Education Capital Programme - Owlsmoor Primary School Award of Contract
DecidedCommittee1 paper
Education Capital Programme Contracts Committee decided this item on Tuesday 9 September 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the contract for the construction works for Phase 3 of the expansion of Owlsmoor Primary School be awarded to Tenderer A subject to the final lump sum not exceeding the amount set out in paragraph 26 of the Restricted Appendix.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Report to Education Capital Programme Contracts Committee
Purpose of report
1.1The purpose of the report is to seek approval to award the contract for the construction works for the final Phase 3 of the expansion of Owlsmoor Primary School under the Education Capital Programme previously approved by the Executive.
Recommendation
2.1That the contract for the construction works for Phase 3 of the expansion of Owlsmoor Primary School be awarded to Tenderer A subject to the final lump sum not exceeding the amount set out in paragraph 26 of the Restricted Appendix.
Reasons for recommendation
3.1The value of this contract requires Executive approval under the Council’s Contract Standing Orders.
Alternative options considered
4.1A masterplan was undertaken to identify different options for the expansion of the school buildings which has been subject to consultation and agreement with the Headteacher and Governing Body.
4.2Doing nothing is not an option because the Council has a statutory duty to provide sufficient pupil places.
5. SUPPORTING INFORMATION
Background
5.1The expansion of Owlsmoor Primary school from 2.5FE to 3FE for a total of 630 places forms part of the Education Capital Programme approved by the Executive in October 2013 and is also set out in the school Capacity Strategy approved by the Executive in October 2012.
5.2Through the School Places Plan, a shortfall of places has been identified in Crowthorne & Sandhurst, and the project to expand Owlsmoor Primary school from a Published Admission Number (PAN) of 76 to 90 has been initiated to need to meet the Council’s statutory duty to provide sufficient pupil places to meet rising rolls.
5.3A masterplan scheme was originally developed in 2010 to raise the school to a PAN of 90, and this forms the basis of the project. The works will provide the additional classrooms, teaching and associated spaces, through a series of extensions and internal alterations to create the additional capacity required. Unrestricted
5.4The expansion is being completed in three phases, and Phases 1 and 2 were completed in 2012 and 2013 respectively. This report is in respect of the final Phase 3 works to complete the expansion to 3FE in all year groups.
Owlsmoor Phase 3
5.5The final Phase 3 works include the demolition of the existing nursery block and construction of new reception classrooms, a nursery classroom and the additional classrooms to bring the school up to three forms of entry in all year groups.
5.6Pupil numbers have already justified the expansion of the school which was full to its Published Admission Number of 90 in September 2012 and is forecast to be full again to 90 for September 2014, and in the foreseeable future.
Timescales
5.7The programme for the Phase 3 Works is for a start on site in September 2014, with handover and commissioning in August 2015. The works will be completed on a phased basis, with three distinct sections of work.
Costs and Funding
5.8Initial funding for this contract has already been approved by the Executive as part of the Education Capital Programme, and is drawn from a number of sources including DfE Basic Need Grant and DFE Targeted Basic Need grant.
5.9Taking account of the total funding allocated to date on schemes developing school places, in order to fully finance this contract and other costs associated with this scheme, there will need to be a commitment to use £0.710m of the 2015-16 DfE Basic Need grant which has already been confirmed at £3.477m and will be released when the Council agrees the 2015-16 capital programme in February 2015. Planned expenditure on this scheme in the current year can be managed through the cash flow within the school places programme.
6. ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1The value of the works is below the OJEU threshold and the Public Contracts regulations are not engaged. Nothing further to add to this report.
Borough Treasurer
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Education Capital Programme Contracts Committee at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.