RESOLVED that the award of contract for the construction works for the expansion of Great Hollands Primary School be awarded to Tenderer F, as detailed in the restricted appendix to the Director of Children, Young People and Learning’s report, subject to the final lump sum not exceeding the amount set out in paragraph 19 of the Restricted Appendix .
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The purpose of the report is to approve the award the contract for the construction works for the expansion of Great Hollands Primary School under the Education Capital Programme previously approved by the Executive.
Recommendation
2.1That the Executive approves the award of contract for the construction works for the expansion of Great Hollands Primary School to Tenderer F subject to the final lump sum not exceeding the amount set out in paragraph 19 of the attached Restricted Appendix.
Reasons for recommendation
3.1The value of this contract requires Executive approval under the Council’s Contract Standing Orders.
Alternative options considered
4.1Great Hollands was one of eleven South Bracknell primary schools considered for expansion by the Education Capital Programme Board in 2014 and it was selected because of the schools with sufficient site area, it had a “Good” rating at Ofsted and the estimated cost was affordable.
4.2A feasibility study was then undertaken of Great Hollands to identify different options for the expansion of the school buildings which has been subject to consultation and agreement with the Headteacher and Governing Body.
4.3Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
5. SUPPORTING INFORMATION
Background
5.1This project is for the expansion of Great Hollands Primary school by 1 Form of Entry (FE), from 2FE to 3FE, or expansion by 210 places from 420 to 630 places. The Published Admission Number (PAN) will increase from 60 to 90, and the school nursery for 52 places will be retained and relocated within the site as part of the works. Unrestricted
5.2This project forms part of the Education Capital Programme previously approved by the Executive in February 2015, and is also set out in the school Capacity Strategy approved by the Executive in December 2014.
5.3The project was raised in response to the School Places Plan 2014-19, which forecast a shortfall of primary school places in South Bracknell, and this will enable the Council to meet its statutory duty to provide sufficient pupil places across this organisational area.
5.4The scheme as designed will provide all of the additional classrooms, teaching and associated spaces required through four phases of construction including new build extension and internal refurbishment.
5.5Phase 1 was completed in August 2015 to enable the expansion to commence from September 2015 and falls outside the scope of this report. The award of contract in this report is in respect of all of the remaining works in Phases 2-4 required to complete the expansion in all year groups.
Timescales
5.7The programme for the works is for a start on site in February 2016, with handover and commissioning of the last phase of work in April 2018. The works will be completed on a phased basis, with three distinct sections of work.
Costs and Funding
5.8This contract will be let subject to Executive approval in February 2016 of the balance of the funding required as part of the 2016/17 Education Capital Programme from DfE Basic Need Grant.
6. ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1No significant legal issues arise from the matters discussed in this report.
Borough Treasurer
6.2Subject to approval of the 2016-17 capital programme, the Borough Treasurer is satisfied that sufficient resources exist within confirmed Basic Needs Grant allocations to fund the proposed contract ward.
Equalities Impact Assessment
6.3All new construction will be designed in accordance with Building regulation Part M (Access to and Use of Buildings).
Strategic Risk Management Issues
6.4Are set out in the attached Restricted APPENDIX A Unrestricted
Consultation
Principal Groups Consulted
7.1The Headteacher, Governing Body, staff, pupils, parents and neighbours of Great Hollands Primary School.
Method of Consultation
7.2The Headteacher and Governors have been consulted throughout the design process via meetings and workshops held at the school.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.