Education Capital Programme Contracts Committee, Tuesday 29 July 2014 at 5.00pm

Education Capital Programme Award of Contract - Garth Hill College

Decided Committee 1 paper

Education Capital Programme Contracts Committee decided this item on Tuesday 29 July 2014. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED That the contract for the construction works for the expansion of Garth Hill College be awarded to Tenderer A as set out in paragraph 23 of the Restricted Appendix A.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Education Capital Programme Contracts Committee

Purpose of report

1.1The purpose of the report is to seek approval to award the contract for construction works for the expansion of Garth Hill College under the Education Capital Programme previously approved by the Executive.

Recommendation

2.1That the contract for the construction works for the expansion of Garth Hill College be awarded to Tenderer A as set out in paragraph 23 of the Restricted Appendix A.

Reasons for recommendation

3.1The value of this contract requires Executive approval under the Council’s Contract Standing Orders.

3.1The recommended tender is affordable within the budget previously approved by the Executive.

Alternative options considered

4.1If Garth Hill College were not expanded then North Bracknell secondary pupils would need to be transported to schools in other parts of the Borough.

4.2Expansion of Garth Hill College will provide additional secondary school places for North Bracknell to address the forecast deficit until the new school at Blue Mountain is built.

5. SUPPORTING INFORMATION

Background

5.1The expansion of Garth Hill College forms part of the Education Capital Programme which was approved by the Executive in October 2013. It is also included in the School Capacity Strategy approved by the Executive in December 2013. The expansion will create 350 new school places at Garth Hill College, increasing the capacity from 1,620 to 1,970 and increasing the Published Admission Number from 270 to 312.

5.2In May 2014 the Executive agreed that Contract Standing Orders be waived to enable an executive committee, to be appointed by the Leader, to take the decision in relation to the award of contract for this project. Unrestricted

Post 16 Centre

5.3The expansion of Garth Hill College will be achieved by constructing a new stand alone Post 16 Centre in the north of the staff car park. The former Post 16 spaces and teaching spaces previously timetabled for Post 16 in the existing main building will then be freed up for expansion of Key Stages 3 & 4.

5.4The Post 16 Centre will be modular construction and the recommended contractor has been selected from the Government’s GPS Framework for modular buildings on the basis of best value for money through the Council’s established procurement and tender evaluation process.

Parking Drop-off and Pick-up

5.5This project also includes the acquisition of the Wick Hill car park which is accessed from Bull Lane. The car park will be retained for use by Garth hill College, and will also be managed to provide drop-off and pick-up facilities to mitigate the impact of vehicle movements at peak times. Additional parking spaces are also being provided within the main school site.

Timescales

5.6The works are due to commence on site in November 2014 for completion in June 2015. The programme is time critical due to DfE grant funding condition requiring the additional school places to be available from the start of the September 2015 academic year.

Costs and Funding

5.7Funding for this contract has already been approved by the Executive as part of the Education Capital Programme, and is drawn from a number of sources including DfE Basic Need Grant, DFE Targeted Basic Need grant and S106 contributions.

6. ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS

Borough Solicitor

6.1The estimated cost of the works exceeds the threshold for Public Works contracts, but the contract proposed to be awarded will be called off under the terms of a compliant framework agreement so that the requirements of the Public Contracts Regulations will be complied with

Borough Treasurer

6.2The Borough Treasurer is satisfied that sufficient resources have been allocated to this scheme to fund the contract award proposal and all other anticipated expenditure.

Equalities Impact Assessment

6.3All new construction will be designed in accordance with Building regulation Part M (Access to and Use of Buildings).

Strategic Risk Management Issues

6.4Are set out in the attached Restricted APPENDIX A Unrestricted

Consultation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Education Capital Programme Award of Contract: Garth Hill CollegeReport 32 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 4 attended
DG
Councillor Dr Gareth Barnard CONCommittee Member, apologies
DB
Councillor Dale Birch CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
AW
Councillor Alan Ward CONChair, present

On this subject at Bracknell Forest

Search all
  1. Education Capital Programme Award of Contract - Garth Hill CollegeThis decision
  2. Education Capital Programme - Great Hollands Primary School ExpansionDecided
  3. Education Capital Programme - Cranbourne Primary School Award of ContractApproved
  4. Education Capital Programme - Owlsmoor Primary School Award of ContractDecided
  5. Education Capital Programme - The Brakenhale School Award of ContractAgreed
  6. Education Capital Programme - The Pines Primary School Award of ContractDecided

More from Bracknell Forest Education Capital Programme Contracts Committee

All decisions
MeetingDecisionOutcome
9 Sep 2014 ChairmanRESOLVED that Councillor Birch be elected to chair the meeting. Decided Open
9 Sep 2014 Education Capital Programme - Owlsmoor Primary School Award of ContractRESOLVED that the contract for the construction works for Phase 3 of the expansion of Owlsmoor Primary School be awar... Decided Open
29 Jul 2014 Election of ChairmanRESOLVED that Councillor Ward be appointed Chairman of the Committee. Decided Open
29 Jul 2014 Education Capital Programme - The Brakenhale School Award of ContractIt was agreed that contingency funding be added to the risk section. RESOLVED that the contract for the construction ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies