RESOLVED that the report be accepted, and Option 1 be approved, namely: • Members provide appropriate challenge to the financial outcomes in the report; • Continue to support appropriate financial control procedures agreed by Council; and • Note the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
1.1To provide Members with an overview of each Portfolio’s actual and forecast capital expenditure against funding approvals for the 2024/2025 financial year, as at 30th September 2024.
2. Scope and Background
2.1This report provides details on the following:
• Forecast financial position to 31st March 2025 across all portfolios. • Details of any significant adverse and/or favourable variances
2.2This report forms part of the councils financial reporting framework.
3. Options for Recommendation
3.1Option 1 (Recommended Option)
Members accept the report and • Provide appropriate challenge to the financial outcomes in the report. • Continue to support appropriate financial control procedures agreed by Council. • To note the budgetary control and monitoring procedures in place within the Capital Team, to safeguard Authority funding.
3.2Option 2 Do not accept the report.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan 4.1 This report supports the Forward-Looking Corporate Plan 2022/27 as it ensures effective forward financial planning arrangements are in place to support the Council’s financial resilience. This is a key element to achieving “An ambitious and innovative council delivering quality services at the right time and in the right place”.
5. Implications Against Each Option
5.1Impact on Budget (short and long term impact)
5.1.1 The current capital programme is approximately £66m and is funded by: -
WG Grant - £38.2m Other grant funding - £11.7m Council Resources - £16.1m
It is forecast that expenditure of £54m will be incurred on capital projects / schemes during 2024/25, with the remainder allocated for use in future years.
The overall financial position as forecast at 30th September 2024 indicates an overspend of £0.160m against a total in year capital budget of £54m.
The overall position across all Portfolios is shown below: -
Total Future In year Forecast Actual Forecast Approvals funding funding Expenditure Expenditure to to Variance Q2 30/09/2024 underspent 31/03/2025 (Month 6) / (Sept (overspent) 2024)
£000 £000 £000 £000 £000 £000
66,058 12,060 53,997 54,157 20,791 (160)
5.1.2 The report has identified two significant overspends within the Capital Programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.