councillor Nigel GrundyMember, present
LP
Councillor Les PhillimoreMember, present
BT
Councillor Ben TaylorMember, present
JS
Julia SmithOfficer, in attendance
SP
Sarah PennelliOfficer, in attendance
LH
Louisa HortonOfficer, in attendance
MG
Marc GreenwoodOfficer, in attendance
CH
Caroline HarbourOfficer, in attendance
GM
Gary MorrisOfficer, in attendance

All 17 on the meeting page

On this subject at Blaby

Search all
  1. Quarter 1 Capital Programme Review 2024/25This decision
  2. Quarter 1 Capital Programme Review 2026-27Approved
  3. Quarter 3 Capital Programme Review 2025/26Approved
  4. Quarter 1 Capital Programme Review 2025/26Approved
  5. Quarter 3 Capital Programme Review 2024/25Decided
  6. Quarter 2 Capital Programme Review 2024/25Decided

More from Blaby Cabinet Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Quarter 1 Budget ReviewDECISIONS 1. That the financial performance against the budget for the quarter ending 30th June 2026 be accepted. 2. ... Approved Open
21 Sep 2026 Risk Management StrategyDECISION That the revised be adopted. Reasons: 1. The should be subject to regular review to ensure that it reflects ... Approved Open
21 Sep 2026 Quarter 1 Treasury Management Update 2026-27RECOMMENDATIONS TO COUNCIL 1. That the latest position in respect of treasury activities, and the prudential indicato... Approved Open
21 Sep 2026 Quarter 1 Capital Programme Review 2026-27RECOMMENDATIONS TO COUNCIL 1. That the report be accepted. 2. That the latest Capital Programme for 2026/27, totallin... Approved Open
29 Jun 2026 Update on Local Government Reorganisation and Establishment of voluntary Joint CommitteesDECISIONS 1. That the current position regarding Local Government Reorganisation in Leicester, Leicestershire and Rut... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies