RESOLVED that the report be accepted and Cabinet Members provided appropriate challenge to the financial outcomes in the report; continued to support appropriate financial control procedures agreed by Council; and noted the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding (Option 1).
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
Cabinet and Council only Date signed off by the Monitoring Officer: 21.02.25 Date signed off by the Section 151 Officer: 24.02.25
Committee: Cabinet Date of meeting: 5th March 2025 Report Subject: Capital Budget Monitoring, Forecast for 2024/2025 Financial Year (As at 31 December 2024) Portfolio Holder: Leader & Cabinet Member Corporate & Performance Report Submitted by: Corporate Director of Corporate Services
Reporting Pathway Directorate Executive Portfolio Governan Democrati Scrutiny Cabinet Council Other Management Team/Apoll Holder / ce & Audit c Services Committee (please Team o Chair Committee Committee state) 19/02/2025 19.02.25 19/02/20 05/03/2025 25 (briefing)
1. Purpose of the Report 1.1 To provide Members with an overview of each Portfolio’s actual and forecast capital expenditure against funding approvals for the 2024/2025 financial year, as at 31st December 2024.
2. Scope and Background 2.1 This report provides details on the following:
• Forecast financial position to 31st March 2025 across all portfolios. • Details of any significant adverse and/or favourable variances
2.2This report forms part of the councils financial reporting framework.
3. Options for Recommendation 3.1 Option 1 (Recommended Option) Members accept the report and • Provide appropriate challenge to the financial outcomes in the report. • Continue to support appropriate financial control procedures agreed by Council. • To note the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
3.2Option 2 Do not accept the report.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan 4.1 This report supports the Forward-Looking Corporate Plan 2022/27 as it ensures effective forward financial planning arrangements are in place to support the Council’s financial resilience. This is a key element to achieving “An ambitious and innovative council delivering quality services at the right time and in the right place”. 5. Implications Against Each Option 5.1 Impact on Budget (short and long term impact)
5.1.1 The current capital programme is approximately £74.9m and is funded by: -
WG Grant - £45m Other grant funding - £14.1m Council Resources - £15.8m
External grant funding has increased by £8m since quarter 2 and this is mainly due to additional WG grant of £4.09m for the New Welsh Primary School and £2m for the HIVE. Both these projects are experiencing significant additional costs following the change in contractor required as a consequence of the liquidation of the original contractor. Further detail is shown in Appendix 2 attached.
Across the programme, it is forecast that expenditure of £55m will be incurred on capital projects / schemes during 2024/25, with the remainder allocated for use in future years.
The overall financial position as forecast at 31st December 2024 indicates an overspend of £0.167m against a total in year capital budget of £54.8m.
The overall position across all Portfolios is shown below: -
Total Future In year Forecast Actual Forecast Approvals funding funding Expenditure Expenditure to to Variance Q2 31/12/2024 underspent 31/03/2025 (Month 9) / (Dec (overspent) 2024)
£000 £000 £000 £000 £000 £000
74,844 20,008 54,836 55,002 26,062 (167)
5.1.2 The report has identified two significant overspends within the Capital Programme.
Children’s Residential Homes - £151,848
Despite receiving additional grant funding for this project, escalating costs have resulted in a significant overspend. Fundamental issues have impacted upon the level of work required, timescales and ultimately costs
The project has been delayed and the contractor has notified an extension of 12 weeks for completion of the project. Funding options will need to be identified to mitigate the overspend.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.