Council Wide Support Services Transformation Project

Agreed Executive 3 papers

Executive agreed this item on Tuesday 14 March 2017. Below is the council's own wording, with the papers it was decided on.

Item79

Resolved

RESOLVED that the Business Case be endorsed and agreed the Implementation Plan proposed for the ‘Do’ Phase of the Council Wide Support Services Review.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Transformation Programme

Project Title: Council Wide Support Services

‘Do’ Phase

Implementation Plan

Issue Date: January 2017

1 1 Introduction .................................................................................................................... 3 2 Project Approach ............................................................................................................ 3 3 Work Breakdown Structure............................................................................................. 5 4 Project Workstreams/Sub Projects ................................................................................. 5 5 Deliverables ................................................................................................................... 7 6 Project Quality Strategy .................................................................................................. 8 7 Financial Plan................................................................................................................. 9 8 Milestone Table .............................................................................................................. 9 9 Project Plan ..................................................................... Error! Bookmark not defined.

2 1 Introduction This document has been produced to capture and record the basic information needed to implement the project in the ‘Do’ phase. The plan addresses the following aspects:

 Project approach describing the key elements of the project  Work breakdown structure where there are several work streams or sub-projects.  Details of activities within each work stream, including resources required, cost and duration.  Details of the specific deliverables expected from the project, including which outcomes the deliverables are supporting.  Quality assurance details.  Project budget.  Milestone table.  Summary project schedule. (A full project gantt chart will also be developed)

When approved by the Project Board this plan will provide the “Baseline” for the implementation. Any changes should be subject to change control. Any changes to this document must be carried out using a Change Management process and agreed by the Project Board.

2 Project Approach

This project will follow the commissioning cycle of Analyse, Plan, Do, Review.

Early in the project an engagement plan will be produced which will include looking at the extent of cultural change that will be required and identifying the depth of engagement that will be required.

Challenge will be provided by a Challenge Director and Challenge Officers on the project board and the external advisors. The analyse and plan phases will also look at models in other organisations and engage with the market to look at innovative ideas for service delivery.

The analyse and plan phases will be carried out looking at all services in scope. The implementation is likely to require a number of different work streams depending on the sourcing solution selected.

The Analyse phase will involve working with staff from each support service to confirm current performance and costs, map out current processes and collate any existing benchmark data. This phase will also confirm the scope of the project, what the strategic requirements are for support services and what delivery models are available, looking at how support services are delivered in other organisations, what the market can provide and what benefits these models have brought to the organisations which use them. The phase will include mapping current high level customer journeys to establish how support services are accessed and received. The results of this activity will be developed into an outcome framework and an outline business case. This phase is likely to take 8 weeks and a gateway review at the end of the phase will confirm that the phase has looked at the correct areas and that the outcomes are realistic, achievable and will deliver what the organisation requires.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
8. b CWSSImplementationPlan2Report 452 KB DownloadRead as text
PDF
8.a CWSSPlanPhaseBusinessCase2Report 1.1 MB Download
PDF
Council Wide Support Services Transformation ProjectReport 210 KB Download

At this meeting

Whole meeting

Who was there

7 of 9 attended
PB
Councillor Paul Bettison OBE CONChair, apologies
DG
Councillor Dr Gareth Barnard CONVice-Chair, in the Chair, present
DB
Councillor Dale Birch CONCommittee Member, present
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
PH
Councillor Peter Heydon CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
CT
Councillor Chris Turrell CONCommittee Member, present
PP
Priya PatelClerk, expected

On this subject at Bracknell Forest

Search all
  1. Council Wide Support Services Transformation ProjectThis decision
  2. Restructure of Council Wide Support Services - Employment ImplicationsNoted

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies